NR 120.14(23)(b)9.9. The project sponsor prior to the payment of cost-share funds shall certify compliance with the manure management prohibitions in s. NR 151.08.
NR 120.14(23)(c)(c) Standards.
NR 120.14(23)(c)1.1. NRCS field office technical guides are as follows:
NR 120.14(23)(c)1.a.a. 312 — waste management system; January, 1987.
NR 120.14(23)(c)1.b.b. 313 — waste storage structure; September, 1998.
NR 120.14(23)(c)1.c.c. 634 — manure transfer; January, 1999.
NR 120.14(23)(c)1.d.d. 590 — nutrient management; March, 1999.
NR 120.14(23)(c)1.e.e. 382 — fence; November, 1999.
NR 120.14(23)(c)1.f.f. 561 — heavy use protection area; September, 1999.
NR 120.14(23)(c)2.2. Other standards as specified by the department.
NR 120.14(24)(24)Animal waste storage system abandonment.
NR 120.14(24)(a)(a) Description. Manure storage system abandonment is the permanent disabling and proper abandonment of leaking and improperly sited manure storage systems including a system with bottom at or below groundwater level; a system whose pit fills with groundwater; a system whose pit leaks into the bedrock; a system which has documented reports of discharging manure into surface water or groundwater due to structural failure; or a system with evidence of existing structural failure or evidence of imminent structural failure that will likely result in resource degradation. This practice shall be implemented using one or more of the standards in par. (c).
NR 120.14(24)(b)(b) Conditions.
NR 120.14(24)(b)1.1. Cost-sharing may be provided for the following practices to protect water resources from contamination by manure:
NR 120.14(24)(b)1.a.a. Proper removal and disposal of accumulated wastes in the pond or structure.
NR 120.14(24)(b)1.b.b. Removal of any constructed soil liner, concrete or membrane liner.
NR 120.14(24)(b)1.c.c. Removal of all soil saturated with waste, which can be removed.
NR 120.14(24)(b)1.d.d. Proper land spreading of excavated liner material and waste saturated soil.
NR 120.14(24)(b)1.e.e. Filling, shaping to insure surface drainage away from site, and seeding of area.
NR 120.14(24)(b)2.2. Cost-sharing may not be provided for removal and spreading of manure that can be removed using conventional equipment and routine agricultural practices.
NR 120.14(24)(c)(c) Standards.
NR 120.14(24)(c)1.1. Standards from the NRCS field office technical guide are as follows:
NR 120.14(24)(c)1.a.a. 312 — waste management system; January, 1987.
NR 120.14(24)(c)1.b.b. 313 — waste storage structure; September, 1998.
NR 120.14(24)(c)1.c.c. 634 — manure transfer; January, 1999.
NR 120.14(24)(c)1.d.d. 590 — nutrient management; March, 1999.
NR 120.14(24)(c)1.e.e. 382 — fence; November, 1999.
NR 120.14(24)(c)1.f.f. 561 — heavy use protection area; September, 1999.
NR 120.14(24)(c)2.2. Other standards as specified by the department.
NR 120.14(25)(25)Milking center waste control systems.
NR 120.14(25)(a)(a) Description. A milking center waste control system is a piece of equipment, practice or combination of practices installed in a milking center for purposes of reducing the quantity or pollution potential of the wastes. This practice shall be implemented using one or more of the standards in par. (c).
NR 120.14(25)(b)(b) Conditions.
NR 120.14(25)(b)1.1. Cost-sharing may be provided for:
NR 120.14(25)(b)1.a.a. Design and construction of filter strip systems with appropriate pretreatment measures, storage systems and land irrigation equipment.
NR 120.14(25)(b)1.b.b. Repair or modification of existing milking center waste control measures.
NR 120.14(25)(b)1.c.c. Stationary waste transfer equipment, such as piping and pumps, needed to convey milking center wastes to storage, treatment or land application systems provided that the equipment is an integral component of the system and is designed for that exclusive use.
NR 120.14(25)(b)1.d.d. Other milking center waste control measures when they are needed to assure that the milking center waste treatment systems will meet identified water quality objectives. These measures may include conservation sinks, pre-cooler water utilization systems, manifold cleaning systems, air injection systems, waste milk diverter valves, booster pumps for parlor floor cleaning and other measures as approved by the department.
NR 120.14(25)(b)2.2. Cost-sharing may not be provided for:
NR 120.14(25)(b)2.a.a. Design and construction of systems, practices or components that are installed or adopted for purposes other than for the correction of an identified water pollution hazard.
NR 120.14(25)(b)2.b.b. Buildings or modifications to buildings, unless modifications to buildings are essential for installation of a milking center waste control system.
NR 120.14(25)(b)2.c.c. Portable equipment for spreading milking center wastes onto land or incorporating the wastes into land.
NR 120.14(25)(c)(c) Standards.
NR 120.14(25)(c)1.1. Standards from the NRCS field office technical guide are as follows:
NR 120.14(25)(c)1.a.a. 635 — wastewater treatment strip; July, 2001.
NR 120.14(25)(c)1.b.b. 634 — manure transfer; January, 1999.
NR 120.14(25)(c)1.c.c. 614 — trough or tank; September, 1989.
NR 120.14(25)(c)1.d.d. 313 — waste storage facility; September, 1998.
NR 120.14(25)(c)1.e.e. 590 — nutrient management; March, 1999.
NR 120.14(25)(c)2.2. Milking center waste control systems shall be planned in accordance with the Pollution Control Guide for Milking Center Wastewater Management (UWEX Pub. No. A3592-July, 1994), which is incorporated by reference for this chapter and designed in accordance with standards approved by the department.
NR 120.14 NoteNote: Copies of this document may be inspected at the offices of the Department’s Bureau of Watershed Management, NRCS, the Secretary of State and the Legislative Reference Bureau, all in Madison, WI.
NR 120.14(26)(26)Roofs for barnyard runoff management and manure storage facilities.
NR 120.14(26)(a)(a) Description. Roofs for barnyard runoff management and manure storage facilities are a roof and supporting structure constructed specifically to prevent precipitation from contacting manure. This practice shall be implemented using the standards in par. (c).
NR 120.14(26)(b)(b) Conditions.
NR 120.14(26)(b)1.1. Cost-sharing may not be provided for materials and labor for other structures or buildings.
NR 120.14(26)(b)2.2. The roofed structure may not be permanently enclosed unless the landowner receives written approval from the department.
NR 120.14(26)(b)2.a.a. For purposes of this subsection, a permanently enclosed structure is defined as a structure where the sum of the length of the walls exceeds 50% of the total length of the perimeter of the structure. When the structure has a shape other than a rectangle or square, each rectangular or square portion of the total structure, excluding the common sides, shall be calculated separately to determine whether it exceeds 50%. A segment of the perimeter shall be considered a wall if greater than 50% of the opening from eave to floor is of solid building material.
NR 120.14(26)(b)2.b.b. An application requesting cost-sharing for the enclosure of a roofed barnyard runoff management system shall be submitted in writing to the department for its approval. The written application and the applicable cost-share agreement shall include a recognition by the landowner or land operator that the barnyard may not be used for purposes other than an animal lot for the duration of the cost-share agreement.
NR 120.14(26)(b)3.3. The livestock facility may not establish additional outdoor animal lots on the site unless the department certifies that adequate runoff control practices are established for the duration of the cost-share agreement.
NR 120.14(26)(c)(c) Standards.
NR 120.14(26)(c)1.1. The roof shall be designed to support wind, snow and other live and dead loads consistent with the American Society of Agricultural Engineers (ASAE) Engineering Practice (EP) 288.5, 1992, which is incorporated by reference for this chapter.
NR 120.14 NoteNote: Copies of this publication are available for inspection at the central office of the department of Natural Resources, and the offices of the Legislative Reference Bureau and Secretary of State.
NR 120.14(26)(c)2.2. The roof and supporting structure shall be constructed of materials with a life expectancy of a minimum of 10 years.
NR 120.14(26)(c)3.3. The structure shall have sufficient ventilation.
NR 120.14(27)(27)Livestock fencing.
NR 120.14(27)(a)(a) Description. Livestock fencing is the enclosure, separation or division of one area of land from another in a manner that provides a permanent barrier to livestock. The purpose of the practice is to exclude livestock from land areas that should be protected from grazing or gleaning where degradation of the natural resource will likely result if livestock access is permitted. This practice shall be implemented using one or more of the standards in par. (c).
NR 120.14(27)(b)(b) Conditions.
NR 120.14(27)(b)1.1. Cost-sharing may be provided for permanent fencing when fencing is needed to:
NR 120.14(27)(b)1.a.a. Eliminate the degradation of a surface water body.
NR 120.14(27)(b)1.b.b. Reduce the impact to a resource from sedimentation that is being caused by livestock.
NR 120.14(27)(b)1.c.c. Exclude livestock from a forest or woodlot.
NR 120.14(27)(b)1.d.d. Eliminate the degradation of other natural resources as defined within the approved priority watershed plan, priority lake plan, notice of discharge or project grant application.
NR 120.14(27)(b)2.2. Cost-sharing may not be provided for:
NR 120.14(27)(b)2.a.a. Fencing of cropland fields for the primary purpose of providing areas for gleaning by livestock or for handling or segregating of livestock.
NR 120.14(27)(b)2.b.b. Temporary fencing.
NR 120.14(27)(b)2.c.c. Situations where benefits to water quality improvement cannot be readily defined.
NR 120.14(27)(b)2.d.d. Electric fence energizers.
NR 120.14(27)(c)(c) Standards and specifications. NRCS field office technical guide standards and specifications are as follows:
NR 120.14(27)(c)1.1. 382 — fence; November, 1999.
NR 120.14(27)(c)2.2. 472 — livestock exclusion; June, 1983.
NR 120.14(28)(28)Urban best management practices.
NR 120.14(28)(a)(a) Description. Urban best management practices include structural urban best management practices and other source area measures, transport system and end-of-pipe measures designed to control storm water runoff rates, volumes and discharge quality. In this definition, “source area” means a component of urban land use including rooftops, sidewalks, driveways, parking lots, storage areas, streets and lawns from which storm water pollutants are generated during periods of snowmelt and rainfall runoff.
NR 120.14(28)(b)(b) Conditions.
NR 120.14(28)(b)1.1. Cost-sharing may be provided for:
NR 120.14(28)(b)1.a.a. Excavation, grading, mulching, seeding, necessary landscaping, piping, drop spillways and other measures required to implement the practice.
NR 120.14(28)(b)1.b.b. Land acquisition, including storm sewer rerouting and the removal of structures necessary to install structural urban best management practices.
NR 120.14(28)(b)1.c.c. Materials and labor for the initial installation of groundwater monitoring wells required by the department.
NR 120.14(28)(b)1.d.d. On a prorated basis, for multi-purpose practices which manage both water quality and unrelated water quantity problems.
NR 120.14(28)(b)2.2. Cost-sharing under this chapter may not be provided for:
NR 120.14(28)(b)2.a.a. Urban best management practices, land acquisition, storm sewer rerouting or removal of structures where the practices serve solely to solve drainage and flooding problems unrelated to the primary water quality improvement strategy in a priority watershed or lake plan or application selected for funding under this chapter.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.