Emission Limits and Work Practice Standards
Table 2
Operating Limits for Boilers and Process Heaters With Particulate Matter Emission Limits
Table 3
Operating Limits for Boilers and Process Heaters With Mercury Emission Limits and Boilers and Process
Heaters That Choose To Comply With the Alternative Total Selected Metals Emission Limits
Table 4
Operating Limits for Boilers and Process Heaters With Hydrogen Chloride Emission Limits
Table 5
Performance Testing Requirements
As stated in s.
NR 462.05 (3), you shall comply with the following requirements for performance testing for existing, new or reconstructed affected sources:
-
See PDF for table
a All test methods from Appendix A to
40 CFR part 60 listed in this column are incorporated by reference in s.
NR 484.04(13), (15) and (20m), all ASTM standard test methods listed in this column are incorporated by reference in s.
NR 484.10., and ASME PTC 19, Part 10 (1981) is incorporated by reference in s.
NR 484.11 (6) (b).
Table 6
Fuel Analysis Requirements
As stated in s.
NR 462.05 (4), you shall comply with the following requirements for fuel analysis testing for existing, new or reconstructed affected sources:
-
See PDF for table
a All ASTM standard test methods in this column are incorporated by reference in s.
NR 484.10. All SW-846 test methods in this column are incorporated by reference in s.
NR 484.06 (4) (e).
Table 7
Establishing Operating Limits
Table 8
Demonstrating Continuous Compliance
Table 9
Reporting Requirements
NR 462.07 History
History: CR 05-116: cr.
Register November 2006 No. 611, eff. 12-1-06.