This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
Trans 209.08(12) (12) Improving system continuity and safety.
Trans 209.08(13) (13) Ensuring compatibility with various local, regional and state plans through cooperation with local units of government, county and regional planning and review agencies and other state agencies.
Trans 209.08 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81; correction in (intro.) made under s. 13.92 (4) (b) 6., Stats., Register February 2013 No. 686.
Trans 209.09 Trans 209.09Program development and evaluation.
Trans 209.09(1)(1) The department shall maintain information on a range of alternative dollar level programs. This information illustrates a range of options and offers the secretary, as well as the governor and the legislature, choices as to the appropriate funding levels for the highway program.
Trans 209.09(2) (2) Based on the analysis performed in s. Trans 209.08, the department shall select candidate projects and the appropriate level of improvement. The level of improvement proposed for a candidate project may vary dependent upon the dollar level of the program.
Trans 209.09(3) (3) The department shall accomplish both project level and program level evaluations. Evaluations shall assist in the identification of appropriate projects, improvement levels and program dollar levels.
Trans 209.09(4) (4) The central office shall review and evaluate the region's program recommendations with several iterations of development and review necessary to produce a single statewide program.
Trans 209.09(5) (5) Project level evaluation shall include comparing the extent and severity of deficiencies:
Trans 209.09(5)(a) (a) Between projects;
Trans 209.09(5)(b) (b) To region and state average for such deficiencies;
Trans 209.09(5)(c) (c) To program level average (region and state) for such deficiencies;
Trans 209.09(5)(d) (d) And to the proposed improvement level rationale of Figure 2.
Trans 209.09(6) (6) The department shall accomplish program level evaluation statewide and between regions by evaluating the:
Trans 209.09(6)(a) (a) Extent and severity of project deficiencies corrected;
Trans 209.09(6)(b) (b) Changes in accident and system capacity that result;
Trans 209.09(6)(c) (c) And the environmental and energy implications of the programs.
Trans 209.09(7) (7) The department shall maintain a file of information which specifies the deficiencies of projects analyzed for the program.
Trans 209.09 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81; corrections in (4), (5) (b), (c), (6) (intro.) made under s. 13.92 (4) (b) 6., Stats., Register February 2013 No. 686.
Trans 209.10 Trans 209.10Program selection. The alternative programs and their costs and benefits shall be documented and reviewed by the secretary who shall select a program level and recommend it to the governor. After the enactment of the biennial budget by the legislature and the governor, the program shall be adjusted to be consistent with the approved funding level for the current biennium.
Trans 209.10 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81.
Trans 209.11 Trans 209.11Public review.
Trans 209.11(1) (1) The department shall seek public review and comment concerning the program.
Trans 209.11(2) (2) Such review shall include an informational presentation of the proposed program of major projects by the department to all transportation related legislative committees at a time mutually agreeable to the department and the committees prior to February 15 of the odd numbered years.
Trans 209.11(3) (3) After the enactment of the biennial budget, the department shall make the program document available to interested individuals and organizations and will also inform the general public of this availability. Informational hearings shall be held after the release of the program document at times and locations determined by the secretary and publicized through the local media. These hearings shall serve both to inform the public and to obtain reactions for use in the ongoing program development activities.
Trans 209.11(4) (4) The public review of the program shall be supplemented by public reviews of policy and system planning efforts and of individual projects.
Trans 209.11 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81.
Trans 209.12 Trans 209.12Program recycle. Program development shall be maintained as a continuous process. Upon the completion of one program cycle, a new program development cycle shall begin. Recycling the program normally involves: extending it 2 years; updating data, project alternatives, and project cost estimates; reassessing the underlying policies; and refining methods and procedures.
Trans 209.12 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81.
Trans 209.13 Trans 209.13Program adjustments. Programs are estimates and are not absolute. Adjustments to the program are necessary due to changes in project design, the time to acquire the right-of-way and obtain the required clearances and completion of the environmental impact statement procedure. These adjustments shall be continual in order to assure the most optimum use of resources. The goal of the adjustments shall be consistent with s. Trans 209.04.
Trans 209.13 History History: Cr. Register, September, 1981, No. 309, eff. 10-1-81.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.