DHS 163.14(5)(c)8.8. ‘Interpretation of laboratory results.’ Compare the residual lead level from each dust sample, as determined by laboratory analysis, with the applicable clearance level for lead in dust on floors, interior windowsills and window troughs. If the residual lead level in a dust sample equals or exceeds the applicable clearance level, all of the components represented by the failed sample shall be recleaned or sealed by the person who conducted the activity being cleared and retested by the person conducting clearance until clearance levels are met. For dust wipe samples taken during clearance, clearance is achieved when the laboratory result for a sample is less than the following:
DHS 163.14(5)(c)8.a.a. Ten micrograms per square foot (10 mg/ft2) on an interior floor.
DHS 163.14(5)(c)8.am.am. Forty micrograms per square foot (40 mg/ft2) on a porch floor.
DHS 163.14(5)(c)8.b.b. One hundred micrograms per square foot (100 mg/ft2) on an interior windowsill.
DHS 163.14(5)(c)8.c.c. One hundred micrograms per square foot (100 mg/ft2) on window wells or troughs.
DHS 163.14(5)(c)9.9. ‘Preparation of report following clearance of activities involving abatement.’ Within 10 working days after clearance of activities involving abatement or within 10 working days after receipt of any required laboratory results, whichever is later, prepare a written clearance report for submission to the person who conducted the activities being cleared and to the property owner or the person who contracted for the clearance. The report shall include all of the following information:
DHS 163.14(5)(c)9.a.a. Date and time of the clearance.
DHS 163.14(5)(c)9.b.b. Address of the job site, including street address and unit number when applicable.
DHS 163.14(5)(c)9.c.c. Name, address, telephone number and certification number of each individual and lead company conducting the clearance and signature of each certified lead hazard investigator, inspector, risk assessor or sampling technician.
DHS 163.14(5)(c)9.cm.cm. The description and results of the visual inspection for the presence of visible dust, debris, residue, or paint chips and the presence of deteriorated paint.
DHS 163.14(5)(c)9.cr.cr. The specific locations on the property where clearance samples were taken.
DHS 163.14(5)(c)9.d.d. A copy of the laboratory report with the results of clearance testing and, if applicable, all soil analyses. The clearance report shall include the name, address and telephone number of each laboratory that conducted the analyses.
DHS 163.14(5)(c)10.10. ‘Preparation of report following clearance of interim controls or renovation activities.’ Within 10 working days after clearance of interim controls or renovation activities or within 10 working days after receipt of any required laboratory results, whichever is later, prepare a written clearance report for submission to the person who conducted the activities being cleared and to the property owner or the person who contracted for the clearance. The report shall include all of the following information:
DHS 163.14(5)(c)10.a.a. All information under subd. 9.
DHS 163.14(5)(c)10.b.b. The start and completion dates of the non-abatement lead-based paint activity.
DHS 163.14(5)(c)10.c.c. The name and address of each company conducting the interim controls or renovation activities.
DHS 163.14(5)(c)10.d.d. The name and department certification number of the person in charge of the work.
DHS 163.14(5)(c)10.e.e. A description of the interim controls or renovation activities.
DHS 163.14(5)(c)11.11. ‘Submission of clearance results involving registered lead-safe property.’ Within 10 working days after receipt of clearance results involving a registered lead-safe property, the certified person who conducted the clearance shall submit all of the following clearance information to the department on a form obtained from the department:
DHS 163.14(5)(c)11.a.a. The registered lead-safe property identification number as shown on the lead-safe certificate.
DHS 163.14(5)(c)11.b.b. The address of the property as shown on the lead-safe certificate.
DHS 163.14(5)(c)11.c.c. The name and lead certification identification number of the primary person who conducted the clearance.
DHS 163.14(5)(c)11.d.d. The name and department-issued lead identification number of the recognized laboratory that processed the clearance samples.
DHS 163.14(5)(c)11.e.e. The clearance results as reported by the recognized laboratory.
DHS 163.14 NoteNote: Submit required information by mail to the Lead and Asbestos Section, 1 W. Wilson Street, Room 137, Madison WI 53703-3445, by email to dhsasbestoslead@wi.gov, or by fax to 608-266-9711.
DHS 163.14(6)(6)Elevated blood lead investigation.
DHS 163.14(6)(a)(a) Who may conduct. Only a certified lead hazard investigator or risk assessor may perform an elevated blood lead investigation.
DHS 163.14(6)(b)(b) Elevated blood lead investigation protocol. An elevated blood lead investigation in response to a child with lead poisoning shall be conducted according to documented methodologies consistent with funding criteria and guidance issued to public health agencies by the department.
DHS 163.14(7)(7)Lead hazard screen.
DHS 163.14(7)(a)(a) Who may perform. Only a certified lead hazard investigator or risk assessor associated with a certified lead company may perform a lead hazard screen involving target housing or a child-occupied facility. Under direct on-site supervision of a certified lead hazard investigator or risk assessor, a certified lead inspector or sampling technician may assist with a lead hazard screen.
DHS 163.14(7)(b)(b) Lead hazard screen protocol. In performing a lead hazard screen, the certified lead hazard investigator or risk assessor shall comply with all requirements under pars. (c) to (g).
DHS 163.14(7)(c)(c) Background information. Collect background information on the physical characteristics of the residential dwelling or child-occupied facility and occupant use patterns that may cause lead-based paint exposure to a child under 6 years of age.
DHS 163.14(7)(d)(d) Deteriorated paint. Conduct a visual inspection of the real property to determine if any deteriorated paint is present. Treat untested deteriorated paint as lead-based paint. If a contract under s. DHS 163.13 (5) (d) specifies that sampling for the presence of lead-based paint should be conducted, do all of the following:
DHS 163.14(7)(d)1.1. Use documented methodologies that incorporate adequate quality control procedures to sample or test each testing combination with deteriorated paint.
DHS 163.14(7)(d)2.2. Have all collected paint chip samples analyzed by a recognized laboratory to determine if they contain detectable levels of lead that can be quantified numerically.
DHS 163.14(7)(d)3.3. Determine that lead-based paint is present if the laboratory results are more than 0.5% lead by weight or that lead-based paint is not present if the laboratory results are equal to or less than 0.5% lead by weight.
DHS 163.14 NoteNote: Refer to s. DHS 163.03 (29) for documented methodologies.
DHS 163.14(7)(e)(e) Dust-lead.
DHS 163.14(7)(e)1.1. Collect 4 dust samples from the floors and 4 dust samples from the windows, in rooms, hallways, stairwells or other living areas where a child under 6 years of age is most likely to come into contact with dust.
DHS 163.14(7)(e)2.2. In multi-family dwellings and child-occupied facilities, collect dust samples from common areas where a child under 6 years of age is most likely to come into contact with dust in addition to samples collected under subd. 1.
DHS 163.14(7)(e)3.3. Collect all dust samples by using documented methodologies that incorporate adequate quality control procedures.
DHS 163.14(7)(e)4.4. Have all collected dust samples analyzed by a recognized laboratory to determine if they contain detectable levels of lead that can be quantified numerically.
DHS 163.14(7)(f)(f) Lead-based paint hazards. Evaluate the results of the lead hazard screen against the lead-based paint hazard levels under s. DHS 163.15 to determine whether a lead-based paint hazard is present.
DHS 163.14(7)(g)(g) Written report. Within 10 working days after a lead hazard screen or receipt of any required laboratory results, whichever is later, prepare a written lead hazard screen report for submission to the person who contracted for the lead hazard screen. The report shall include all of the following information:
DHS 163.14(7)(g)1.1. Date of the lead hazard screen.
DHS 163.14(7)(g)2.2. Address of each building screened.
DHS 163.14(7)(g)3.3. Date of construction of buildings.
DHS 163.14(7)(g)4.4. Apartment number of units screened, if applicable.
DHS 163.14(7)(g)5.5. Name, address and telephone number of each current owner of each building.
DHS 163.14(7)(g)6.6. Name, address, telephone number, certification number and signature of each certified individual participating in the lead hazard screen.
DHS 163.14(7)(g)7.7. Name, address, telephone number and certification number of the certified lead company conducting the lead hazard screen.
DHS 163.14(7)(g)8.8. Name, address and telephone number of each recognized laboratory conducting analysis of collected samples.
DHS 163.14(7)(g)9.9. Background information collected under par. (c).
DHS 163.14(7)(g)10.10. Results of the visual inspection.
DHS 163.14(7)(g)11.11. Description of testing method and sampling procedure used for paint analysis.
DHS 163.14(7)(g)12.12. Specific locations of each painted component tested for the presence of lead.
DHS 163.14(7)(g)13.13. All data collected from on-site testing, including quality control data and, if used, the serial number of any XRF.
DHS 163.14(7)(g)14.14. A copy of the laboratory report of the analysis of collected paint, soil, and dust samples.
DHS 163.14(7)(g)15.15. A written evaluation of the sample analysis results that were provided by the laboratory.
DHS 163.14(7)(g)16.16. Recommendations, if warranted, for a follow-up risk assessment and, as appropriate, any further actions.
DHS 163.14(8)(8)Lead inspection and partial lead inspection.
DHS 163.14(8)(a)(a) Who may conduct. Only a certified lead inspector or risk assessor associated with a certified lead company may perform an inspection involving target housing or a child-occupied facility. Under direct on-site supervision of a certified lead inspector or risk assessor, a certified lead hazard investigator or sampling technician may assist with an inspection, but may not use an XRF.
DHS 163.14(8)(b)(b) Inspection protocol. In performing an inspection, the certified lead inspector or risk assessor shall comply with all requirements under pars. (c) to (f).
DHS 163.14(8)(c)(c) Locations to test for lead-based paint. Select the following locations by using documented methodologies and test for the presence of lead-based paint:
DHS 163.14(8)(c)1.1. In a dwelling or child-occupied facility, test each interior and exterior testing combination.
DHS 163.14(8)(c)2.2. In a multi-family dwelling or child-occupied facility, also test each interior and exterior testing combination in every common area.
DHS 163.14(8)(c)3.3. When a partial inspection is conducted to determine if lead-safe work practices are required in an area to be renovated, test each interior and exterior testing combination within that area in accordance with subd. 1. or 2. The inspection shall be based on a written contract under s. DHS 163.13 (5) that specifies the limits of the partial inspection. A partial inspection may not be conducted when a certificate of lead-free status is being sought.
DHS 163.14 NoteNote: Refer to s. DHS 163.03 (29) for documented methodologies.
DHS 163.14(8)(d)(d) Paint analysis. Conduct paint analysis by using one or both of the following methods:
DHS 163.14(8)(d)1.1. Analyze paint to determine the presence of lead by using documented methodologies that incorporate adequate quality control procedures.
DHS 163.14(8)(d)2.2. Have all collected paint chip samples analyzed by a recognized laboratory to determine if they contain detectable levels of lead that can be quantified numerically.
DHS 163.14(8)(e)(e) XRF requirements. When using an XRF, a certified lead inspector or risk assessor shall be trained to operate the specific model of XRF being used and shall do all of the following:
DHS 163.14(8)(e)1.1. Comply with radiation protection requirements under ch. DHS 157.
DHS 163.14(8)(e)2.2. Replace the radiation source of the XRF according to recommendations from the manufacturer.
DHS 163.14(8)(e)3.3. Warm up the XRF according to recommendations from the manufacturer or documented methodologies.
DHS 163.14(8)(e)4.4. Conduct calibration checks according to recommendations from the manufacturer or documented methodologies.
DHS 163.14(8)(e)5.5. Conduct substrate corrections when required.
DHS 163.14(8)(e)6.6. If the XRF provides an inconclusive reading according to the performance characteristics sheet for the make and model of XRF used, assume the painted surface with the inconclusive reading contains lead-based paint unless sampling is required by contract. If a contract under s. DHS 163.13 (5) (d) specifies that sampling for the presence of lead-based paint should be conducted, conduct further testing or sampling and determine that lead-based paint is present if the laboratory results are more than 0.5% lead by weight or that lead-based paint is not present if the laboratory results are equal to or less than 0.5% lead by weight.
DHS 163.14(8)(e)7.7. Except as specified under subd. 6., evaluate the results of each XRF reading as follows:
DHS 163.14(8)(e)7.a.a. If the XRF reading exceeds 1 milligram per square centimeter, determine that lead-based paint is present.
DHS 163.14(8)(e)7.b.b. If the XRF reading is less than or equal to 1 milligram per square centimeter, determine that lead-based paint is not present.
DHS 163.14(8)(f)(f) Written report. Within 10 working days after an inspection or receipt of any required laboratory results, whichever is later, prepare a written inspection report for submission to the property owner or owners and to any other person who contracted for the inspection. The report shall include all of the following information:
DHS 163.14(8)(f)1.1. Date of the inspection.
DHS 163.14(8)(f)2.2. Address of building inspected.
DHS 163.14(8)(f)3.3. Date of construction of the building.
DHS 163.14(8)(f)4.4. Apartment numbers of units inspected, if applicable.
DHS 163.14(8)(f)5.5. Name, address and telephone number of the current owner of each residential dwelling or child-occupied facility.
DHS 163.14(8)(f)6.6. Name, address, telephone number, certification number and signature of each certified individual participating in the inspection.
DHS 163.14(8)(f)7.7. Name, address, telephone number and certification number of the certified lead company conducting the inspection.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.