NR 151.015(18)(b)(b) An area within 1000 feet of a municipal well.
NR 151.015(18)(c)(c) An area within 300 feet upslope or 100 feet downslope of a direct conduit to groundwater.
NR 151.015(18)(d)(d) A channel that flows to a direct conduit to groundwater.
NR 151.015(18)(e)(e) An area where the soil depth to groundwater or bedrock is less than 2 feet.
NR 151.015(18)(f)(f) An area where the soil does not exhibit one of the following soil characteristics:
NR 151.015(18)(f)1.1. At least a 2-foot soil layer with 40% fines or greater above groundwater and bedrock.
NR 151.015(18)(f)2.2. At least a 3-foot soil layer with 20% fines or greater above groundwater and bedrock.
NR 151.015(18)(f)3.3. At least a 5-foot soil layer with 10% fines, or greater above groundwater and bedrock.
NR 151.015 NoteNote: See s. NR 151.002 (32) for definition of percent fines.
NR 151.015(18g)(18g)“Soil texture” means the surface texture of the Silurian bedrock soil map unit.
NR 151.015(18r)(18r)“Solid manure” has the meaning given in s. NR 243.03 (58) when applied to facilities subject to ch. NR 243, Wis. Adm. Code and the meaning given in UW A2809 for all other agricultural facilities where manure is generated.
NR 151.015 NoteNote: Copies of the University of Wisconsin — Extension publication A2809 Nutrient Application Guidelines for Field, Vegetable, and Fruit Crops in Wisconsin, dated 2012 (A2809) may be inspected at the office of the department, the Wisconsin Department of Agriculture, Trade and Consumer Protection and the legislative reference bureau, Madison, Wisconsin. A2809 is also available electronically at: http://learningstore.uwex.edu/assets/pdfs/A2809.pdf.
NR 151.015(19)(19)“Stored manure” means manure that is kept in a manure storage facility or an unconfined manure pile.
NR 151.015(20)(20)“Substantially altered” means a change initiated by an owner or operator that results in a relocation of a structure or facility or significant changes to the size, depth or configuration of a structure or facility including:
NR 151.015(20)(a)(a) Replacement of a liner in a manure storage structure.
NR 151.015(20)(b)(b) An increase in the volumetric capacity or area of a structure or facility by greater than 20%.
NR 151.015(20)(c)(c) A change in a structure or facility related to a change in livestock management from one species of livestock to another such as cattle to poultry.
NR 151.015(21)(21)“Tolerable soil loss” or “T” means the maximum rate of erosion, in tons per acre per year, allowable for particular soils and site conditions that will maintain soil productivity.
NR 151.015(22)(22)“Unconfined manure pile” means a quantity of manure that is at least 175 ft3 in volume and which covers the ground surface to a depth of at least 2 inches and is not confined within a manure storage facility, livestock housing facility or barnyard runoff control facility or covered or contained in a manner that prevents storm water access and direct runoff to surface water or leaching of pollutants to groundwater.
NR 151.015(22m)(22m)“UW A2809” means the 2012 version of the University of Wisconsin – Extension Nutrient Application Guidelines for Field, Vegetable, and Fruit Crops in Wisconsin (A2809).
NR 151.015 NoteNote: Copies of the University of Wisconsin — Extension publication A2809 Nutrient Application Guidelines for Field, Vegetable, and Fruit Crops in Wisconsin, dated 2012 (A2809) may be inspected at the office of the department, the Wisconsin Department of Agriculture, Trade and Consumer Protection and the legislative reference bureau, Madison, Wisconsin. A2809 is also available electronically at: http://learningstore.uwex.edu/assets/pdfs/A2809.pdf.
NR 151.015(24)(24)“Water quality management area” or “WQMA” means the area within 1,000 feet from the ordinary high water mark of navigable waters that consist of a lake, pond or flowage, except that, for a navigable water that is a glacial pothole lake, the term means the area within 1,000 feet from the high water mark of the lake; the area within 300 feet from the ordinary high water mark of navigable waters that consist of a river or stream; and a site that is susceptible to groundwater contamination, or that has the potential to be a direct conduit for contamination to reach groundwater.
NR 151.015(25)(25)“Winter grazing area” means a cropland or pasture where livestock feed on dormant vegetation or crop residue, with or without supplementary feed, during the period of October 1 to April 30.
NR 151.015 HistoryHistory: CR 00-027: cr. Register September 2002 No. 561, eff. 10-1-02; CR 09-112: r. and recr. (1), (8), (16), am. (7), (18) (c), (d), cr. (13g), (15e), (15m), (15s), (25), r. (17) Register December 2010 No. 660, eff. 1-1-11; CR 17-062: cr. (2), (2m), (7m), (8d), (8h), (8p), (8t), (11m), (13j), (15n), (15w), (17), (18g), (18r), (22m), Register June 2018 No. 750 eff. 7-1-18; corrections in (8t) and (17) made under s. 35.17, Stats., Register June 2018 No. 750.
NR 151.02NR 151.02Sheet, rill and wind erosion performance standard.
NR 151.02(1)(1)All land where crops or feed are grown, including pastures, shall be managed to achieve a soil erosion rate equal to, or less than, the “tolerable” (T) rate established for that soil.
NR 151.02(2)(2)This standard first applies to pastures beginning July 1, 2012.
NR 151.02 NoteNote: Soil loss will be calculated according to the revised universal soil loss equation II as referenced in ch. ATCP 50 and appropriate wind loss equations as referenced in ch. ATCP 50.
NR 151.02 HistoryHistory: CR 00-027: cr. Register September 2002 No. 561, eff. 10-1-02; CR 09-112: am. Register December 2010 No. 660, eff. 1-1-11.
NR 151.03NR 151.03Tillage setback performance standard. The purpose of this standard is to prevent tillage operations from destroying stream banks and depositing soil directly in surface waters. In this section, “surface water” has the meaning given in s. NR 102.03 (7).
NR 151.03(1)(1)No crop producer may conduct a tillage operation that negatively impacts stream bank integrity or deposits soil directly in surface waters.
NR 151.03(2)(2)No tillage operations may be conducted within 5 feet of the top of the channel of surface waters. Tillage setbacks greater than 5 feet but no more than 20 feet may be required to meet this standard.
NR 151.03(3)(3)Crop producers shall maintain the area within the tillage setback required under sub. (2) in adequate sod or self-sustaining vegetative cover that provides a minimum of 70% coverage.
NR 151.03(4)(4)This section does not apply to grassed waterways installed as conservation practices.
NR 151.03 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11; correction to (intro.) made under s. 13.92 (4) (b) 7., Stats., Register December 2010 No. 660.
NR 151.04NR 151.04Phosphorus index performance standard.
NR 151.04(1)(1)All crop and livestock producers shall comply with this section.
NR 151.04(2)(a)(a) Croplands, pastures, and winter grazing areas shall average a phosphorus index of 6 or less over the accounting period and may not exceed a phosphorus index of 12 in any individual year within the accounting period.
NR 151.04(2)(b)(b) Except as provided under sub. (3), for purposes of compliance with this section the phosphorus index shall be calculated using the version of the Wisconsin Phosphorus Index available as of January 1, 2011.
NR 151.04 NoteNote: The Wisconsin Phosphorus Index is maintained by the University of Wisconsin department of soil science and can be found at http://wpindex.soils.wisc.edu/.
NR 151.04 NoteNote: Soil test phosphorus concentration may be used to help identify fields that are high priority for evaluation with the Wisconsin Phosphorus Index. For example, croplands with soil test phosphorus concentrations of 35 parts per million or greater should be given higher priority for evaluation.
NR 151.04 NoteNote: Best management practices developed by the department of agriculture, trade and consumer protection may be used alone or in combination to meet the requirements of this section.
NR 151.04(2)(c)(c) The accounting period required under par. (a) shall meet the following conditions:
NR 151.04(2)(c)1.1. The accounting period shall begin once a nutrient management plan meeting the requirements of s. NR 151.07 and s. ATCP 50.04 (3) is completed.
NR 151.04(2)(c)2.2. During the first 8 years of implementation of this standard by a producer, computation of the phosphorus index may be based on a combination of planned crop management and historic data. Planned crop management data is based on projected management and crop rotations. Historic data is based on management and crop rotations that have actually occurred.
NR 151.04(2)(c)3.3. Once the nutrient management plan under s. NR 151.07 and s. ATCP 50.04 (3) is developed, historic data shall be used for each year as it becomes available.
NR 151.04(3)(3)If the phosphorus index is not applicable to a particular crop or situation, an equivalent calculation approved by the department shall be used to meet the requirements of this section.
NR 151.04 NoteNote: The requirement provides for alternative methods to calculate a phosphorus index. Some strategies for assessing and reducing phosphorus index values, algorithms, and software can be found at http://wpindex.soils.wisc.edu/.
NR 151.04(4)(4)Producers may not apply nutrients or manure directly, through mechanical means, to surface waters as defined in s. NR 102.03 (7).
NR 151.04(5)(5)The phosphorus index requirement under sub. (2) (a) first takes effect for pastures beginning July 1, 2012.
NR 151.04 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11; correction to (4) made under s. 13.92 (4) (b) 7., Stats., Register December 2010 No. 660.
NR 151.05NR 151.05Manure storage facilities performance standards.
NR 151.05(1)(1)Applicability. All livestock producers building new manure storage facilities, substantially altering manure storage facilities, or choosing to abandon their manure storage facilities shall comply with this section.
NR 151.05(2)(2)New construction and alterations.
NR 151.05(2)(a)(a) New or substantially altered manure storage facilities shall be designed, constructed and maintained to minimize the risk of structural failure of the facility and minimize leakage of the facility in order to comply with groundwater standards. The levels of materials in the storage facility may not exceed the margin of safety level.
NR 151.05(2)(am)(am) Storage facilities that are constructed or significantly altered on or after January 1, 2011, shall be designed and operated to contain the additional volume of runoff and direct precipitation entering the facility as a result of a 25-year, 24-hour storm.
NR 151.05(2)(b)(b) A new manure storage facility means a facility constructed after October 1, 2002.
NR 151.05(2)(c)(c) A substantially altered manure storage facility is a manure storage facility that is substantially altered after October 1, 2002.
NR 151.05(3)(3)Closure.
NR 151.05(3)(a)(a) Closure of a manure storage facility shall occur when an operation where the facility is located ceases operations, or manure has not been added or removed from the facility for a period of 24 months. Manure facilities shall be closed in a manner that will prevent future contamination of groundwater and surface waters.
NR 151.05(3)(b)(b) The owner or operator may retain the facility for a longer period of time by demonstrating to the department that all of the following conditions are met:
NR 151.05(3)(b)1.1. The facility is designed, constructed and maintained in accordance with sub. (2).
NR 151.05(3)(b)2.2. The facility is designed to store manure for a period of time longer than 24 months.
NR 151.05(3)(b)3.3. Retention of the facility is warranted based on anticipated future use.
NR 151.05(4)(4)Existing facilities.
NR 151.05(4)(a)(a) Manure storage facilities in existence as of October 1, 2002, that pose an imminent threat to public health, fish and aquatic life, or groundwater shall be upgraded, replaced, or abandoned in accordance with this section.
NR 151.05(4)(b)(b) Levels of materials in storage facilities may not exceed the margin of safety level.
NR 151.05 NoteNote: Manure storage facilities are sometimes used to store non-agricultural wastes, such as septage or organic food wastes. These facilities may be subject to additional regulatory and cost-sharing requirements.
NR 151.05 HistoryHistory: CR 00-027: cr. Register September 2002 No. 561, eff. 10-1-02; CR 09-112: am. (title), (2) (a), (4), cr. (2) (am) Register December 2010 No. 660, eff. 1-1-11.
NR 151.055NR 151.055Process wastewater handling performance standard.
NR 151.055(1)(1)All livestock producers shall comply with this section.
NR 151.055(2)(2)There may be no significant discharge of process wastewater to waters of the state.
NR 151.055(3)(3)The department shall consider all of the following factors when determining whether a discharge of process wastewater is a significant discharge to waters of the state:
NR 151.055(3)(a)(a) Volume and frequency of the discharge.
NR 151.055(3)(b)(b) Location of the source relative to receiving waters.
NR 151.055(3)(c)(c) Means of process wastewater conveyance to waters of the state.
NR 151.055(3)(d)(d) Slope, vegetation, rainfall, and other factors affecting the likelihood or frequency of process wastewater discharge to waters of the state.
NR 151.055(3)(e)(e) Available evidence of discharge to a surface water of the state or to a direct conduit to groundwater as defined under s. NR 151.002 (11m).
NR 151.055(3)(f)(f) Whether the process wastewater discharge is to a site that is defined as a site susceptible to groundwater contamination under s. NR 151.015 (18).
NR 151.055(3)(g)(g) Other factors relevant to the impact of the discharge on water quality standards of the receiving water or to groundwater standards.
NR 151.055 NoteNote: Existing technical standards contained in the U.S. department of agriculture natural resources conservation service field office technical guide may be used for managing process wastewater. When such standards are not applicable, the landowner or operator is expected to take reasonable steps to reduce the significance of the discharge in accordance with the agricultural performance standard and prohibition compliance requirements of this chapter. The Wisconsin department of agriculture, trade and consumer protection is responsible under s. 281.16 (3) (c), Stats., for developing additional management practices if needed.
NR 151.055 HistoryHistory: CR 09-112: cr. Register December 2010 No. 660, eff. 1-1-11.
NR 151.06NR 151.06Clean water diversion performance standard.
NR 151.06(1)(1)All livestock producers within a water quality management area shall comply with this section.
NR 151.06(2)(2)Runoff shall be diverted away from contacting feedlot, manure storage areas and barnyard areas within water quality management areas except that a diversion to protect a private well under s. NR 151.015 (18) (a) is required only when the feedlot, manure storage area or barnyard area is located upslope from the private well.
NR 151.06 HistoryHistory: CR 00-027: cr. Register September 2002 No. 561, eff. 10-1-02; CR 09-112: am. (title) Register December 2010 No. 660, eff. 1-1-11.
NR 151.07NR 151.07Nutrient management.
NR 151.07(1)(1)All crop producers and livestock producers that apply manure or other nutrients directly or through contract to agricultural fields shall comply with this section.