NR 734.13(2)(2) In addition to the class 2 notice required in sub. (1), the department may also solicit project-specific statements of qualifications by any appropriate method, including any of the following: NR 734.13(2)(a)(a) Placing the notice in trade publications or newspapers within the locale of the project. NR 734.13(2)(b)(b) Mailing the notice directly to potential consultants, if such measure is deemed necessary by the department to assure an adequate number of consultants for consideration by the selection committee. NR 734.13(3)(3) Criteria for evaluating project-specific qualifications shall be established by the selection committee or the designee of the chairperson prior to review of the statements of qualification. NR 734.13(4)(4) Proposals may be requested from one or more consultants who meet the project-specific qualification criteria. NR 734.13 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94; CR 12-023: am. (title), cr. (1) (f) Register October 2013 No. 694, eff. 11-1-13. NR 734.15(1)(1) Upon selection of one or more qualified consultants, the selection committee shall transmit to the consultants the department’s project scope of work and a request for a proposal for completing the project. NR 734.15(2)(2) The selection committee may request proposals from any number of qualified consultants. NR 734.15(3)(3) The department’s proposed project scope of work shall include all of the following: NR 734.15(4)(4) The request for proposal shall specify a date by which the consultant’s proposal shall be submitted to the department. If the consultant cannot provide the completed proposal by the time specified, the department may either grant a time extension or deem the consultant non-responsive and remove the consultant from further consideration for the project. NR 734.15(5)(5) The consultant’s proposal shall include all of the following: NR 734.15(5)(b)(b) A list of key personnel expected to work on the project and their qualifications pursuant to ch. NR 712. NR 734.15(5)(c)(c) A cost breakdown for the work to be performed, by task and assigned personnel. NR 734.15(5)(d)(d) A list of subcontractors expected to work on the project and their qualifications pursuant to ch. NR 712. NR 734.15 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94; CR 12-023: cr. (5) (g) Register October 2013 No. 694, eff. 11-1-13. NR 734.17NR 734.17 Proposal review. In selecting a consultant for a project, the department shall consider the adequacy of the proposal submitted under s. NR 734.15, in addition to the information in subs. (1) to (5). NR 734.17(2)(2) Experience and expertise necessary for the specific project. NR 734.17(4)(4) The consultant’s geographic proximity to the site or facility. NR 734.17 NoteNote: The department shall attempt to ensure that at least 5% of the total amount expended under this section in each fiscal year is paid to minority businesses, as required in s. 23.41 (6), Stats. NR 734.17 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94. NR 734.19(1)(1) If the selection committee considers it necessary, the committee may interview one or more consultants for the purpose of discussing the department’s requested scope of services and the consultant’s proposed method to implement the department’s scope of work. NR 734.19(2)(2) Upon completion of the consultant’s presentations, the selection committee shall select a consultant in accordance with the requirements of s. NR 734.15. An alternate consultant may also be designated by the committee. NR 734.19 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94. NR 734.21(1)(1) The department may negotiate the costs and scope of work for any project with a consultant. NR 734.21(2)(2) Upon completion of contract negotiations, a contract shall be sent to the consultant for signature. NR 734.21(3)(3) The contract shall be signed by the consultant and the department’s secretary. NR 734.21(4)(4) Projects with a cost greater than $60,000 shall be signed by the governor, in addition to the signatures required pursuant to sub. (3). NR 734.21(5)(5) No work on a project may commence until after the required signatures have been obtained. NR 734.21 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94; CR 12-023: am. (4) Register October 2013 No. 694, eff. 11-1-13. NR 734.23NR 734.23 Performance reporting. The department may evaluate the performance of consultants, create a written record of that evaluation, provide summaries of the evaluation to the consultant, provide the consultant an opportunity to discuss the evaluation with the department and allow the consultant to submit a written response for inclusion in the record. NR 734.23 HistoryHistory: Cr. Register, April, 1994, No. 460, eff. 5-1-94.
/exec_review/admin_code/nr/700/734
true
administrativecode
/exec_review/admin_code/nr/700/734/17/3
Department of Natural Resources (NR)
Chs. NR 700-799; Environmental Protection – Investigation and Remediation of Environmental Contamination
administrativecode/NR 734.17(3)
administrativecode/NR 734.17(3)
section
true