This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
Trans 28.05(2)(f)(f) The project has a lower priority than others requiring harbor assistance program funding during the current biennium.
Trans 28.05(2)(g)(g) The eligible applicant has not met the program planning requirements under s. Trans 28.10.
Trans 28.05(2)(h)(h) The project proposed is inconsistent with applicable harbor development plans or local comprehensive plans.
Trans 28.05(3)(3)The department shall establish an advisory council, under authority of s. 15.04 (1) (c), Stats., to evaluate harbor assistance program project applications. The advisory council shall include a representative of the Wisconsin Economic Development Corporation and of the Wisconsin coastal management council and shall include 2 or 3 other persons familiar with water transportation. Consistent with this chapter, the advisory council shall evaluate and rank the proposed projects and shall recommend to the department the priority of the projects to be funded.
Trans 28.05 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; correction in (2) (g) made under s. 13.93 (2m) (b) 7., Stats., Register, December, 1987, No. 384; CR 01-117: am. (1) (a) 1., (c), and (3) Register March 2002 No. 555, eff. 4-1-02; CR 05-019: am. (1) (b) 2. d. to f., (2) (e) and (g) Register July 2005 No. 595, eff. 8-1-05; correction in (3) made under s. 13.92 (4) (b) 6., Stats., Register January 2012 No. 673; correction in (3) made under s. 13.92 (4) (b) 6., Stats., Register January 2012 No. 673; correction in (3) made under s. 13.92 (4) (b) 6., Stats., Register February 2012 No. 674.
Trans 28.06Trans 28.06Grant award.
Trans 28.06(1)(1)The department shall annually establish deadlines for filing harbor assistance project applications and shall give appropriate notice of the deadlines. Notice shall be by mail, sent to every eligible applicant that has met the planning requirements under s. Trans 28.10. The department shall issue notice of the grant awards within 180 days after an application deadline. No grant funds may be committed to an eligible applicant until a grant agreement is negotiated and signed by the department and the eligible applicant.
Trans 28.06(2)(2)The department may rescind grant awards in whole or in part if:
Trans 28.06(2)(a)(a) All legally required permits are not obtained by July 1 of the calendar year for which a grant is awarded;
Trans 28.06(2)(b)(b) Local matching funds are not advanced when due;
Trans 28.06(2)(c)(c) Funds to be made available from other sources because of the grant are not advanced when due;
Trans 28.06(2)(d)(d) Work eligible for grant reimbursement is not begun in the calendar year for which the grant was awarded;
Trans 28.06(2)(e)(e) A significant change in the project scope occurs after notice of the grant award is issued; or
Trans 28.06(2)(f)(f) The grantee is in default under the grant agreement.
Trans 28.06(3)(3)The department shall rescind a grant award if the eligible applicant withdraws its application or is unable to enter a grant agreement in the calendar year for which the grant is awarded.
Trans 28.06(4)(4)Recision of a grant award, in whole or in part, shall permit the department to award a grant to the next, most highly ranked, unfunded project on the current project priority list that can be funded under the requirements of this chapter.
Trans 28.06 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; CR 05-019: am. (1) Register July 2005 No. 595, eff. 8-1-05.
Trans 28.07Trans 28.07Grant amounts.
Trans 28.07(1)(1)In accordance with s. 85.095 (2) (a), Stats., the state share of project costs may not exceed 80% of the eligible costs incurred by the eligible applicant for the harbor assistance project.
Trans 28.07(2)(2)For projects funded in part by the U.S. army corps of engineers, the state share may not exceed 50% of the non-federal share of the project costs.
Trans 28.07(3)(3)For projects with federal funding, other than those projects funded in part by the U.S. army corps of engineers as described in sub. (2), the state share may not exceed 80% of the non-federal share of project costs; furthermore, the minimum eligible applicant share shall be no less than 10% of project costs.
Trans 28.07(4)(4)The department may not assume a continuing funding responsibility for any project.
Trans 28.07 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; CR 01-117: am. (4) Register March 2002 No. 555, eff. 4-1-02; CR 05-019: am. (1) and (3) Register July 2005 No. 595, eff. 8-1-05.
Trans 28.08Trans 28.08Grant agreement.
Trans 28.08(1)(1)Harbor assistance projects for which grants are approved shall be formally implemented through grant agreements between the department and the eligible applicant. If the eligible applicant is unable or unwilling to enter into a grant agreement with the department in the calendar year for which the applicant’s project is approved, the applicant shall resubmit another application for the project before the department shall again consider it for funding.
Trans 28.08(2)(2)The types and amounts of costs eligible for state assistance shall be negotiated in developing a grant agreement. Eligible costs may include final engineering, construction, and dredging costs and other costs agreed to by the department and the eligible applicant. The following items, however, are not eligible for reimbursement:
Trans 28.08(2)(a)(a) Eligible applicant’s general grant administration costs;
Trans 28.08(2)(b)(b) Costs of acquiring permits or of preparing environmental documents, feasibility studies, conceptual project designs or design revisions; and
Trans 28.08(2)(c)(c) Interest on money borrowed by the eligible applicant or interest charged to the applicant for late payment of project costs.
Trans 28.08(3)(3)The maximum amount granted by the department shall be stated in the grant agreement for the project.
Trans 28.08(4)(4)The grant agreement shall require a grant recipient to:
Trans 28.08(4)(a)(a) Save and hold the department harmless from and against all liability, damage, loss, claims, demands and actions of any nature whatsoever related to the project; and provide, at its expense, a comprehensive general liability insurance policy, with per occurrence limits to be determined by the department, naming the department and its officers, employees and agents as additional insureds.
Trans 28.08(4)(b)(b) Provide evidence of performance and payment bonds, satisfying all applicable requirements of ss. 30.32 and 779.14, Stats., for the full amount of any and all construction contracts let by the eligible applicant in connection with the project.
Trans 28.08(4)(c)(c) Maintain project-related books and records as required by the department and make such records available to the department for audit purposes. In addition, grant recipients shall make periodic progress reports to the department. The content and timing of these reports shall be specified in the grant agreement.
Trans 28.08(5)(5)In the grant agreement, the department shall require repayment of grant funds advanced to an eligible applicant if:
Trans 28.08(5)(a)(a) The project for which the grant funds are awarded is not completed in accordance with all terms of the grant agreement, including required completion dates; or
Trans 28.08(5)(b)(b) Any commercial transportation facility for which the grant is awarded is converted during that time established in the grant agreement to a use inconsistent with the purposes of the harbor assistance program or inconsistent with the terms of the grant agreement or is converted during that period to a use not approved in writing by the department. Conversion to a use approved in writing by the department may, nonetheless, require repayment of all or a portion of the grant funds to the department.
Trans 28.08 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; CR 05-019: am. (2) (intro.), (a), (c), (4) (b) and (5) (intro.) Register July 2005 No. 595, eff. 8-1-05.
Trans 28.09Trans 28.09Application process.
Trans 28.09(1)(1)Applications for harbor assistance program grants shall be submitted to the department in a manner and form prescribed by the department. Forms shall be available without charge.
Trans 28.09(2)(2)Each application shall include the following information:
Trans 28.09(2)(a)(a) A resolution officially adopted by the eligible applicant containing:
Trans 28.09(2)(a)1.1. A formal request for assistance.
Trans 28.09(2)(a)2.2. The name of the eligible applicant’s representative authorized to sign forms or claims. The representative shall be the applicant’s contact person for the project. If there are more than one, all their names shall be included in the application.
Trans 28.09(2)(a)3.3. A statement that the eligible applicant will accept responsibility for operation and maintenance of the proposed project after completion of the work funded.
Trans 28.09(2)(a)4.4. A statement that the proposed project is consistent with the harbor development plan or with the comprehensive plan of the local government if a plan or plans have been adopted. A copy of any plan shall be attached to the application.
Trans 28.09(2)(a)5.5. A statement that the proposed project is consistent with the 3-year harbor development statement of intentions submitted by the eligible applicant as required by s. Trans 28.10.
Trans 28.09(2)(a)6.6. A statement that the eligible applicant agrees to provide the department, in a timely manner, additional analysis or documentation supporting the application, whenever the department considers it necessary during the application review process.
Trans 28.09(2)(a)7.7. A statement that the eligible applicant agrees to provide required matching funds up to a stated maximum at the time and in the manner specified in the grant agreement.
Trans 28.09(2)(b)(b) A narrative description of the project which, at a minimum, shall include:
Trans 28.09(2)(b)1.1. A detailed description of the work to be performed including plans, drawings, sounding reports or other information necessary to fully describe the project.
Trans 28.09(2)(b)2.2. A detailed description of the means by which the work is to be performed.
Trans 28.09(2)(b)3.3. A statement of justification and reasons for accomplishing the project, including a discussion of possible alternatives in type and scope to the project.
Trans 28.09(2)(b)4.4. A map, sketch, or other depiction of the project site.
Trans 28.09(2)(b)5.5. A statement of current ownership of the project site and facilities and of the ownership proposed upon completion of the project.
Trans 28.09(2)(b)6.6. A time schedule for performing major project tasks.
Trans 28.09(2)(c)(c) A detailed estimate of project cost, indicating the eligible applicant’s cost share, amount of state funding requested, other sources or potential sources of funds and full description of timetables and conditions affecting funds other than funds already budgeted by the applicant.
Trans 28.09(2)(d)(d) An estimate of project development costs, not included as estimated project costs, that are essential to the success of the project. This may include, for example, the value of existing land and facilities, the cost of additional site development and the cost of storage or transfer facilities.
Trans 28.09(2)(e)(e) An estimate of the eligible applicant’s annual revenues from the project if completed, or of revenues lost if the project is not completed, and an estimate of the annual costs necessary to maintain the project property.
Trans 28.09(2)(f)(f) An estimate of the number and type of jobs directly attributable to the proposed project, or of those jobs lost if the project is not completed. The estimates shall be supported by a description of the means by which the number of jobs is calculated.
Trans 28.09(2)(g)(g) A list of commodities and a disclosure of the tonnage of waterborne commerce using the project property and expected to use the project property if the project is completed, with origin and destination information.
Trans 28.09(2)(h)(h) A list of permits necessary for the project to proceed and, if the permits have not been obtained, a description of the actions taken or to be taken to obtain the permits.
Trans 28.09(2)(i)(i) A description of the probable environmental impact of the project. Copies of environmental reports, environmental screening worksheets, environmental assessments, and environmental impact statements shall be provided.
Trans 28.09(2)(j)(j) An estimated annual number of passengers that will be affected by the project.
Trans 28.09(3)(3)If an eligible applicant fails to supply required information or supplies erroneous information, the department may disapprove the application.
Trans 28.09(4)(4)The eligible applicant shall submit an application to the department by August 1 in order to receive primary consideration for funding during the following calendar year. If funds are available, applications may be submitted by March 15, 1985, and by February 1 of each year thereafter, for funding in the same calendar year. The department may waive the requirements in this subsection for emergency repair projects.
Trans 28.09 NoteNote: Application forms for harbor assistance program grants may be obtained without charge from: Manager, Harbor Assistance Program, P.O. Box 7914, Madison, Wisconsin 53707-7914.
Trans 28.09 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; correction in (2) (a) 5., made under s. 13.93 (2m) (b) 7., Stats., Register, December, 1987, No. 384; CR 01-117: am. (2) (a) 5. and cr. (2) (j) Register March 2002 No. 555, eff. 4-1-02; CR 05-019: am. (2) (a) 3., 6., 7., (e), (3) and (4) Register July 2005 No. 595, eff. 8-1-05.
Trans 28.10Trans 28.10Planning requirement. No grant may be made under s. 85.095, Stats., and this chapter, unless the eligible applicant provides the department a description of the harbor projects for which the applicant may request state assistance under s. 85.095, Stats., or federal aid, or both, during the next 3 years. The description shall be submitted prior to April 1 preceding the fiscal year in which the applicant seeks aid under this chapter. The department may waive this planning requirement.
Trans 28.10 HistoryHistory: Cr. Register, February, 1985, No. 350, eff. 3-1-85; CR 05-019: am. Register July 2005 No. 595, eff. 8-1-05.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.