This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
PSC 113.0704 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0705PSC 113.0705Power quality diagnostic services.
PSC 113.0705(1)(1)Each utility shall own or otherwise arrange to have available when needed, suitable monitoring equipment for surveying its system and the electrical system of its customers at the point of service for power quality problems; such as harmonic distortion, voltage sags and swells, transients and flicker; that may adversely affect or interfere with the overall adequacy of service to its customers. If the source of the power quality problem is determined to be equipment operated by a specific customer, the utility shall notify the customer and it shall be the customer’s responsibility to correct the problem. If the problem is caused by the utility delivery system operating outside the limits set forth in s. PSC 113.0702 the responsible utility shall correct the problem.
PSC 113.0705(2)(2)The utility and the affected and/or offending customer shall cooperate as necessary to promptly investigate, diagnose and resolve power quality complaints and problems. The utility shall share the results of its investigation with the affected and/or offending customer. If a utility offers power quality correction or mitigation services or equipment through a non-regulated affiliate or otherwise as a non-utility service, it may advise the customer of this option, but shall disclose the non-utility nature of this offering and that the customer is not obligated to take such services from the utility or its affiliate.
PSC 113.0705 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0706PSC 113.0706Check of standards by commission.
PSC 113.0706(1)(1)Each utility shall submit to a public service commission-approved calibration facility once each year a portable digital standard watthour meter and once each 2 years a portable digital indicating voltmeter or multimeter, unless waived by the commission under the provisions of s. PSC 113.0902 (1). Smaller Class C and D utilities, may be allowed to continue to use the older electromechanical portable watthour standard for a reasonable future time period, if so authorized by the commission.
PSC 113.0706 NoteNote: The rapid movement to the newer fully-electronic digital watthour standards by the measurement industry has limited a laboratory’s ability to get replacement parts needed to maintain and calibrate the older electromechanical standards. All utilities have been advised of the need to acquire electronic/digital standards when it is reasonably feasible to replace the older obsolete electromechanical standards.
PSC 113.0706(2)(2)Each utility shall be equipped with or otherwise arrange to have available when needed, portable digital indicating and recording voltmeters having internal memory channels of an accuracy and quantity sufficient to make a determination that the service voltage supplied to their customers complies with the requirements set forth in ch. PSC 113. This instrument shall be maintained with an error no greater than 0.8% of full scale.
PSC 113.0706 NoteNote: (1) Caution should be exercised in using digital meters in areas of high electrical fields such as in close proximity to substations, high voltage lines, transformers, regulators, etc., as unstable or erroneous readings may result.
PSC 113.0706 Note(2) Those utilities which operate standards laboratories will require primary or laboratory grade instruments of a higher accuracy class than required above.
PSC 113.0706(3)(3)Each recording voltmeter shall be checked with an indicating voltmeter when it is placed in operation and when it is removed, or periodically if the instrument is in a permanent location. Notations for each record shall indicate when the registration began (time and date) and when the record was ended, as well as indicate the point where the voltage was taken. For non-digital recorders, also include the results of the check with an indicating voltmeter.
PSC 113.0706(4)(4)Utilities with more than 1,000 customers shall have or otherwise arrange to have available when needed, one or more digital recording voltmeters with the appropriate programs to measure both the quality and quantity of the voltage and currents at the point of service. The meters shall be capable of storing the test results in such a manner as the records could be reviewed via a personal computer-based system.
PSC 113.0706(5)(5)Upon customer request each utility shall make a sufficient number of voltage measurements at the point of service to verify its compliance with these rules. These voltage records, unless replaced by more recent records, shall be available for inspection by the commission for a period of 2 years
PSC 113.0706 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0707PSC 113.0707Radio and television interference.
PSC 113.0707(1)(1)Each utility shall own or otherwise arrange to have available when needed, suitable monitoring equipment for surveying its lines and equipment for possible radio and/or television interference.
PSC 113.0707(2)(2)Each utility shall establish and routinely utilize in the course of regular operation, means whereby the presence of radio and/or television interference may be detected.
PSC 113.0707(3)(3)Each utility shall, upon notification or detection of the presence of radio and/or television interference, survey its lines and equipment for possible sources of radio and television interference. When significant interference is found, reasonable measures shall be taken to locate the source and, if on the utility’s system, to mitigate the interference. Where the magnitude and nature of the interference is found to be so small, intermittent or insignificant that it affects only a few customers or a particular, unique piece of customer equipment that may have limited capabilities to receive weak signals, it may be necessary to limit the utility’s responsibility for mitigation to reasonable, cost-effective measures.
PSC 113.0707 NoteNote: In some cases, some interference from the utility’s system may be detected, but found to be insignificant and inconsequential for the majority of customers. Its elimination or mitigation may still not result in adequate reception of some signals. In many areas, radio or television reception of some transmissions is normally inadequate due to frequency, weak signal strength, high ambient noise, distance from the source, terrain or other obstacles beyond the utility’s control. The capabilities and limitations of the customer’s receiver should also be evaluated and considered in determining the nature, extent and cost of the utility’s mitigation activities. Also, other options may be available and more feasible, for example, applying the mitigation to the customer’s equipment or substitution of cable television (CATV) or digital satellite service for local antenna systems.
PSC 113.0707(4)(4)Where the source of interference is determined to be equipment owned by a specific customer, the customer shall be so advised and informed of his or her responsibility to correct the problem (see s. PSC 113.0201).
PSC 113.0707 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
subch. VIII of ch. PSC 113Subchapter VIII — General Customer Metering and Meter Accuracy
PSC 113.0801PSC 113.0801Measuring energy on system. Where practical to do so, all electrical quantities required to be reported to the commission shall be metered. Quantities may be calculated when permitted by s. PSC 113.0802.
PSC 113.0801 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0802PSC 113.0802Measuring customer service.
PSC 113.0802(1)(1)Except as provided in sub. (2), all energy sold to customers shall be measured by commercially acceptable measuring devices owned and maintained by the utility. All other electrical quantities which the rates or utility’s rules indicate are to be metered shall be metered by commercially acceptable instruments owned and maintained by the utility.
PSC 113.0802(2)(2)For temporary or special installations where it is impractical to meter loads, such as certain highway or area lighting which may be billed at a flat rate based on lamp rating and use, the consumption may be calculated.
PSC 113.0802(3)(3)The metering and wiring in nontransient, multi-dwelling-unit residential buildings, mobile home parks and commercial establishments where individual unit metering is provided, or required under the provisions of s. PSC 113.0803, shall be so installed or arranged so that each customer or tenant is metered for his or her own consumption only. Energy used by common area loads, for example, hallway lighting and heating, shall be separately metered and billed as appropriate under the utility’s filed tariff.
PSC 113.0802(4)(4)Utilities shall inspect existing properties for jointly metered service where a tenant reasonably suspects that he or she is being billed for significant usage (e.g., furnace, water heater, etc.) that is serving more than one rental dwelling unit. The utility may bill the property owner for such an inspection. See s. 196.643, Stats.
PSC 113.0802 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0803PSC 113.0803Individual electric meters required for non-transient multi-dwelling unit residential buildings, mobile home parks and for commercial establishments.
PSC 113.0803(1)(1)Each dwelling in a multi-dwelling unit residential building and mobile home park constructed after March 1, 1980, shall have installed a separate electric meter for each such dwelling unit. Dwelling unit means a structure or that part of a structure which is used or intended to be used as a home, residence or a sleeping place by one or more persons maintaining a common household and shall exclude transient multi-dwelling buildings and mobile home parks: for example, hotels, motels, campgrounds, hospitals, community-based residential facilities, residential care apartment complexes or similar facilities, nursing homes, college dormitories, fraternities, and sororities.
PSC 113.0803(2)(2)Each tenant space in a commercial building constructed after March 1, 1980 shall have installed a separate electric meter.
PSC 113.0803(3)(3)Any existing building which undergoes alterations involving a change in type of occupancy or substantial remodeling shall have installed a separate electric meter for each separate tenant space.
PSC 113.0803(4)(4)For the purpose of carrying out the provisions of sub. (1), individual unit metering will not be required:
PSC 113.0803(4)(a)(a) In commercial buildings where the commercial unit space requirements are subject to alteration, as evidenced by temporary versus permanent type of wall construction separating the commercial unit spaces. Examples of temporary wall construction are partition walls which do not extend through the ceiling and walls which do not constitute a code-required fire separation.
PSC 113.0803(4)(b)(b) For electricity used in central heating, ventilating and air conditioning systems.
PSC 113.0803(4)(c)(c) For electric back-up service to storage heating and cooling systems or when alternative renewable energy resources are utilized in connection with central heating ventilating and air conditioning systems.
PSC 113.0803(5)(5)For reasonable cause shown, the commission may grant waivers of this rule on a case-by-case basis. Applications for a waiver must be submitted to the commission in writing and set forth the facts or reasons applicant believes justify a waiver. In cases involving multi-dwelling unit residential buildings, the applicant must show that the electric equipment under tenant control is substantially more efficient than required by applicable codes and that the overall electric usage under tenant control is minimal. Example cases which would not qualify for waiver are buildings which are electrically heated or buildings which have individual unit electric water heaters.
PSC 113.0803 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00; CR 02-027: am. (1), Register December 2002 No. 564, eff. 1-1-03.
PSC 113.0804PSC 113.0804One-point metering. Every reasonable effort shall be made to measure at one point all the electrical quantities necessary for billing a customer under a given rate.
PSC 113.0804 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0805PSC 113.0805Tamper-resistant equipment. Where electrical energy has been diverted or the utility’s equipment for measuring the service or controlling a customer’s load has been interfered with, the utility may require the customer to install entrance and service equipment to prevent current diversion or interference with the metering or control equipment.
PSC 113.0805 NoteNote: See s. PSC 113.0808.
PSC 113.0805 NoteNote: Care should be taken in determining the existence of diversion and amount of energy diverted. In case check-meters are used, the possibility of grounds between meters, normal meter inaccuracies and incorrect connections of meters should not be over-looked. The requirements of the Wisconsin state electrical code for entrances should effectively prevent such diversion. Attention is directed to ss. 939.32 and 943.20, Stats.
PSC 113.0805 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0806PSC 113.0806Multipliers and test constants.
PSC 113.0806(1)(1)Meters which are not direct reading shall have the multiplier plainly marked on the dial of the instrument or otherwise suitably marked and all charts taken from recording meters shall be marked with the date of the record, the meter number, customer and chart multiplier.
PSC 113.0806(2)(2)The register ratio shall be marked on all meter registers.
PSC 113.0806(3)(3)The watthour constant for the meter itself shall be placed on each watthour meter.
PSC 113.0806 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0807PSC 113.0807Meter compensation.
PSC 113.0807(1)(1)Metering equipment shall not be set “fast” or “slow” to compensate for supply transformer or line losses.
PSC 113.0807(2)(2)Loss compensators designed to be used with meters and which accurately add iron losses, copper losses, or both may be used. The compensator shall carry a tag identifying the compensation and shall be tested when the associated meter is tested and when the associated supply equipment on lines are changed.
PSC 113.0807 NoteNote: See s. PSC 113.0917 which covers test requirements for transformer loss compensators.
PSC 113.0807 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0808PSC 113.0808Sealing meters and service entrance equipment.
PSC 113.0808(1)(1)Meters and metering equipment enclosures, which if open, would permit access to live parts from which energy could be used without proper measurement and utility-owned devices and equipment located on a customer’s property for the control of his or her, load shall be sealed.
PSC 113.0808(2)(2)Where the entrance switch is combined with meter-test facilities, or is installed on the supply side of the meter, the entrance switch boxes may be sealed by the utility. The customer may remove the seal from any fuse compartment to replace fuses if the utility is promptly notified that such seal has been broken.
PSC 113.0808(3)(3)Where a utility supplies different classes of service at different rates to the same premises, such as lighting service and electric water heating service, the utility may seal the service switches.
PSC 113.0808(4)(4)Sealing and resealing shall be without charge to the customer.
PSC 113.0808(5)(5)This rule shall not require modernization of old installations or the sealing of installations which cannot practicably be sealed. Sealing shall not be such as to interfere with the operation of any switch or protective equipment.
PSC 113.0808 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0809PSC 113.0809Installation of metering equipment.
PSC 113.0809(1)(1)The customer or the customer’s agent should confer with the utility as one of the first steps in planning an electrical installation. The watthour meter should be located where it will be readily accessible for reading, testing and repairs and where it will not be subjected to adverse operating conditions or cause inconveniences to the customer. Normally, the utility shall determine the location and type of metering equipment to be installed.
PSC 113.0809(2)(2)The utility should have available for distribution to customers, architects, contractors and electricians copies of rules, specifications and requirements that may be in force relative to meter installations. Installations should conform to such specifications and to applicable codes and safety requirements.
PSC 113.0809(3)(3)Whether installed indoors or outdoors, meters should not be located where they will be subject to vibration or mechanical damage and should be mounted without tilt.
PSC 113.0809(4)(4)Meters and associated equipment used on outdoor installations shall be designed specifically for such use or shall be suitably housed for outdoor service. Meters installed outdoors should not be located where they may be damaged, such as on buildings where unguarded meters will extend into alleys, walkways or driveways.
PSC 113.0809(5)(5)Meters installed outdoors should not be more than 6 feet or less than 4 feet above final ground level (measured from the center of the meter cover) except in the case of meters on pedestals or padmounted transformers where they shall be placed as high as practicable and meters on underground services which may, when practicable, be placed as low as 2.5 feet above final ground level (measured from the center of the meter cover). On individual installations indoors, the meter should be not more than 6 feet or less than 4 feet above floor level (measured from the center of the meter cover). On group installations of meters indoors, no meter should be more than 6 feet or less than 2 feet above floor level (measured from the center of the meter cover). When a number of meters are placed on the same meter panel the distance between centers should be not less than 8.5 inches vertically or 7.5 inches horizontally. For meters installed both indoors and outdoors there should be a minimum of 3 feet of unobstructed space in front of the meter from the surface on which it is mounted.
PSC 113.0809(6)(6)When there is more than one meter at a location, each shall be so tagged or marked as to indicate the circuit metered. Where similar types of meters record different quantities (for example, kilowatt-hours and reactive power) the meters shall be tagged to indicate what they are recording.
PSC 113.0809(7)(7)Test facilities shall be placed in enclosures of sufficient size and of such construction as to make it possible for meter testers to perform the tests required by these rules with safety.
PSC 113.0809 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0810PSC 113.0810Rental charge for metering equipment. The utility may charge a rental for equipment installed to furnish additional metering information to a customer for his or her use or because of governmental requirements.
PSC 113.0810 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00.
PSC 113.0811PSC 113.0811Accuracy of watthour meters. In this section, “meter” or “meters” may refer to metering system(s).
PSC 113.0811(1)(1)Watthour meters used for measuring electrical quantities supplied to customers shall:
PSC 113.0811(1)(a)(a) Be of proper design for the circuit on which they are used, be properly connected and installed, be in good mechanical condition, have adequate insulation, correct internal connections and correct register.
PSC 113.0811(1)(b)(b) Not creep at “no load” a full revolution of the disk in 10 minutes or less when the load wires are disconnected and potential is impressed or in a test in the shop where the load wires are disconnected and the permissible voltage variation impressed. If the rate of creep can be determined in a shorter interval, it is not necessary to wait the full 10-minute period.
PSC 113.0811(1)(c)(c) If the meters are designed for use on alternating current circuits, they shall be accurate to within plus or minus 1% at 2 load tests: one equal to between 8% and 12% of full reference test current at unity power factor and the other between 90% and 110% of full reference test current at unity power factor; and for polyphase meters, shall be accurate to within plus or minus 2% at between 75% and 100% full reference test current and approximately 50% lagging power factor. For self-contained meters the reference test current shall be the ampere or test ampere rating of the meter, whichever is shown on the nameplate. For meters used with current transformers the reference test current shall be the test-ampere rating of the meter or the secondary rating of the current transformers.
PSC 113.0811 NoteNote: See s. PSC 113.0926 (2) for accuracy requirements for meters operating in the reverse-registration mode.
PSC 113.0811(2)(2)Polyphase meters shall have their stators in balance within 2% at 100% load at unity and at approximately 50% lagging power factor.
PSC 113.0811(3)(3)Meters used with instrument transformers shall be adjusted, if necessary, so that the overall accuracy of the metering installation will meet the requirements of this rule.
PSC 113.0811 HistoryHistory: Cr. Register, July, 2000, No. 535, eff. 8-1-00; CR 02-027: r. (4), Register December 2002 No. 564, eff. 1-1-03.
PSC 113.0812PSC 113.0812Accuracy of demand meters. In this section, “meter” or “meters” may refer to metering system(s).
PSC 113.0812(1)(1)A demand meter, demand register, or demand attachment used to measure customer’s service shall:
PSC 113.0812(1)(a)(a) Be in good mechanical and electrical condition.
PSC 113.0812(1)(b)(b) Have proper constants, indicating scale, contact device and resetting device.
PSC 113.0812(1)(c)(c) Not register at no load.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.