AB820,14 24Section 14 . 84.062 (5) (a) 2. d. of the statutes, as created by 2019 Wisconsin
25Act 9
, is repealed.
AB820,15
1Section 15. 84.062 (5) (a) 2. f. of the statutes is created to read:
AB820,6,32 84.062 (5) (a) 2. f. The design-builder or a member has been in business for at
3least 12 months.
AB820,16 4Section 16 . 84.062 (5) (a) 2. h. of the statutes, as created by 2019 Wisconsin
5Act 9
, is amended to read:
AB820,6,86 84.062 (5) (a) 2. h. The design-builder can provide information to the technical
7review committee
upon request about ownership, management, and control of the
8design-builder.
AB820,17 9Section 17 . 84.062 (5) (a) 2. i. of the statutes, as created by 2019 Wisconsin Act
109
, is amended to read:
AB820,6,1311 84.062 (5) (a) 2. i. The design-builder or a member has not been debarred from
12any government contracts and has not been found to have committed tax avoidance
13or evasion in any jurisdiction in the previous 10 5 years.
AB820,18 14Section 18 . 84.062 (5) (a) 2. k. of the statutes, as created by 2019 Wisconsin
15Act 9
, is amended to read:
AB820,6,2016 84.062 (5) (a) 2. k. No design professional employed by the design-builder or
17a member or who is assigned to the design-build project and no design professional
18that the design-builder will contract with for the design-build project has been
19disciplined in any jurisdiction in the previous 5 years under a license that is currently
20in use.
AB820,19 21Section 19 . 84.062 (5) (b) of the statutes, as created by 2019 Wisconsin Act 9,
22is amended to read:
AB820,6,2423 84.062 (5) (b) The office department shall advertise the request for
24qualifications.
AB820,20 25Section 20 . 84.062 (5) (c) of the statutes is created to read:
AB820,7,5
184.062 (5) (c) The technical review committee shall certify at least 2 but not
2more than 5 design-builders as qualified responsible bidders. If the department does
3not receive at least 2 responses to the request for qualifications or if the technical
4review committee certifies only one design-builder as a qualified responsible bidder,
5the department may re-advertise or cancel the project.
AB820,21 6Section 21 . 84.062 (5) (d) of the statutes is created to read:
AB820,7,97 84.062 (5) (d) In making determinations under this subsection, the technical
8review committee may not consider whether a design-builder or member exercised
9legal rights specified in statute or rule or under a contract with the department.
AB820,22 10Section 22 . 84.062 (6) (a) 11. of the statutes, as created by 2019 Wisconsin Act
119
, is amended to read:
AB820,7,1212 84.062 (6) (a) 11. Amount of stipend, if any.
AB820,23 13Section 23 . 84.062 (6) (a) 14. of the statutes is created to read:
AB820,7,1714 84.062 (6) (a) 14. A requirement that the design-builder perform not less than
1530 percent of the construction services under the contract with labor provided by
16employees of the design-builder or member and equipment owned or rented by the
17design-builder or member.
AB820,24 18Section 24 . 84.062 (6) (b) of the statutes is created to read:
AB820,7,2119 84.062 (6) (b) The technical review committee shall evaluate each technical
20proposal, which may include a confidential interview, and shall assign points in
21accordance with the request for proposals and subject to all of the following:
AB820,7,2522 1. For a project that will be awarded as either a low bid design-build contract
23or a fixed price variable scope design-build contract, the technical review committee
24shall determine whether technical proposals are responsive to the request for
25proposals without ranking or scoring the proposals.
AB820,8,10
12. For a project that will be awarded as a best value design-build contract, the
2technical review committee shall determine whether technical proposals are
3responsive to the request for proposals and score each responsive technical proposal
4as required by the request for proposals. The technical review committee may award
5not more than 20 percent of the points awarded to a technical proposal based on the
6design-builder's qualifications and ability to design, contract, and deliver the project
7in accordance with any deadline established in the request for proposals. The
8technical review committee may award a technical proposal not less than 25 percent
9and not more than 60 percent of the maximum number of combined points that may
10be awarded to a technical proposal and cost proposal.
AB820,25 11Section 25 . 84.062 (6) (c) of the statutes is created to read:
AB820,8,1512 84.062 (6) (c) The department shall allow design-builders to include
13alternative technical concepts and value engineering changes in their proposals by
14describing the process for submission and evaluation of alternative technical
15concepts and value engineering changes in the request for proposals.
AB820,26 16Section 26 . 84.062 (6) (d) of the statutes is created to read:
AB820,8,2217 84.062 (6) (d) The technical review committee may not consider a proposal
18responsive unless the proposal includes a conceptual design, critical path method,
19bar schedule of the work to be performed or similar schematic, design plans and
20specifications, technical reports, and all other information required by the request
21for proposals. The technical review committee may not consider any price or fee
22included in the technical proposal.
AB820,27 23Section 27 . 84.062 (6) (e) of the statutes is created to read:
AB820,9,224 84.062 (6) (e) The department shall notify the design-builder for each proposal
25that is determined to be responsive under par. (b) that the design-builder may

1submit a cost proposal under par. (7). The department shall reject all proposals that
2are determined to be nonresponsive under par. (b).