Trans 400.04(6)
(6) “DEIS" or “draft environmental impact statement" means the preliminary version of an EIS.
Trans 400.04(7)
(7) “EA" or ``environmental assessment" means a concise, comprehensive document containing an analysis of a proposed action to determine the significance of the action's environmental effects and whether or not the action constitutes a major action.
Trans 400.04(8)
(8) “Environmental effect" or “environmental impact" means a beneficial or adverse influence resulting from an action of the department. The term includes ecological, aesthetic, historic, cultural, economic, social or health effects.
Trans 400.04(9)
(9) “EIS" or “environmental impact statement" means a written report containing an analysis of a proposed major action and its alternatives to identify and address their effects on the quality of the human environment.
Trans 400.04(10)
(10) “ER" or
“environmental report" means a brief
document used internally by the department to demonstrate a proposed action fits the criteria
or conditions for approval as a categorical exclusion under s.
Trans 400.08 (1)
(d) or
has been properly coordinated with other agencies having jurisdiction by law over specific activities.
Trans 400.04(11)
(11) “FEIS" or “final environmental impact statement" means the final version of an EIS.
Trans 400.04(12)
(12) “FONSI" or "finding of no significant impact" means an approved, completed EA containing a finding that the proposed action is not a major action.
Trans 400.04(13)
(13) “Human environment" means the natural or physical environment and the relationship of people with that environment.
Trans 400.04(14)
(14) “Joint lead agency" means the department together with any local, state or federal agency having equal responsibility for the preparation, content and processing of an environmental document for a proposed action.
Trans 400.04(16)
(16) “Lead agency" means the local, state or federal agency preparing or having taken primary responsibility for preparing the environmental document for a proposed action.
Trans 400.04(17)
(17) “LEIS" or “legislative environmental impact statement" means a written report containing an analysis to identify and address the effects on the quality of the human environment of a department-initiated report or recommendation on a proposal for legislation.
Trans 400.04(18)
(18) “Major action" means an action that will have significant effects on the quality of the human environment. It does not include actions whose significance is based only on economic or social effects.
Trans 400.04(19)
(19) “Major and significant new proposal" means a new proposal developed by the department which, if legislatively authorized and funded, may significantly affect the quality of the human environment and represents a significant departure from, or expansion of, the department's existing responsibilities by substantially expanding or substantially reducing total resources allocated to any existing programs.
Trans 400.04(20)
(20) “Mitigation" means avoiding, minimizing, rectifying, reducing, eliminating or compensating for adverse environmental effects of a proposed action.
Trans 400.04(22)
(22) “Notice of availability," “notice of intent," “notice of opportunity for public hearing" or “notice of public hearing" means a class 1 notice as defined in ch.
985, Stats.
Trans 400.04(22m)
(22m) “
Participating agency" means any Native American
tribe or
any
local,
state,
or
federal
agency, other
than
the
lead
agency, with
an
interest
in the project. “Participating agency" includes cooperating agencies but does not include nongovernmental organizations or other private
entities.
Trans 400.04(23)
(23) “ROD" or “record of decision" means a public record which identifies:
Trans 400.04(24)
(24) “Reevaluation" means the review of an approved
draft
or
final
environmental
document, including DEIS, FEIS, ROD, EA, FONSI, ER, and CE,
to
assess
whether
there
have
been changes in the proposed action, the applicable laws, regulations, or policies, the affected human environment, the anticipated environmental impacts, or the proposed mitigation
measures.
Trans 400.04(25)
(25) “Scoping" means an early, open process with the public and public agencies for identifying the anticipated range of issues for a proposed action.
Trans 400.04(26)
(26) “Significant effects" means considerable and important impacts of department actions on the quality of the human environment.
Trans 400.04(27)
(27) “SEE" or “system-plan environmental evaluation" means a conceptual environmental evaluation, that shall be considered the “detailed statement" required by statute commonly known as“environmental impact statement," developed as an integral element of a system plan that contemplates that if the plan recommendations are implemented, there will be subsequent project or site-specific environmental reviews. A SEE also serves as the LEIS regarding reports or recommendations on legislation required to implement the plan.
Trans 400.04(28)
(28) “System plan" means a plan which identifies transportation facility or service needs for a statewide system. The needs are identified conceptually without addressing specific design and locational details.
Trans 400.04(29)
(29) “Tiering" means the coverage of general matters in a broad EIS with subsequent narrower statements or environmental analyses which incorporate by reference the general discussion of the EIS.
Trans 400.04 History
History: Cr.
Register, April, 1992, No. 436, eff. 5-1-92
; am. (7) and (12),
Register, February, 1999, No. 518, eff. 3-1-99;
CR 16-069: am. (3) to (5), (10), r. (15), cr. (22m), am. (24) Register October 2019 No. 766, eff. 11-1-19. Trans 400.05
Trans 400.05
Federal regulations adopted. References throughout this chapter to federal regulations and orders are hereby adopted by the department and are attached hereto in appendix 1:
23 CFR 771.115,
771.116,
771.117, and
771.118, April 1, 2015;
40 CFR 1500.4,
1500.5,
1506.8, and
1508.4, July l, 2015;
49 CFR 266.19, October 1, 2014; and the United States department of transportation federal aviation administration order 5050.4B, chapters 6, 7, and 9, April 28, 2006.
Trans 400.06(1)(1)
The department shall strive to protect and enhance the quality of the human environment in carrying out its basic transportation mission and shall consider pertinent environmental factors consequential to any proposed actions. The policy expressed in this section and the procedures defined in this chapter shall be implemented as an integrated process beginning during the initial planning stage for department action.
Trans 400.06(2)
(2) The department acknowledges WEPA as a legal obligation shared by all divisions of the department to evaluate and be aware of environmental consequences of proposed actions.
Trans 400.06(3)
(3) Alternative courses of action shall be evaluated and decisions on proposed actions shall be made in the best overall public interest consistent with state and federal statutes and regulations. Decisions on proposed actions shall be based upon a balanced consideration of the findings of the environmental document, public comments, and the need for safe and efficient transportation consistent with local, state and national environmental goals.
Trans 400.06(4)
(4) Public involvement, interagency coordination and consultation, and a systematic interdisciplinary approach to analysis of the issues shall be essential parts of the environmental process for proposed actions.
Trans 400.06(5)
(5) Measures necessary for
the mitigation of adverse environmental impacts of proposed actions shall be part of
the development and evaluation of
alternatives.
Trans 400.06(6)
(6) The department shall implement procedures to make the WEPA process more useful to decision makers and the public by reducing paperwork and reducing delay utilizing the means for achieving these goals as specified in the rules of the United States council on environmental quality at
40 CFR 1500.4 and
1500.5, which are attached hereto in appendix 1. Environmental documents shall be concise, clear, and to the point and emphasize real environmental issues and alternatives.
Trans 400.06(7)
(7) In carrying out its responsibility under s.
1.11, Stats., the department shall substantially follow the guidelines issued as rules by the United States council on environmental quality and federal transportation agencies.
Trans 400.06 History
History: Cr.
Register, April, 1992, No. 436, eff. 5-1-92;
CR 16-069: am. (5), (6) Register October 2019 No. 766, eff. 11-1-19; correction in (1) made under s. 35.17, Stats., Register October 2019 No. 766. Trans 400.07
Trans 400.07
Action designation and environmental documentation. Trans 400.07(1)(1)
The designations, EIS and CE shall be used to categorize department actions. Actions designated EIS actions shall be considered major actions, and actions designated CE shall be considered categorical exclusions. An EA and an ER describe procedures to be followed to categorize department actions. The EA process yields a determination whether an action requires an EIS or a finding of no significant impact. The ER process confirms whether an action falls within a categorical exclusion or requires further evaluation and documentation.
Trans 400.07(2)
(2) Actions and procedures designated
EIS, EA or ER shall require the following environmental
documentation:
Trans 400.07(2)(a)
(a)
EIS or LEIS. An EIS action is a major action. An LEIS may be prepared for a major and significant new proposal.
Trans 400.07(2)(a)1.
1. An environmental impact statement, or EIS, shall be prepared for major actions.
Trans 400.07(2)(a)2.
2. A legislative environmental impact, or LEIS, may be prepared when a major and significant new proposal consists of a report or recommendation of the department on a proposal for legislation initiated by the department that is not within the scope of any categorical exclusion.
Trans 400.07(2)(b)
(b)
EA, SEE or screening sheet. An EA is a procedure followed for an action for which the significance of the environmental impact is not clearly established. An EA, SEE or screening sheet may be used as follows:
Trans 400.07(2)(b)1.
1. An EA shall be prepared for those project actions for which the significance of the environmental impact is not clearly established. If it is
concluded from
the
analysis in
the
EA
that the
action is
a
major action, an
EIS
shall be prepared. If it is concluded from the analysis in the EA that the action is not a major action, the EA shall be revised to constitute a FONSI, and the FONSI shall serve as the environmental document. The FONSI shall be prepared only after -
See PDF for diagram availability of the EA for public, and cooperating and participating agency, review and
comment
and
the
incorporation
of
any
appropriate
revisions
resulting
from
the public involvement process. Where a permit will be required or other agency coordination is
specifically
required
by
law, the
FONSI
may
serve
as
the
vehicle
for such permit or coordinating agency
approval.
Trans 400.07(2)(b)2.
2. A SEE may be prepared in the case of proposals contained in system plans, if it is concluded they are major and significant new proposals. If it is concluded from an analysis of the system plan that it does not contain any major and significant new proposals, a clear statement of that determination may be incorporated within the system plan or as a separately identifiable and retained record of the department's determination.
Trans 400.07(2)(b)3.
3. In the case of reports or recommendations of the department on proposals for legislation initiated by the department, if it is concluded from the screening sheet they contain major and significant new proposals, an LEIS may be prepared. If it is concluded from the screening sheet that they do not contain any major and significant new proposals or are within the scope of any categorical exclusion, a clear statement of that determination may be included on the screening sheet.
Trans 400.07(2)(c)
(c)
ER. An ER is a procedure followed for an action that is likely to fit the criteria for a conditional categorical exclusion in
23 CFR 771.117 (d),
23 CFR 771.118 (d), or federal aviation administration order 5050.4B, chapter 6, paragraph 605, or otherwise requires coordination with or concurrence of another agency. An environmental report, or ER, shall be prepared to demonstrate whether the proposed action does fit the criteria or conditions for approval as a categorical exclusion and has been properly coordinated with other agencies having jurisdiction by law over specific activities. The ER shall serve as the department's record of coordination with other agencies having jurisdiction over specific activities, including the following activities:
Trans 400.07(2)(c)1.
1. Construction-related activities including, but not limited to, stream crossings, fills in wetlands and temporary structures in or over streams or wetlands.
Trans 400.07(2)(c)2.
2. Defined land use acquisition including, but not limited to, the acquisition of agricultural lands, historic or archeological sites, and state, county or national forest lands.
Trans 400.07 History
History: Cr.
Register, April, 1992, No. 436, eff. 5-1-92; am. (1), (2) (intro.), (a), (b) and (c) (intro.),
Register, February, 1999, No. 518, eff. 3-1-99;
CR 16-069: am. (2) (intro.), (b) 1., (c) (intro.) Register October 2019 No. 766, eff. 11-1-19. Trans 400.08
Trans 400.08
Categorization of department actions. Trans 400.08(1)(1)
Based on federal regulations and past experience with analysis of similar actions the following are categorized as EIS, EA, ER or CE:
Trans 400.08(1)(a)
(a)
EIS — Environmental Impact Statement. The following are examples of department
major actions that normally require the preparation of an environmental impact statement:
Trans 400.08(1)(a)1.c.
c. Construction or extension of a fixed transit facility, such as rapid rail, light rail, commuter rail, or
bus
rapid
transit that
will
not
be
located
within an existing transportation right-of-way.
Trans 400.08(1)(a)1.d.
d. New construction or extension of a separate roadway for buses or high occupancy vehicles not located within an existing highway facility.
Trans 400.08(1)(a)2.a.a. Unconditionally approving or funding
the first
airport
layout
plan
or
airport
location
for
a
new
commercial service located in a metropolitan statistical
area.
Trans 400.08(1)(a)2.b.
b. Unconditionally approving or funding a new runway to accommodate air carrier aircraft at a commercial service airport located in a metropolitan statistical area.
Trans 400.08 Note
Note: The federal highway administration regulations at
23 CFR 771.115 (a) and federal aviation administration order 5050.4B, chapter 9, paragraph 903, identify types of federally funded actions which normally require the preparation of an environmental impact statement.
Trans 400.08(1)(b)
(b)
EA — Environmental Assessment. EA procedures apply to actions for which the significance of the environmental impacts is not clearly established and require the preparation of an environmental assessment to make that determination.
Trans 400.08(1)(b)1.
1. `Highways and transit.' In addition to actions the department determines to meet the criteria for an EA action under this chapter, the department may apply EA procedures to the highway and transit actions generally identified in
23 CFR 771.115 (c).
Trans 400.08(1)(b)2.
2. `Airports.' In addition to actions the department determines to meet the criteria for an EA action under this chapter, the department may apply EA procedures to actions generally identified in federal aviation administration order 5050.4B.
Trans 400.08(1)(b)3.
3. `Administrative facilities.' Examples of department actions regarding administrative facilities to which EA procedures normally apply are: construction of a new or replacement administrative building, including an office building, state patrol academy, driver licensing and testing station, state patrol communications building, or other similar facility, at a new location.
Trans 400.08(1)(b)4.
4. `Financial assistance.' This provision applies to issuance as well as acceptance of the following grants by the department:
Trans 400.08(1)(b)4.c.
c. Financial grant for construction of a new disposal facility for harbor dredge material.
Trans 400.08(1)(b)4.d.
d. Financial grant for dredging of material for the purpose of expanding an existing harbor.
Trans 400.08(1)(b)4.e.
e. Financial grant for disposal of contaminated harbor dredge material into a new disposal facility.
Trans 400.08(1)(b)5.
5. `Policy, contract, standard and specification changes.' Examples of department actions regarding policy, contract, standard, and specification changes to which EA procedures normally apply are:
Trans 400.08(1)(b)5.a.
a. Change in policy for nonhighway use of highway right-of-way or non-railroad use of railroad right-of-way by utility companies, or for access to public roads or private residential or commercial driveways or farm crossings.
Trans 400.08(1)(b)5.b.
b. Change in policy for transport of hazardous cargo, such as explosives, hazardous wastes, toxins, radioactive material, or any other similar cargo.
Trans 400.08(1)(b)5.c.
c. Change in policy for the maintenance program relating to the use of deicing materials, or to the use of pesticides, herbicides or insecticides within the right-of-way, or to the use of cutback asphalt or creosoted ties, or other similar materials.
Trans 400.08(1)(b)6.
6. `System planning.' Publication or adoption of a system plan. Preparation of a SEE or EA for a system plan is discretionary.
Trans 400.08(1)(c)
(c)
CE — Categorical Exclusions. CE actions are categorically excluded from the requirement to prepare environmental documentation because, based on past experience with similar actions, they do not involve significant environmental impacts. They are actions which do not induce significant impacts to planned growth or land use for the area, do not require the relocation of significant numbers of people, do not have a significant impact on any natural, cultural, recreational, historic or other resource, do not involve significant air, noise, or water quality impacts, do not have significant impacts on travel patterns, and do not otherwise, either individually or cumulatively, have any significant environmental impacts.
Trans 400.08(1)(c)1.
1. `Highways, transit, and rail.' In addition to actions the department determines to meet the criteria for a CE action under this chapter, the department may classify as CE actions those highway, transit, and rail actions identified in
23 CFR 771.116 (c),
23 CFR 771.117 (c), and
23 CFR 771.118 (c).