NR 211.19 Loss of treatment capacity and bypass. Subchapter II — POTW Requirements
NR 211.20 Establishment of pretreatment programs. NR 211.21 Compliance dates. NR 211.22 Legal authority requirements. NR 211.23 Procedural requirements. NR 211.235 Regulation of significant industrial users. NR 211.24 Requests for pretreatment program approval. NR 211.25 Reporting requirements. NR 211.26 Confidentiality. NR 211.27 Pretreatment program modification. Subchapter III — Department Activities
NR 211.30 Pretreatment program approval and removal credit authorization. NR 211.31 Department activities in the absence of a pretreatment program. NR 211.32 Supplemental compliance monitoring and enforcement activities. NR 211.33 Certification of industrial user category. NR 211.34 Pretreatment standards and requirements based upon federally promulgated regulations. Subchapter IV — Regulation of Chloride and Mercury Sources
NR 211.40 POTW authority to regulate chloride discharges from all sources. NR 211.41 POTW action to reduce mercury discharges from all sources. Ch. NR 211 NoteNote: Chapter NR 211 as it existed on July 31, 1983 was repealed and a new chapter NR 211 was created effective August 1, 1983. Corrections made under s. 13.93 (2m) (b) 6. and 7., Register, March, 1997, No. 495. NR 211.01NR 211.01 Purpose. The purpose of this chapter is to establish under s. 283.21 (2), Stats., the responsibilities of industrial users and of publicly owned treatment works in preventing the discharge into publicly owned treatment works of pollutants which will interfere with the operation of the POTW, will pass through the POTW insufficiently treated, or which will impair the use or disposal of POTW sludge. NR 211.02NR 211.02 Applicability. The provisions of this chapter apply to industrial users and to publicly owned treatment works which receive or may receive wastewater from such industrial users. NR 211.02 HistoryHistory: Cr. Register, July, 1983, No. 331, eff. 8-1-83. NR 211.03NR 211.03 Definitions. The following special definitions are applicable to terms used in this chapter. Definitions of other terms are set forth in ch. NR 205 and ch. 283, Stats. NR 211.03(1)(1) “Average daily flow” means a reasonable measure of the average daily flow for a 30-day period. For new sources, flows shall be estimated using projected values. NR 211.03(1e)(1e) “Best management practices” or “BMPs” means maintenance or operating procedures, schedules of activities, prohibited practices, treatment requirements and other management practices to implement the prohibitions listed in s. NR 211.10 (1) and (2) or to control plant site runoff, spillage or leaks, sludge or waste disposal, or drainage from raw materials storage areas. NR 211.03(1m)(1m) “Bypass” means the intentional diversion of waste streams from any portion of an industrial user’s treatment facility. NR 211.03(2)(2) “Categorical pretreatment standard” means any standard specifying quantities or concentrations of pollutants or pollutant properties which may be discharged to a POTW by industrial users in specific industrial categories. NR 211.03(2e)(2e) “Centralized waste treater” means an industrial user that treats wastes generated by activities located at a site other than where treatment occurs and introduces the wastes into a POTW. This definition does not include an industrial user whose generating facility and treatment facility are owned by the same entity, and who do not accept wastes generated by entities other than the industrial user. NR 211.03(2s)(2s) “Commencement of construction” means the beginning of any of the following activities as part of a continuous on-site construction program: NR 211.03(2s)(a)(a) The placement, assembly or installation of facilities or equipment; NR 211.03(2s)(b)(b) Significant site preparation work, such as clearing, excavation or the removal of existing buildings, structures or facilities if their removal is necessary for the placement, assembly or installation of new source facilities or equipment; or NR 211.03(2s)(c)(c) The making of binding contractual obligations for the purchase of facilities or equipment which are intended to be used in the new source’s operation. Options to purchase or contracts which may be terminated without a substantial loss and contracts for feasibility, engineering or design studies do not constitute a commencement of construction. NR 211.03(3)(3) “Consistent removal rate” means a rate of consistent removal as calculated in accordance with s. NR 211.13 (2). NR 211.03(4)(4) “Control authority” means the POTW in relation to POTWs which have a pretreatment program and means the department in relation to POTWs which do not have a pretreatment program. NR 211.03(4m)(4m) “EPA” means the U.S. environmental protection agency. NR 211.03(5)(5) “Existing source” means any source which is not a new source. NR 211.03(6)(6) “Indirect discharge” means the introduction of pollutants into a POTW from any point source other than residential or commercial sources that discharge only domestic waste. Method of introduction includes, but is not limited to, by pipe, truck, or rail car. NR 211.03(7)(7) “Industrial user” means any source of indirect discharge. NR 211.03(8)(8) “Interference” means the inhibition or disruption of a POTW’s sewer system, treatment processes, or operations by an indirect discharge which, alone or in conjunction with the discharge or discharges from other sources, causes a violation or increases the magnitude or duration of a violation of any requirement of the POTW’s WPDES permit, or impairs the use or disposal of POTW sludge under chs. 281 and 283, Stats. NR 211.03(8m)(8m) “Maximum allowable industrial loading” means the total mass of a pollutant that all industrial users of a POTW, or groups of industrial users identified by the POTW, may discharge pursuant to local limits developed under s. NR 211.10 (3). NR 211.03(9)(9) “New source” means any building, structure, facility, or installation: NR 211.03(9)(b)(b) For which the commencement of construction occurred after the publication in the federal register of proposed pretreatment standards that will be applicable if promulgated according to section 307 (c) of the federal clean water act, 33 USC 1251 et seq.; and NR 211.03(9)(c)2.2. A total replacement of the process or production equipment that causes the discharge of pollutants at an existing source; or NR 211.03(9)(c)3.3. Substantially independent from an existing source at the same site. Whether or not a source is substantially independent shall be determined based on, among other factors, the extent to which the new facility is engaged in the same general type of activity as the existing source, and the extent to which the new facility’s production and wastewater generation are integrated with the existing source. NR 211.03(9m)(9m) “Overflow” means any diversion of flow from a POTW before the POTW treatment plant. NR 211.03(10)(10) “Pass through” means the discharge of pollutants through the POTW to waters of the state in quantities or concentrations which, alone or in conjunction with the discharge or discharges from other sources, causes a violation or increases the magnitude or duration of a violation of any requirement of the POTW’s WPDES permit. NR 211.03(11)(11) “POTW” or “Publicly owned treatment works” means a treatment works which is owned by a municipality and any sewers that convey wastewater to such a treatment works. This definition includes any devices or systems used by a municipality in the storage, treatment, recycling, and reclamation of municipal sewage or liquid industrial wastes. The term also means the municipality or local unit of government which has jurisdiction over the indirect discharges to, and the discharges from, such a treatment works. NR 211.03(12)(12) “POTW treatment plant” means that portion of the POTW which is designed to provide treatment, including recycling and reclamation, of municipal sewage and industrial waste. NR 211.03(13)(13) “Pretreatment” means the reduction of the amount of pollutants, the elimination of pollutants, or the alteration of the nature of pollutant properties in wastewater to a less harmful state prior to, or in lieu of, discharging such pollutants into a POTW. NR 211.03(14)(14) “Pretreatment program” means a program administered by a POTW that meets the criteria established in subch. II and which has been approved by the department in accordance with subch. III. NR 211.03(15)(15) “Pretreatment requirement” means any substantive or procedural requirement related to pretreatment, other than a pretreatment standard, imposed on an industrial user. NR 211.03(16)(16) “Pretreatment standard” means any regulation which applies to industrial users and which contains pollutant discharge limits promulgated by the department in accordance with s. 283.21 (2), Stats. This term includes both prohibited discharge standards set forth in or established under s. NR 211.10 and categorical pretreatment standards set forth in s. NR 211.11 and in chs. NR 221 through 297. NR 211.03(17)(17) “Prohibited discharge standard” means any standard specifying quantities or concentrations of pollutants or pollutant properties which may be discharged to a POTW by industrial users regardless of industrial category. NR 211.03(18)(18) “Regulated stream” means a stream regulated by a categorical pretreatment standard. NR 211.03(19)(19) “Removal” means a reduction in the amount of a pollutant in the POTW’s effluent or alteration of a pollutant during treatment at the POTW. The reduction or alteration may be physical, chemical or biological and may be the result of designed POTW capabilities or incidental to the operation of the treatment system. Removal does not mean dilution of a pollutant in the POTW. NR 211.03(19m)(b)(b) Any industrial user which discharges an average of 25,000 gallons per day or more of wastewater to the POTW, excluding sanitary, noncontact cooling and boiler blowdown wastewater; NR 211.03(19m)(c)(c) Any industrial user that discharges to the POTW a process waste stream which makes up 5% or more of the average dry weather hydraulic or organic capacity of the POTW treatment plant; or NR 211.03(19m)(e)(e) Any other industrial user designated as a significant industrial user by the control authority. NR 211.03(20)(20) “Sludge requirements” means the following statutory provisions and regulations or permits issued pursuant to them: section 405 of the federal clean water act; 33 USC 1251 et seq.; the solid waste disposal act (SWDA), 42 USC 6901 et seq.; the federal clean air act, 42 USC 1857 et seq.; the toxic substances control act, 15 USC 2601 et seq.; the marine protection, research and sanctuaries act, 33 USC 1401 et seq.; and ch. 281, Stats. NR 211.03(20m)(20m) “Slug” means any nonroutine, episodic discharge, such as a discharge resulting from a spill or a noncustomary batch discharge. NR 211.03(21)(21) “Unregulated stream” means a stream not regulated by a categorical pretreatment standard. NR 211.03(22)(22) “WPDES permit” means a permit issued to a POTW under s. 283.31, Stats., for the purposes of controlling pollutant discharge. NR 211.03 HistoryHistory: Cr. Register, July, 1983, No. 331, eff. 8-1-83; r. (6), renum. (1) to (5) and (7) to (15) to be (2), (4), (6) to (8) and (10) to (17) and (22), cr. (1), (3), (5), (9) and (18) to (21), Register, September, 1986, No. 369, eff. 10-1-86; cr. (1m), (2e), (2s), (9m), (19m) and (20m), am. (8) and (10), r. and recr. (9), Register, March, 1992, No. 435, eff. 4-1-92; CR 13-006: cr. (1e), (4m), am. (8), cr. (8m), am. (16), (19m) (a), (c), r. (19m) (d) Register January 2014 No. 697, eff. 2-1-14; correction in (16) made under s. 13.92 (4) (b) 7., Stats., Register January 2014 No. 697. NR 211.10NR 211.10 Prohibited discharge standards. NR 211.10(1)(1) Industrial users may not discharge pollutants into a POTW which pass through or interfere with the operation or performance of the POTW, and thereby cause or significantly contribute to a violation of the POTW’s WPDES permit. NR 211.10(2)(2) The following pollutants may not be introduced into a POTW: NR 211.10(2)(a)(a) Pollutants that create or contribute to a fire or explosion hazard in the POTW, including waste streams with a closed cup flashpoint of less than 140° F or 60° C using the test methods in s. NR 661.0021. NR 211.10(2)(b)(b) Pollutants which will cause or contribute to corrosive structural damage to the POTW but in no case discharges with a pH lower than 5.0, unless the POTW is specifically designed to accommodate such discharges. NR 211.10(2)(c)(c) Solid or viscous pollutants in amounts which will cause or contribute to obstruction to the flow in sewers or other interference with the operation of the POTW. NR 211.10(2)(d)(d) Any pollutant, including oxygen demanding pollutants, released in a discharge of such volume or strength as to cause or contribute to interference in the POTW. NR 211.10(2)(e)(e) Heat in amounts which will inhibit or contribute to the inhibition of biological activity in the POTW treatment plant resulting in interference or causing damage to the POTW but in no case heat in such quantities that the temperature exceeds 40°C (104°F) at the influent to the POTW treatment plant unless the department, at the request of the POTW, has approved alternate temperature limits. NR 211.10(2)(f)(f) Petroleum oil, nonbiodegradable cutting oil or products of mineral oil origin in amounts that will cause interference or pass through. NR 211.10(2)(g)(g) Pollutants which result in the presence of gases, vapors or fumes within the POTW in a quantity which may cause acute worker health or safety problems. NR 211.10(2)(h)(h) Any trucked or hauled pollutants, except at discharge points designated by the POTW. NR 211.10(3)(a)(a) POTWs developing pretreatment programs under subchapter II shall develop specific prohibited discharge standards to enforce the general prohibitions of subs. (1) and (2). All other POTWs shall, where the contributions of industrial users result in pass-through or interference and the resulting permit violation is likely to recur, develop and enforce specific prohibited discharge standards which, together with appropriate POTW facility or operation changes, are necessary to ensure continued compliance with the POTW’s WPDES permit. NR 211.10(3)(b)(b) This subsection is not intended to require pretreatment as a substitute for adequate municipal treatment. NR 211.10(3)(c)(c) Specific prohibited discharge standards may not be developed and enforced by the POTW without giving prior notice to persons or groups who have requested notice and an opportunity to respond.
/exec_review/admin_code/nr/200/211
true
administrativecode
/exec_review/admin_code/nr/200/211/03/1e
Department of Natural Resources (NR)
Chs. NR 200-299; Environmental Protection – Wisconsin Pollutant Discharge Elimination System
administrativecode/NR 211.03(1e)
administrativecode/NR 211.03(1e)
section
true