ATCP 93.550(1)(e)
(e) The owner shall have a revised tank registration, form TR-WM-137, and part A of the department's tank system service and closure assessment report, form TR-WM-140, completed and submitted to the department within 21 business days of changing a tank system to storage of a non-regulated substance.
ATCP 93.550 Note
Note: Form TR-WM-137 - Underground Flammable/Combustible/Hazardous Liquid Storage Tank Registration, and form TR-WM-140 – Tank System Service and Closure Assessment Report are available from the Bureau of Weights and Measures, PO Box 8911, Madison, WI 53708-8911, or at telephone (608) 224-4942, or from the Bureau's Web site at
https://datcp.wi.gov/Pages/Programs_Services/PetroleumHazStorageTanks.aspx.
ATCP 93.550(1)(f)
(f) The change in service shall occur within 60 days after in-use or temporarily out of service status is terminated.
ATCP 93.550(2)
(2) When a tank system that held a non-regulated substance undergoes a change in service to store a regulated substance, all applicable requirements of this chapter apply upon placing the tank system into service. These requirements include precision tightness testing for the liquid-containing portion and tightness testing for the ullage portion.
ATCP 93.550 History
History: CR 17-092: cr.
Register October 2019 No. 766, eff. 11-1-19; correction in (1) (d) made under s.
35.17, Stats.,
Register October 2019 No. 766.
ATCP 93.560(1)(a)(a) At least 5 business days before beginning permanent closure of a tank system, the owner or operator or designee shall notify the authorized agent or the department of the intended closure on form TR-WM-121, except a shorter notification period is permitted where unexpected closure is commenced upon finding adverse conditions during a corrective action conducted under s.
ATCP 93.585.
ATCP 93.560(1)(b)
(b) Any date or time changes to the original submitted notification form, TR-WM-121, shall be requested at least one business day prior to the original date or time. The new date or time must be later than the original date or time.
ATCP 93.560(2)(a)
(a) To permanently close an underground tank system, the owner or operator shall have the tank and piping emptied and cleaned, by removing all liquids and accumulated sludge, and shall remove the tank and piping from the site unless allowed otherwise under par.
(e). Tanks that are removed shall be scrapped unless reused in accordance with s.
ATCP 93.350 (3) (i) or
93.500 (3) (c).
ATCP 93.560(2)(am)
(am) Tank basin and piping trench excavation shall be left open until inspector approves backfilling and tank and piping must remain onsite until inspector approves removal.
ATCP 93.560 Note
Note: For guidance in complying with the tank-cleaning requirements in API standard 2015, as listed on line 17 of Table 93.200-2, API publishes RP 2016, Guidelines and Procedures for Entering and Cleaning Petroleum Storage Tanks, which is available from API at the address listed in the table.
ATCP 93.560(2)(d)
(d) When an underground tank system is closed, or when a previously closed tank system is removed under sub.
(4), the owner shall have a revised tank registration, form TR-WM-137, and part A of the department's tank-system service and closure assessment report, form TR-WM-140, completed and submitted to the department within 21 business days of closure or removal.
ATCP 93.560 Note
Note: Form TR-WM-137 — Underground Flammable/Combustible/Hazardous Liquid Storage Tank Registration, and form TR-WM-140 – Tank System Service and Closure Assessment Report are available from the Bureau of Weights and Measures, PO Box 8911, Madison, WI 53708-8911, or at telephone (608) 224-4942, or from the Bureau's Web site at
https://datcp.wi.gov/Pages/Programs_Services/PetroleumHazStorageTanks.aspx.
ATCP 93.560(2)(e)
(e) Underground tanks systems may be closed in-place by filling with an inert, solid material, after emptying and cleaning, if the department determines, upon written request from the owner or operator, that one or more of the following conditions exist:
ATCP 93.560(2)(e)1.
1. Excavation would impact the structural integrity of an adjacent building or structure.
ATCP 93.560(2)(e)4.
4. Unauthorized encroachment would occur onto neighboring property under different ownership.
ATCP 93.560(2)(e)8.
8. Excavation would necessitate the permanent disconnection or relocation of underground utilities.
ATCP 93.560 Note
Note: Closing a tank in-place does not exempt the tank from tank-system site assessment requirements.
ATCP 93.560(2)(f)
(f) The department's Tank System Service and Closure Assessment Report form, TR-WM-140, shall be filled out by the certified remover and provided to the certified tank system inspector at the closure inspection.
ATCP 93.560(3)
(3)
Tank-system site assessment. A tank-system site assessment shall be performed in accordance with ss.
ATCP 93.575 to
93.585 after notifying the authorized agent or the department but before closing a tank system in place, installing a new system, or backfilling the tank basin and the piping trenches.
ATCP 93.560 Note
Note: The department and the department of natural resources share jurisdiction over tank closures and tank-system site assessments. The DNR must be notified if a release is discovered.
ATCP 93.560(4)(a)
(a)
General. When directed by the department, the owner or operator of any tank system closed in-place before December 22, 1988, shall have the system removed in accordance with this section and have the tank basin assessed in conformance with s.
ATCP 93.580.
ATCP 93.560(4)(b)
(b)
Systems previously closed without solid, inert fill. The owner or operator of any tank system that was closed before October 1, 1971, without removing the tank from the site but by filling the tank with water, shall bring the closed system into compliance with sub.
(2) within a time period established by the department on a case-by-case basis, except that the tank-system site assessment in s.
ATCP 93.580 is not required unless there is a suspected or obvious release. Written documentation shall be provided to prove closure with water before September 1, 1971.
ATCP 93.560 Note
Note: Before September 1, 1971, ch. Ind 8 — Flammable and Combustible Liquids Code allowed UST systems to be filled with water when closed or abandoned in-place.
ATCP 93.560(4)(c)
(c)
Other tank systems. Empty or improperly closed or abandoned tank systems that do not meet the requirements of sub.
(2) or the exemption under par.
(b) shall be permanently closed in accordance with all of the provisions of this section.
ATCP 93.560 History
History: CR 17-092: cr.
Register October 2019 No. 766, eff. 11-1-19; correction in (2) (c), (e) (intro.) made under s.
35.17, Stats.,
Register October 2019 No. 766.
ATCP 93.565(1)(1)
General. Tank systems that are abandoned with or without product shall be closed within 60 days of non-compliance with s.
ATCP 93.545 or in-use tank system requirements.
ATCP 93.565(2)
(2)
Exceptions. Abandoned tank systems that are less than 30 years old or of double-wall construction may be returned to service if they all of the following conditions:
ATCP 93.565(2)(b)1.1. The integrity of a fiberglass tank shall be assessed and certified by the manufacturer or a qualified professional engineer. The assessment shall include an internal inspection and certification that the tank is suitable for continued service.
ATCP 93.565(2)(b)2.
2. The integrity assessment of a steel tank shall be performed in accordance with API 1631.
ATCP 93.565(2)(b)2.a.
a. Tanks that have an overall average tank metal thickness or an average tank thickness of a designated thin wall area of less than 75 percent or any through-wall perforations shall be immediately closed per s.
ATCP 93.560.
ATCP 93.565(2)(b)2.b.
b. Tanks that have an overall average tank metal thickness or an average tank thickness of a designated thin wall area of 75 percent to 85 percent shall have an impressed current system installed per s.
ATCP 93.520 or be immediately closed per s.
ATCP 93.560.
ATCP 93.565(2)(b)2.c.
c. The certification and report of the assessment shall be submitted to the department for approval prior to adding product to the tank.
ATCP 93.565(2)(b)5.
5. A complete underground tank system functionality verification shall be conducted per s.
ATCP 93.510 (2). Form TR-WM-139 documenting the verification shall be submitted to the department.
ATCP 93.565(2)(b)6.
6. The tank system shall fully comply with this chapter before being placed back into service, except double-wall construction is not newly required for tank systems installed before February 1, 2009.
ATCP 93.565(2)(b)7.
7. The tank system shall pass a department storage tank system inspection conducted in accordance with this chapter.
ATCP 93.565 History
History: CR 17-092: cr.
Register October 2019 No. 766, eff. 11-1-19; (1) (title) created under s.
13.92 (4) (b) 2., Stats., and correction in (2) (intro.), (b) 1., 7. made under s.
35.17, Stats.,
Register October 2019 No. 766.
ATCP 93.570
ATCP 93.570 Conditions indicating a release. The owner or operator of a storage tank system shall follow the procedures in s.
ATCP 93.575 when any of the following conditions exist or when ordered to do so by the department:
ATCP 93.570(1)
(1)
Operating conditions. Unusual operating conditions exist, such as erratic behavior of product dispensing equipment, loss of product from the tank system, an unexplained presence of water in the tank, or water or product in the interstitial space of a secondarily contained system.
ATCP 93.570 Note
Note: Significant damage to equipment would be considered to be an unusual operating condition that could result in needing to perform the assessments specified in s.
ATCP 93.575.
ATCP 93.570(2)
(2)
Monitoring results. Results from a leak detection method, including an alarm, indicate that a release may have occurred.
ATCP 93.570(3)
(3)
Off-site impacts. Off-site impacts appear, such as the presence of contaminated soils or free product, dissolved phase product or vapors in soils, basements, sewer or utility lines, or nearby waters of the state.
ATCP 93.570(4)
(4)
Inventory verification. Inventory verification results indicate that a required method of leak detection has failed.
ATCP 93.570 History
History: CR 17-092: cr.
Register October 2019 No. 766, eff. 11-1-19.
ATCP 93.575
ATCP 93.575 Tank-system integrity assessment. ATCP 93.575(1)(1)
General. The owner or operator shall assess all suspected or obvious releases in accordance with sub.
(2) within 7 business days of discovery of any of the conditions described in s.
ATCP 93.570, unless any of the following conditions occur:
ATCP 93.575(1)(a)
(a) System equipment or the monitoring device is found to be defective and is immediately repaired, recalibrated or replaced, and additional monitoring does not confirm the initial result.
ATCP 93.575(1)(b)
(b) Inventory control is the method of leak detection, as allowed by s.
ATCP 93.510 (3) (d), and the data is reevaluated using an additional 7 days of data, and the reevaluation does not show a loss.
ATCP 93.575(2)
(2)
Assessment. The owner or operator shall evaluate and confirm all suspected or obvious releases by taking one or all of the following actions and shall also do so in accordance with any corresponding directive of the department:
ATCP 93.575(2)(a)2.
2. For UST systems with secondary containment, the owner or operator shall have the integrity of the interstitial space tested in accordance with one of the following, to determine whether a breach of the interstitial space has occurred:
ATCP 93.575(2)(a)2.a.
a. Requirements developed by the manufacturer, if the manufacturer has developed testing requirements.
ATCP 93.575(2)(a)2.b.
b. An approved standard developed by a nationally recognized association or independent testing laboratory.
ATCP 93.575(2)(a)2.c.
c. Requirements determined by the department to be no less protective of human health and the environment than the requirements listed in this subdivision.
ATCP 93.575(2)(b)
(b)
Tank-system site assessment. The owner or operator shall have the site assessed for the presence of a release in accordance with s.
ATCP 93.580.
ATCP 93.575 History
History: CR 17-092: cr.
Register October 2019 No. 766, eff. 11-1-19.
ATCP 93.580(1)(1)
General. When a tank-system site assessment is required by this chapter, or when directed by the department, the owner or operator shall have the site evaluated for the presence of a suspected or obvious release in accordance with sub.
(3).
ATCP 93.580 Note
Note: An “obvious release” means there is an indication of a release, and there is both environmental evidence, such as soil discoloration, observable free product, or odors — and a known source, such as a tank or piping with cracks, holes or rust plugs, or leaking joints. A “suspected release” means either of the following: (a) There is an indication that a tank system has leaked — such as inventory losses; observable free product or evidence of free product in secondary containment at dispensers, submersible pumps or spill buckets; petroleum odors; or leak detection alarm system activation — but there is no observable environmental evidence of a release; or (b) There is observable environmental evidence of a release, such as soil discoloration or free product, but the source is unknown.
ATCP 93.580(2)
(2)
Exemption from assessment. A tank system site assessment is required for the following tank systems or components only if there is a suspected or obvious release:
ATCP 93.580(2)(a)
(a) Tanks which have a capacity of less than 4,000 gallons and which stored heating oil for consumptive use on the premises where stored.
ATCP 93.580(2)(b)
(b) Tanks located at a private residence or on a farm premises, which have a capacity of less than 1,100 gallons, and which stored fuel for dispensing into motorized vehicles.
ATCP 93.580(2)(c)
(c) The closure of double-wall pipe when modification or upgrading is conducted on a system that will remain in operation, unless the piping is to be closed in-place.
ATCP 93.580(2)(d)
(d) Where the entire tank system, including the connections at the tank and dispensers, has been placed in liquid-tight secondary containment for the entire operational life of the system.
ATCP 93.580(3)(a)
(a)
General. When a tank-system site assessment is required, the owner or operator shall have a certified tank-system site assessor document field observations and sample for the presence of a release wherever contamination is identified or is most likely to be present at the tank site. If the assessor discovers obvious contamination, he or she shall complete the appropriate assessment sampling, such as for the entire system; or for only the tank, or piping, or sumps, or dispensers, and complete the documentation and reporting in its entirety. All sampling, documentation, and reporting under this paragraph shall be in a format prescribed by the department.
ATCP 93.580 Note
Note: The sampling documentation and reporting prescribed by the department is contained in
Tank System Site Assessment: A Guide to the Assessment and Reporting of Suspected or Obvious Releases from Underground and Aboveground Storage Tank Systems available from the department's Web site at
https://datcp.wi.gov/Documents/TSSA.pdf.
ATCP 93.580 Note
Note: In s.
ATCP 93.585, releases are required to be reported to the department of natural resources. Failure to notify the DNR of a release may have serious consequences – such as forfeitures under s.
168.26, Stats., of $10 to $5,000 for each violation. Each day of continued violation is a separate offense, and under s.
ATCP 93.180, each tank that is in violation is a separate offense.
ATCP 93.580(3)(b)
(b)
Exception. A person who is not a certified tank-system site assessor may perform assessments if directly supervised by a certified tank-system site assessor who is on the site during the entire assessment.