This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
The purpose of this practice is to reduce slope length of the disturbed area and to intercept and retain transported sediment from disturbed areas.
III.   Conditions Where Practice Applies
A.   This standard applies to the following applications where:
1.   Erosion occurs in the form of sheet and rill erosion1. There is no concentration of water flowing to the barrier (channel erosion).
2.   Where adjacent areas need protection from sediment-laden runoff.
3.   Effectiveness is required for less than 3 months.
4.   Conditions allow for the bales to be properly entrenched and staked as outlined in the Criteria Section V.
B.   Under no circumstance shall sediment bale barriers be used in the following applications:
1.   Below the ordinary high watermark or placed perpendicular to flow in streams, swales, ditches or any place where flow is concentrated.
2.   Where the maximum gradient upslope of the sediment bale barriers is greater than 50% (2:1).
IV.   Federal, State, and Local Laws
Users of this standard shall be aware of applicable federal, state, and local laws, rules, regulations, or permit requirements governing the use and placement of the sediment bale barrier. This standard does not contain the text of federal, state, or local laws.
V.   Criteria
This section establishes the minimum standards for design, installation and performance requirements.
A.   Placement
1.   At a minimum, sediment bale barriers shall be placed in a single row, lengthwise on the contour, with the ends of adjacent sediment bale barriers tightly abutting one another. The holes between bales shall be chinked (filled by wedging) with straw, hay or equivalent material to prevent water from escaping between the bales.
2.   The maximum allowable slope lengths contributing runoff to a sediment bale barrier are specified in Table 1.
Table 1 - See PDF for table PDF
3.   Sediment bale barriers shall not be placed perpendicular to the contour.
4.   The end of the sediment bale barrier shall be extended upslope to prevent water from flowing around the barrier ends.
B.   Height – Installed sediment bale barrier shall be a minimum of 10 inches high and shall not exceed a maximum height of 20 inches from ground level.
C.   Anchoring and Support
1.   The barrier shall be entrenched and backfilled. A trench shall be excavated the width of a sediment bale barrier and the length of the proposed barrier to a minimum depth of 4 inches. After bales are staked and chinked, the excavated soil shall be backfilled and compacted against the barrier. Backfill to ground level on the down slope side. On the upslope side of the sediment bale barrier backfill to 4 inches above ground level.
2.   At least two wood stakes, “T" or “U" steel posts, or ½ inch rebar driven through at equidistance along the centerline of the barrier shall securely anchor each bale. The minimum cross sectional area for wood stakes shall be 2.0 by 2.0 inches nominal. The first stake in each bale shall be driven toward the previously laid bale to force the bales together. Stakes shall be driven a minimum 12-inches into the ground to securely anchor the sediment bale barriers.
3.   Bales shall be installed so that bindings are oriented around the sides rather than along the tops and bottoms of the bales in order to prevent deterioration of the bindings.
VI.   Considerations
A.   Improper placement as well as improper installation and maintenance of sediment bale barriers will significantly decrease the effectiveness of this practice.
B.   Sediment bale barriers should not be used upslope of the disturbed area.
C.   A double row of sediment bale barriers may be installed in areas where additional protection is needed.
D.   For safety, place all anchoring flush with the sediment bale barrier or cap any exposed anchoring device.
VII.   Plans and Specifications
A.   Plans and specifications for installing sediment bale barriers shall be in keeping with this standard and shall describe the requirements for applying the practice to achieve its intended purpose. The plans and specifications shall address the following:
1.   Location of sediment bale barrier
2.   Contributory drainage area
3.   Schedules
4.   Standard drawings and installation details
5.   Restoration after removal
B.   All plans, standard detail drawings, or specifications shall include schedule for installation, inspection, and maintenance. The responsible party shall be identified.
VIII.   Operation and Maintenance
A.   Sediment bale barriers shall, at a minimum, be inspected weekly and within 24 hours after every precipitation event that produces 0.5 inches of rain or more during a 24-hour period.
B.   Damaged or decomposed sediment bale barriers, any undercutting, or flow channels around the end of the sediment bale barriers shall be repaired.
C.   Sediment shall be properly disposed of once the deposits reach 1/2 the height of the sediment bale barrier.
D.   Sediment bale barriers and anchoring devices shall be removed and properly disposed of when they have served their usefulness, but not before the upslope areas have been permanently stabilized.
E.   Any sediment deposits remaining in place after the sediment bale barrier is no longer required shall be dressed to conform to the existing grade, prepared and seeded.
IX.   Definitions
Channel Erosion (III.A.1): The deepening and widening of a channel due to soil loss caused by flowing water. As rills become larger and flows begin to concentrate soil detachment occurs primarily as a result of shear. The transport capacity of the flow in a channel is based on the availability of sediment and is a monatomic function of velocity.
Sheet and Rill Erosion (III.A.1): Sheet and rill erosion is the removal of soil by the action of rainfall and shallow overland runoff. It is the first stage in water erosion. As flow becomes more concentrated rills occur. As soil detachment continues or flow increases, rills will become wider and deeper forming gullies.
Sediment Basin
1064 (03/06)
Wisconsin Department of Natural Resources
Conservation Practice Standard
Note: Words in the standard that are shown in italics are described in X. Definitions. The words are italicized the first time they are used.
I.   Definition
A sediment control device constructed with an engineered outlet, formed by excavation or embankment to intercept sediment-laden runoff and retain the sediment.
II.   Purposes
Detain sediment-laden runoff from disturbed areas for sufficient time to allow the majority of the sediment to settle out.
III.   Conditions Where Practice Applies
Sediment basins are utilized in areas of concentrated flow or points of discharge during construction activities. Sediment basins shall be constructed at locations accessible for clean out. Site conditions must allow for runoff to be directed into the basin.
Sediment basins are designed to be in place until the contributory drainage area has been stabilized1. Sediment basins are temporary and serve drainage areas up to 100 acres however other conservation practices are often more economical for smaller drainage areas. For drainage areas smaller than 5 acres sediment traps or ditch checks may be applicable; for design criteria refer to WDNR conservation Practice Standard Sediment Trap (1063) or Ditch Check (1062).
Design to WDNR Conservation Practice Standard Wet Detention Basin (1001) when a permanent stormwater basin is required.
IV.   Federal, State, and Local Laws
Users of this standard shall be aware of applicable federal, state, and local laws, rules, regulations, or permit requirements governing the use and placement of sediment basins. This standard does not contain the text of federal, state, or local laws.
V.   Criteria
This section establishes the minimum standards for design, installation and performance requirements. Sediment basins meeting these design criteria are deemed 80% effective by design in trapping sediment.
A.   Timing – Sediment basins shall be constructed prior to disturbance of up-slope areas and placed so they function during all phases of construction. Sediment basins shall be placed in locations where runoff from disturbed areas can be diverted into the basin.
B.   Sizing Criteria – Properly sized sediment basins are more effective at trapping fine-grained particles than sediment traps. Specific trapping efficiency varies based on the surface area and the particle size distribution of the sediment entering the device. See Figure 1 for clarification of terms. Attachment 1 includes a sample design problem.
Treatment Surface Area – The surface area of the sediment basin measured at the invert of the lowest outlet. The treatment surface area shall be sized based on the texture of the soil entering the device and the peak outflow during the 1-year, 24-hour design storm using Equation 1:
Sa = 1.2 * (qout / vs)
Where:
Sa = Treatment surface area measured at the invert of the lowest outlet of sediment basin (square feet)
qout = Peak outflow (cubic feet / second) during the 1-year, 24-hour design storm for the principal outlet
vs = Particle settling velocity (feet/second)
1.2 = EPA recommended safety factor
Particle settling velocities (Vs) shall be based on representative soil class as follows:
a.   Soil Class 1: vs = 1.2*10 -3 ft/sec
b.   Soil Class 2: vs = 7.3*10 -5 ft/sec
c.   Soil Class 3: vs = 1.2*10 -5 ft/sec
Note: Particle settling velocities calculated assuming a specific gravity of 2.65 and a water temperature of 68 degrees Fahrenheit.
  Soil Class 1 includes particles greater than 20 microns generally corresponding to sand, loamy sand, and sandy loam.
  Soil Class 2 includes particles between 5 and 20 microns generally corresponding to loam, silt, and silt loam aggregates as transported in runoff.
  Soil Class 3 includes particles between 2 and 5 microns generally corresponding to clay loam, silty clay, and clay aggregates as transported in runoff.
  The representative soil class shall be selected based on the dominant textural class of the soil entering the device.
  The treatment surface area of sediment basins can be reduced when used in conjunction with water applied polymers. When employing polymers, size the treatment surface area for controlling fine soils (Class 3) using the settling velocity for medium soils (Class 2). When designing for medium sized soils (Class 2) use the settling velocity for coarse soils (Class 1). See WDNR Conservation Practice Standard Sediment Control Water Application of Polymers (1051) for criteria governing the proper use and selection of polymers.
  Depth below Treatment Surface Area – The depth below the treatment surface area as measured from the invert of the lowest outlet of the sediment basin shall be a minimum of 5 feet deep (2 feet for sediment storage plus 3 feet to protect against scour/ resuspension) and a maximum of 10 feet deep to limit the potential for thermal stratification.
  Due to side slope requirements and safety shelf considerations it maybe difficult to maintain 5 feet of depth for the entire treatment surface area. Therefore, 50% of the total treatment surface area shall be a minimum of 5 feet deep. For basins less than 5,000 square feet, maximize the area of 5 feet depth.
  Interior side slopes below the lowest invert shall be 2:1 (horizontal: vertical) or flatter to maintain soil stability.
  While a permanent pool of water below the lowest invert may form, it is not required to be maintained through irrigation or installation of a liner system.
Active Storage Volume – The volume above the treatment surface area shall be calculated using one of the following methods:
a.   The method outlined in TR-55 for determining the storage volume for detention basins. This can be accomplished by using Figure 2 where:
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.