This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 151.12(5)(d)1.f.f. In subd. 1. a., d. and e., determinations of the extent of the protective area adjacent to wetlands shall be made on the basis of the sensitivity and runoff susceptibility of the wetland in accordance with the standards and criteria in s. NR 103.03.
NR 151.12(5)(d)1.g.g. For concentrated flow channels with drainage areas greater than 130 acres, 10 feet.
NR 151.12(5)(d)2.2. This paragraph applies to post-construction sites located within a protective area, except those areas exempted pursuant to subd. 4.
NR 151.12(5)(d)3.3. The following requirements shall be met:
NR 151.12(5)(d)3.a.a. Impervious surfaces shall be kept out of the protective area to the maximum extent practicable. The storm water management plan shall contain a written site-specific explanation for any parts of the protective area that are disturbed during construction.
NR 151.12(5)(d)3.b.b. Where land disturbing construction activity occurs within a protective area, and where no impervious surface is present, adequate sod or self-sustaining vegetative cover of 70% or greater shall be established and maintained. The adequate sod or self-sustaining vegetative cover shall be sufficient to provide for bank stability, maintenance of fish habitat and filtering of pollutants from upslope overland flow areas under sheet flow conditions. Non-vegetative materials, such as rock riprap, may be employed on the bank as necessary to prevent erosion such as on steep slopes or where high velocity flows occur.
NR 151.12 NoteNote: It is recommended that seeding of non-aggressive vegetative cover be used in the protective areas. Vegetation that is flood and drought tolerant and can provide long-term bank stability because of an extensive root system is preferable. Vegetative cover may be measured using the line transect method described in the university of Wisconsin extension publication number A3533, titled “Estimating Residue Using the Line Transect Method”.
NR 151.12(5)(d)3.c.c. Best management practices such as filter strips, swales or wet detention basins, that are designed to control pollutants from non-point sources may be located in the protective area.
NR 151.12 NoteNote: Other regulations, such as ch. 30, Stats., and chs. NR 103, 115, 116 and 117 and their associated review and approval process may apply in the protective area.
NR 151.12(5)(d)4.4. Exemptions. This paragraph does not apply to:
NR 151.12(5)(d)4.a.a. Redevelopment post-construction sites.
NR 151.12(5)(d)4.b.b. In-fill development areas less than 5 acres.
NR 151.12(5)(d)4.c.c. Structures that cross or access surface waters such as boat landings, bridges and culverts.
NR 151.12(5)(d)4.d.d. Structures constructed in accordance with s. 59.692 (1v), Stats.
NR 151.12(5)(d)4.e.e. Post-construction sites from which runoff does not enter the surface water, except to the extent that vegetative ground cover is necessary to maintain bank stability.
NR 151.12 NoteNote: A vegetated protective area to filter runoff pollutants from post-construction sites described in subd. 4. e. is not necessary since runoff is not entering the surface water at that location. Other practices necessary to meet the requirements of this section, such as a swale or basin, will need to be designed and implemented to reduce runoff pollutants prior to runoff entering a surface water of the state.
NR 151.12(5)(e)(e) Fueling and vehicle maintenance areas. Fueling and vehicle maintenance areas shall, to the maximum extent practicable, have BMPs designed, installed and maintained to reduce petroleum within runoff, such that the runoff that enters waters of the state contains no visible petroleum sheen.
NR 151.12 NoteNote: A combination of the following BMPs may be used: oil and grease separators, canopies, petroleum spill cleanup materials, or any other structural or non-structural method of preventing or treating petroleum in runoff.
NR 151.12(5)(f)(f) Location. To comply with the standards required under this subsection, BMPs may be located on-site or off-site as part of a regional storm water device, practice or system, but shall be installed in accordance with s. NR 151.003.
NR 151.12(5)(g)(g) Timing. The BMPs that are required under this subsection shall be installed before the construction site has undergone final stabilization.
NR 151.12 HistoryHistory: CR 00-027: cr. Register September 2002 No. 561, eff. 10-1-02; CR 09-112: cr. (2) (bm) Register December 2010 No. 660, eff. 1-1-11.
NR 151.121NR 151.121Post-construction performance standards.
NR 151.121(1)(1)General. In ss. NR 151.121 to 151.128, “post-construction site” means a construction site subject to regulation under this subchapter, after construction is completed and final stabilization has occurred.
NR 151.121(2)(2)Applicability. Sections NR 151.121 to 151.128 apply to a post-construction site that is or was subject to the construction performance standards of s. NR 151.11, except any of the following:
NR 151.121(2)(a)(a) A post-construction site with less than 10 percent connected imperviousness, based on the area of land disturbance, provided the cumulative area of all impervious surfaces is less than one acre. However, the exemption of this paragraph does not include exemption from the protective area standard of s. NR 151.125.
NR 151.121(2)(b)(b) Agricultural facilities and practices.
NR 151.121 NoteNote: This exemption includes both point and nonpoint discharges from agricultural facilities and practices. Therefore, post-construction structures such as barns, manure storage facilities, sand settling lanes, and barnyard runoff control systems are subject to subch. II and are not subject, under s. NR 216.47 (1), to the post-construction performance standards of this subchapter.
NR 151.121(2)(c)(c) Underground utility construction, but not including the construction of any above ground structures associated with utility construction.
NR 151.121(3)(3)Responsible party. The landowner of the post-construction site or other person contracted or obligated by other agreement with the landowner to implement and maintain post-construction storm water BMPs is the responsible party and shall comply with ss. NR 151.121 to 151.128.
NR 151.121(4)(4)Storm water management plan. A written storm water management plan shall be developed and implemented for each post-construction site and shall incorporate the requirements of ss. NR 151.122 to 151.128.
NR 151.121 NoteNote: Examples of storm water management plans that may be used to comply with ss. NR 151.122 to 151.128 may include those specified in s. NR 216.47 or the municipal storm water management program specified in s. NR 216.07 (5).
NR 151.121(5)(5)Maintenance of effort. For redevelopment sites where the redevelopment will be replacing older development that was subject to post-construction performance standards of this chapter in effect on or after October 1, 2004, the responsible party shall meet the total suspended solids reduction, peak flow control, infiltration, and protective areas standards applicable to the older development or meet the redevelopment standards of ss. NR 151.122 to 151.125, whichever are more stringent.
NR 151.121 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11.
NR 151.122NR 151.122Total suspended solids performance standard.
NR 151.122(1)(1)Requirement. BMPs shall be designed, installed and maintained to control total suspended solids carried in runoff from the post-construction site. BMPs shall be designed in accordance with Table 1., or to the maximum extent practicable as provided in sub. (3). The design shall be based on an average annual rainfall, as compared to no runoff management controls.
NR 151.122(2)(2)Redevelopment. Except as provided in s. NR 151.121 (5), the redevelopment total suspended solids reduction standard of Table 1., applies to redevelopment.
NR 151.122(3)(3)Maximum extent practicable. If the design cannot meet a total suspended solids reduction performance standard of sub. (1), Table 1., the storm water management plan shall include a written, site-specific explanation of why the total suspended solids reduction performance standard cannot be met and why the total suspended solids load will be reduced only to the maximum extent practicable. The department may not require any person to exceed the applicable total suspended solids reduction performance standard to meet the requirements of maximum extent practicable.
NR 151.122 NoteNote: Pollutant loading models such as DETPOND, SLAMM, P8, or equivalent methodology may be used to evaluate the efficiency of the design in reducing total suspended solids. Information on how to access these models is available from the department’s storm water management program at dnr.wi.gov. Use the most recent version of the model and the rainfall files and other parameter files identified for Wisconsin users unless directed otherwise by the regulatory authority.
NR 151.122(4)(4)Off-site drainage. When designing BMPs, runoff draining to the BMP from off-site shall be taken into account in determining the treatment efficiency of the practice. Any impact on the efficiency shall be compensated for by increasing the size of the BMP accordingly.
NR 151.122 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11.
NR 151.123NR 151.123Peak discharge performance standard.
NR 151.123(1)(1)Requirement. By design, BMPs shall be employed to maintain or reduce the 1-year, 24-hour and the 2-year, 24-hour post-construction peak runoff discharge rates to the 1-year, 24-hour and the 2-year, 24-hour pre-development peak runoff discharge rates respectively, or to the maximum extent practicable. The runoff curve numbers in Table 2. shall be used to represent the actual pre-development condition.
NR 151.123 NoteNote: Where the pre-development condition is a combination of woodland, grassland, or cropland, the runoff curve number should be pro-rated by area.
NR 151.123(2)(2)Exemptions. This section does not apply to the following:
NR 151.123(2)(a)(a) A post-construction site where the discharge is directly into a lake over 5,000 acres or a stream or river segment draining more than 500 square miles.
NR 151.123(2)(b)(b) Except as provided under s. NR 151.121 (5), a redevelopment post-construction site.
NR 151.123(2)(c)(c) An in-fill development area of less than 5 acres.
NR 151.123 NoteNote: The intent of s. NR 151.123 is to minimize streambank and shoreline erosion under bank-full conditions.
NR 151.123 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11.
NR 151.124NR 151.124Infiltration performance standard.
NR 151.124(1)(1)Requirement. BMPs shall be designed, installed, and maintained to infiltrate runoff in accordance with the following or to the maximum extent practicable:
NR 151.124(1)(a)(a) Low imperviousness. For development up to 40 percent connected imperviousness, such as parks, cemeteries, and low density residential development, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 90 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than one percent of the post-construction site is required as an effective infiltration area.
NR 151.124(1)(b)(b) Moderate imperviousness. For development with more than 40 percent and up to 80 percent connected imperviousness, such as medium and high density residential, multi-family development, industrial and institutional development, and office parks, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 75 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than 2 percent of the post-construction site is required as an effective infiltration area.
NR 151.124(1)(c)(c) High imperviousness. For development with more than 80 percent connected imperviousness, such as commercial strip malls, shopping centers, and commercial downtowns, infiltrate sufficient runoff volume so that the post-development infiltration volume shall be at least 60 percent of the pre-development infiltration volume, based on an average annual rainfall. However, when designing appropriate infiltration systems to meet this requirement, no more than 2 percent of the post-construction site is required as an effective infiltration area.
NR 151.124 NoteNote: A histogram showing the relationship between connected imperviousness and land use is available from the department at dnr.wi.gov.
NR 151.124(2)(2)Pre-development. Pre-development condition shall be the same as specified in s. NR 151.123 (1), Table 2.
NR 151.124 NoteNote: A model that calculates runoff volume, such as SLAMM, P8, or an equivalent methodology may be used. For performance standards based on an average annual rainfall, specific rainfall files for five geographic locations around the state may be used. Information on how to access SLAMM and P8 and the rainfall files is available from the department’s storm water management program at dnr.wi.gov. Use the most recent version of the model and the parameter files for Wisconsin users unless directed otherwise by the regulatory authority.
NR 151.124(3)(3)Source areas.
NR 151.124(3)(a)(a) Prohibitions. Runoff from the following areas may not be infiltrated and may not qualify as contributing to meeting the requirements of this section unless demonstrated to meet the conditions of sub. (6):
NR 151.124(3)(a)1.1. Areas associated with a tier 1 industrial facility identified in s. NR 216.21 (2) (a), including storage, loading, and parking. Rooftops may be infiltrated with the concurrence of the regulatory authority.
NR 151.124(3)(a)2.2. Storage and loading areas of a tier 2 industrial facility identified in s. NR 216.21 (2) (b).
NR 151.124 NoteNote: Runoff from the employee and guest parking and rooftop areas of a tier 2 facility may be infiltrated but runoff from the parking area may require pretreatment.
NR 151.124(3)(a)3.3. Fueling and vehicle maintenance areas. Rooftops of fueling and vehicle maintenance areas may be infiltrated with the concurrence of the regulatory authority.
NR 151.124(3)(b)(b) Exemptions. Runoff from the following areas may be credited toward meeting the requirement when infiltrated, but the decision to infiltrate runoff from these source areas is optional:
NR 151.124(3)(b)1.1. Parking areas and access roads less than 5,000 square feet for commercial development.
NR 151.124(3)(b)2.2. Parking areas and access roads less than 5,000 square feet for industrial development not subject to the prohibitions under par. (a).
NR 151.124(3)(b)3.3. Except as provided under s. NR 151.121 (5), redevelopment post-construction sites.
NR 151.124(3)(b)4.4. In-fill development areas less than 5 acres.
NR 151.124(3)(b)5.5. Roads in commercial, industrial, and institutional land uses, and arterial residential roads.
NR 151.124(4)(4)Location of practices.
NR 151.124(4)(a)(a) Prohibitions. Infiltration practices may not be located in the following areas:
NR 151.124(4)(a)1.1. Areas within 1,000 feet upgradient or within 100 feet downgradient of direct conduits to groundwater.
NR 151.124(4)(a)2.2. Areas within 400 feet of a community water system well as specified in s. NR 811.16 (4) or within the separation distances listed in s. NR 812.08 for any private well or non-community well for runoff infiltrated from commercial, including multi-family residential, industrial, and institutional land uses or regional devices for one- and two-family residential development.
NR 151.124(4)(a)3.3. Areas where contaminants of concern, as defined in s. NR 720.03 (2), are present in the soil through which infiltration will occur.
NR 151.124(4)(b)(b) Separation distances.
NR 151.124(4)(b)1.1. Infiltration practices shall be located so that the characteristics of the soil and the separation distance between the bottom of the infiltration system and the elevation of seasonal high groundwater or the top of bedrock are in accordance with Table 3:
NR 151.124(4)(b)2.2. Notwithstanding par. (b), applicable requirements for injection wells classified under ch. NR 815 shall be followed.
NR 151.124(4)(c)(c) Infiltration rate exemptions. Infiltration practices located in the following areas may be credited toward meeting the requirement under the following conditions, but the decision to infiltrate under these conditions is optional:
NR 151.124(4)(c)1.1. Where the infiltration rate of the soil measured at the proposed bottom of the infiltration system is less than 0.6 inches per hour using a scientifically credible field test method.
NR 151.124(4)(c)2.2. Where the least permeable soil horizon to 5 feet below the proposed bottom of the infiltration system using the U.S. department of agriculture method of soils analysis is one of the following: sandy clay loam, clay loam, silty clay loam, sandy clay, silty clay, or clay.
NR 151.124(5)(5)Alternate use. Where alternate uses of runoff are employed, such as for toilet flushing, laundry or irrigation or storage on green roofs where an equivalent portion of the runoff is captured permanently by rooftop vegetation, such alternate use shall be given equal credit toward the infiltration volume required by this section.
NR 151.124(6)(6)Groundwater standards.
NR 151.124(6)(a)(a) Infiltration systems designed in accordance with this section shall, to the extent technically and economically feasible, minimize the level of pollutants infiltrating to groundwater and shall maintain compliance with the preventive action limit at a point of standards application in accordance with ch. NR 140. However, if site specific information indicates that compliance with a preventive action limit is not achievable, the infiltration BMP may not be installed or shall be modified to prevent infiltration to the maximum extent practicable.
NR 151.124(6)(b)(b) Notwithstanding par. (a), the discharge from BMPs shall remain below the enforcement standard at the point of standards application.
NR 151.124(7)(7)Pretreatment. Before infiltrating runoff, pretreatment shall be required for parking lot runoff and for runoff from new road construction in commercial, industrial, and institutional areas that will enter an infiltration system. The pretreatment shall be designed to protect the infiltration system from clogging prior to scheduled maintenance and to protect groundwater quality in accordance with sub. (6). Pretreatment options may include, but are not limited to, oil and grease separation, sedimentation, biofiltration, filtration, swales, or filter strips.
NR 151.124(8)(8)Maximum extent practicable. Where the conditions of subs. (3) and (4) limit or restrict the use of infiltration practices, the performance standard of s. NR 151.124 shall be met to the maximum extent practicable.
NR 151.124 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11.
NR 151.125NR 151.125Protective areas performance standard.
NR 151.125(1)(1)Definition. In this section, “protective area” means an area of land that commences at the top of the channel of lakes, streams and rivers, or at the delineated boundary of wetlands, and that is the greatest of the following widths, as measured horizontally from the top of the channel or delineated wetland boundary to the closest impervious surface. However, in this section, “protective area” does not include any area of land adjacent to any stream enclosed within a pipe or culvert, so that runoff cannot enter the enclosure at this location.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.