AB820,3,119
84.062
(2) (a) The department shall administer a program for design-build
10projects
. The department may not designate a project as a design-build project
11unless the department is able to clearly define the scope of work.
AB820,8
12Section 8
. 84.062 (2) (b) of the statutes is created to read:
AB820,3,2213
84.062
(2) (b) The department shall award 6 design-build contracts every 6
14years, beginning on the effective date of this paragraph .... [LRB inserts date].
15During each 6-year period, the department shall award at least one low bid
16design-build contract, one best value design-build contract, and one fixed price
17variable scope design-build contact and 3 additional contracts that may be any
18combination of low bid design-build, best value design-build, and fixed price
19variable scope design-build contracts. The combined cost of the 6 design-build
20contracts awarded under this paragraph in each 6-year period may not exceed
21$250,000,000 and the combined cost of all low bid design-build contracts awarded
22under this paragraph in each 6-year period may not exceed $25,000,000.
AB820,9
23Section 9
. 84.062 (2) (c) of the statutes is created to read:
AB820,4,224
84.062
(2) (c) For each project designated under par. (a), the department shall
25solicit requests for qualifications, requests for proposals, and cost proposals as
1provided in this section and, subject to sub. (7) (c) and (d), let each project by contract
2to a qualified responsible bidder.
AB820,10
3Section 10
. 84.062 (2) (d) of the statutes is created to read:
AB820,4,154
84.062
(2) (d) No more than 6 months following the completion of a
5design-build project designated under this subsection, the department shall prepare
6a report, with input from the design-builder and the technical review committee,
7detailing the project, the decision to designate the project as a design-build project,
8the type of design-build contract let, and recommendations for statutory changes,
9if any. The department shall provide this report to the transportation projects
10commission, the joint committee on finance, and the senate and assembly standing
11committees having jurisdiction over transportation matters. The senate and
12assembly standing committees having jurisdiction over transportation matters shall
13schedule a hearing on the report not more than 30 days following distribution of the
14report by the chief clerks of the senate and the assembly. This paragraph does not
15apply to projects awarded after December 31, 2026.
AB820,11
16Section 11
. 84.062 (3) of the statutes is created to read:
AB820,4,1917
84.062
(3) Technical review committee. (a)
The secretary shall appoint 5
18individuals to a technical review committee to evaluate proposals submitted under
19this section. The committee shall consist of the following:
AB820,4,2020
1. Three employees of the department.
AB820,4,2421
2. Two individuals who are not employees of the department and who are
22chosen in compliance with a memorandum of understanding entered into by the
23department with a state association of architectural, engineering, or design
24companies and a state association of transportation construction companies.
AB820,5,5
1(b) The secretary may not appoint to the technical review committee any person
2associated, as defined in s. 19.42 (2), with a design-builder. No person appointed to
3the technical review committee may review proposals under this section when the
4proposed project could benefit the appointee or the appointee's immediate family, as
5defined in s. 19.42 (7).
AB820,5,76
(c) A person appointed to the technical review committee is an agent of the
7department under s. 895.46.
AB820,5,98
(d) Except as otherwise provided in this section, all records of the technical
9review committee are open to public inspection and copying under s. 19.35 (1).
AB820,12
10Section 12
. 84.062 (4) of the statutes is created to read:
AB820,5,1711
84.062
(4) Selection. The department shall solicit design-build proposals in
122 phases. In the first phase, the department shall solicit requests for qualifications
13under sub. (5) and requests for proposals under sub. (6). The technical review
14committee shall certify responsible bidders as provided in sub. (5) (c) and shall score
15technical proposals as provided in sub. (6) (b). In the 2nd phase, the department shall
16solicit cost proposals and the technical review committee shall evaluate cost
17proposals as provided in sub. (7).
AB820,5,2320
84.062
(5) (a) 1. a. The design and construction experience of the
21design-builder or member, personnel, and contractors who will manage the design,
22engineering, and construction aspects of the project.
The department may not
23require a level of experience that will unreasonably restrict competition.
AB820,15
1Section
15. 84.062 (5) (a) 2. f. of the statutes is created to read:
AB820,6,32
84.062
(5) (a) 2. f. The design-builder or a member has been in business for at
3least 12 months.
AB820,6,86
84.062
(5) (a) 2. h. The design-builder can provide information
to the technical
7review committee upon request about ownership, management, and control of the
8design-builder.
AB820,6,1311
84.062
(5) (a) 2. i. The design-builder or a member has not been debarred from
12any government contracts and has not been found to have committed tax avoidance
13or evasion in any jurisdiction in the previous
10
5 years.
AB820,6,2016
84.062
(5) (a) 2. k. No design professional employed by the design-builder or
17a member
or who is assigned to the design-build project and no design professional 18that the design-builder will contract with
for the design-build project has been
19disciplined in any jurisdiction
in the previous 5 years under a license that is currently
20in use.
AB820,6,2423
84.062
(5) (b) The
office
department shall advertise the request for
24qualifications.
AB820,20
25Section 20
. 84.062 (5) (c) of the statutes is created to read:
AB820,7,5
184.062
(5) (c) The technical review committee shall certify at least 2 but not
2more than 5 design-builders as qualified responsible bidders. If the department does
3not receive at least 2 responses to the request for qualifications or if the technical
4review committee certifies only one design-builder as a qualified responsible bidder,
5the department may re-advertise or cancel the project.
AB820,21
6Section 21
. 84.062 (5) (d) of the statutes is created to read:
AB820,7,97
84.062
(5) (d) In making determinations under this subsection, the technical
8review committee may not consider whether a design-builder or member exercised
9legal rights specified in statute or rule or under a contract with the department.
AB820,7,1212
84.062
(6) (a) 11. Amount of stipend
, if any.
AB820,23
13Section 23
. 84.062 (6) (a) 14. of the statutes is created to read:
AB820,7,1714
84.062
(6) (a) 14. A requirement that the design-builder perform not less than
1530 percent of the construction services under the contract with labor provided by
16employees of the design-builder or member and equipment owned or rented by the
17design-builder or member.
AB820,24
18Section 24
. 84.062 (6) (b) of the statutes is created to read:
AB820,7,2119
84.062
(6) (b) The technical review committee shall evaluate each technical
20proposal, which may include a confidential interview, and shall assign points in
21accordance with the request for proposals and subject to all of the following:
AB820,7,2522
1. For a project that will be awarded as either a low bid design-build contract
23or a fixed price variable scope design-build contract, the technical review committee
24shall determine whether technical proposals are responsive to the request for
25proposals without ranking or scoring the proposals.
AB820,8,10
12. For a project that will be awarded as a best value design-build contract, the
2technical review committee shall determine whether technical proposals are
3responsive to the request for proposals and score each responsive technical proposal
4as required by the request for proposals. The technical review committee may award
5not more than 20 percent of the points awarded to a technical proposal based on the
6design-builder's qualifications and ability to design, contract, and deliver the project
7in accordance with any deadline established in the request for proposals. The
8technical review committee may award a technical proposal not less than 25 percent
9and not more than 60 percent of the maximum number of combined points that may
10be awarded to a technical proposal and cost proposal.
AB820,25
11Section 25
. 84.062 (6) (c) of the statutes is created to read:
AB820,8,1512
84.062
(6) (c) The department shall allow design-builders to include
13alternative technical concepts and value engineering changes in their proposals by
14describing the process for submission and evaluation of alternative technical
15concepts and value engineering changes in the request for proposals.
AB820,26
16Section 26
. 84.062 (6) (d) of the statutes is created to read:
AB820,8,2217
84.062
(6) (d) The technical review committee may not consider a proposal
18responsive unless the proposal includes a conceptual design, critical path method,
19bar schedule of the work to be performed or similar schematic, design plans and
20specifications, technical reports, and all other information required by the request
21for proposals. The technical review committee may not consider any price or fee
22included in the technical proposal.
AB820,27
23Section 27
. 84.062 (6) (e) of the statutes is created to read:
AB820,9,224
84.062
(6) (e) The department shall notify the design-builder for each proposal
25that is determined to be responsive under par. (b) that the design-builder may
1submit a cost proposal under par. (7). The department shall reject all proposals that
2are determined to be nonresponsive under par. (b).
AB820,29
5Section 29
. 84.062 (7) of the statutes is created to read:
AB820,9,106
84.062
(7) Cost proposals. (a) Design-builders notified under sub. (6) (e) may
7submit a cost proposal and the proposal shall include a fixed cost of design,
8engineering, and construction services prepared by a design professional that
9contains all design, engineering, construction, and quality assurance and quality
10control costs of the project.
AB820,9,1611
(b) The technical review committee may open cost proposals only after the
12technical proposals have been reviewed as provided in sub. (6). At the time and place
13specified in the request for proposals, the technical review committee shall open cost
14proposals, read the proposals aloud, and, for a project that will be awarded as a best
15value design-build contract, make public the committee's scoring of the technical
16proposals.
AB820,9,1817
(c) Following a review of cost proposals, the department may issue a notice of
18intent to award a contract, subject to all of the following:
AB820,9,2119
1. For a low bid design-build contract, the contract shall be awarded to the
20qualified responsible bidder that submitted a responsive technical proposal and also
21submitted the lowest responsive cost proposal.
AB820,9,2422
2. For a fixed price variable scope design-build contract, the contract shall be
23awarded to the qualified responsible bidder that submitted a responsive technical
24proposal and that submitted a responsive cost proposal that provides the maximum
1amount of services for the maximum fixed price set by the department or for an
2amount that is less than the maximum fixed price.
AB820,10,143
3. For a best value design-build contract, the contract shall be awarded to the
4qualified responsible bidder with the highest adjusted score, which shall be
5calculated by adding the bidder's technical proposal score to the bidder's cost
6proposal score. The technical review committee shall award the lowest qualified
7responsible bidder the maximum number of points that may be awarded to a cost
8proposal under the request for proposals, but not less than 40 percent and not more
9than 75 percent of the maximum number of combined points that shall be awarded
10to a technical proposal and cost proposal. For each remaining qualified responsible
11bidder, the technical review committee shall calculate the score for the cost proposal
12by reducing the maximum number of points that may be awarded to the cost proposal
13by 1 percent for each percentage point by which the cost proposal exceeds the lowest
14cost proposal.
AB820,10,2315
(d) Following a review of cost proposals, the department may reject all
16proposals. If the department rejects all proposals or does not execute a contract after
17issuing an intent to award a contract under par. (c), the department may reissue the
18request for proposals and allow only the qualified responsible bidders originally
19notified under sub. (6) (e) to submit new proposals. The department shall pay a
20reasonable stipulated fee to each design-builder that provides a responsive but
21unsuccessful proposal in response to the reissued request for proposals. If the
22reissued request for proposals specifies a maximum fixed price, the department may
23not award a stipend to a design-builder whose proposal exceeds that price.
AB820,11,3
1(e) Not less than 5 working days prior to executing a design-build contract, the
2department shall provide notice to each unsuccessful qualified responsible bidder
3that a notice of intent to award a contract has been issued.
AB820,30
4Section 30
. 84.062 (8) of the statutes is created to read:
AB820,11,55
84.062
(8) Contract award. (a) In this subsection:
AB820,11,86
1. “Construction services” means work necessary to construct a project,
7including trucking services and materials purchased regardless of whether the
8materials are installed by the design-builder.
AB820,11,119
2. “Specialty services” means work related to sanitary sewer systems, water
10main systems, staking, electrical, landscaping and erosion control, traffic control,
11signing, pavement marking, fencing, and other work identified by the department.
AB820,11,1612
(b) No later than 10 days following the issuance of a notice of intent to award
13a design-build contract, the department shall verify that the design-builder will
14perform not less than 30 percent of the construction services under the contract with
15labor provided by employees of the design-builder or member and equipment owned
16or rented by the design-builder or member.
AB820,11,1917
(c) The design-builder shall submit to the department in the form prescribed
18by the department documentation of the construction services the design-builder or
19members will perform and the dollar value of the services.
AB820,12,220
(d) The department shall calculate the percentage of total construction services
21identified in the contract to be performed by the design-builder or members by
22subtracting the value of specialty services to be performed from the total contract
23amount and dividing the dollar value of construction services to be performed by the
24design-builder or members by the difference. If the value of construction services
25to be performed by the design-builder or members is less than 30 percent of the value
1of all construction services required under the contract, the department shall cancel
2the contract award.
AB820,31
3Section 31
. 84.062 (11) of the statutes is created to read:
AB820,12,64
84.062
(11) Stipulated fee. (a) The department shall award a stipulated fee
5of not less than three-tenths of 1 percent of the department's estimated cost of design
6and construction as follows:
AB820,12,107
1. To each qualified responsible bidder that provides a responsive but
8unsuccessful proposal when the department issues a notice of intent to award a
9contract. If the request for proposals specifies a maximum fixed price, the
10department may not award a fee to a proposal that exceeds the maximum fixed price.
AB820,12,1211
2. To all qualified responsible bidders that provide a responsive proposal, if the
12department does not issue a notice of intent to award a contract.
AB820,12,1413
3. To all qualified responsible bidders if the department cancels the solicitation
14before the technical review committee reviews technical proposals.
AB820,12,1815
(b) The department shall pay the fee to each qualified responsible bidder under
16par. (a) no later than 90 days after the department issues a notice of intent to award
17a contract, determines that it will not issue a notice of intent to award a contract, or
18cancels the solicitation.
AB820,12,2319
(c) In consideration for paying the fee, the department may use work product
20contained in an unsuccessful proposal in connection with any proposed or awarded
21design-build project without making any additional compensation to the
22design-builder. If an unsuccessful design-builder waives the stipulated fee, the
23department may not use work product in the design-builder's unsuccessful proposal.
AB820,32
24Section 32
. 84.062 (13) of the statutes is created to read:
AB820,13,7
184.062
(13) Appeals. (a) Any person aggrieved and directly affected by a
2decision of the department to issue a request for qualifications or a request for
3proposals under this section shall be entitled to judicial review of the decision as
4provided in ch. 227, subject to the procedural requirements of s. 227.53 (1). A person
5shall be considered a person aggrieved and directly affected by a decision of the
6department if any of the following applies to a request for qualifications or a request
7for proposals issued by the department under this section:
AB820,13,98
1. The request does not include qualifications, requirements, or other items
9required under this section.
AB820,13,1110
2. The request does not comply with procedural requirements under this
11section.
AB820,13,1212
3. The request contains material errors or omissions.
AB820,13,1413
4. The request contains material discrepancies, deficiencies, or ambiguities
14that prevent a person from submitting a responsive proposal.
AB820,13,1615
5. The request indicates a bias against or preference for a specific
16design-builder.
AB820,13,1717
6. The request exceeds the department's authority.
AB820,13,2318
(b) Any person aggrieved and directly affected by a decision of the department
19to issue a notice of intent to award a contract under this section shall be entitled to
20judicial review of the decision as provided in ch. 227, subject to the procedural
21requirements of s. 227.53 (1). A person shall be considered a person aggrieved and
22directly affected by a decision of the department if any of the following applies to a
23notice of intent to award a contract under this section:
AB820,13,2524
1. The design-builder that received the notice of intent to award a contract was
25improperly certified as a qualified responsible bidder.
AB820,14,2
12. A mathematical error was made in scoring any of the proposals that resulted
2in an improper intent to award a contract.
AB820,14,53
3. There is evidence of collusion or fraud involving either the design-builder
4who received the notice of intent to award a contract or a member of the technical
5review committee.
AB820,14,66
4. There is evidence of bias of a member of the technical review committee.
AB820,14,117
5. There is evidence that a member of the technical review committee has a
8conflict of interest because the committee member, a member of his or her immediate
9family, as defined in s. 19.42 (7), or any organization or business with which the
10member is associated, as defined in s. 19.42 (2), may benefit from the intent to award
11a contract.
AB820,14,1612
6. The technical proposal or cost proposal submitted by the design-builder who
13received the notice of intent to award a contract is not responsive to the request for
14proposals, contains conditions or qualifications not provided for in the request for
15proposals, or does not assign costs to all services identified in the technical proposal
16or is otherwise materially unbalanced.
AB820,15,217
(c) If the department prevails upon judicial review, following any protest and
18appellate court proceedings, the department shall be entitled to recover all costs and
19charges included in the final order or judgment, excluding attorney fees. Upon
20payment of costs and charges by the protester, the bond shall be returned. If the
21protesting party prevails, the protesting party shall be entitled to recover from the
22department all costs and charges included in the final order or judgment, excluding
23attorney fees. The entire amount of the bond shall be forfeited if the hearing officer
24determines that a protest was filed for a frivolous or improper purpose, including but
1not limited to the purpose of harassing, causing unnecessary delay, or causing
2needless cost for the department or parties.
AB820,33
3Section 33
. 84.062 (14) of the statutes is created to read:
AB820,15,104
84.062
(14) Deliverables. (a) No later than 9 months after the effective date
5of this section .... [LRB inserts date], the department shall prepare a report that
6establishes a program structure for delivering projects as required under this
7subsection. The report shall specify the types of highway improvement projects to
8be considered and procedures and timelines for the bid process. The department may
9not designate a highway improvement project as a design-build project prior to the
10completion of the report.