PSC 185.65(3)
(3) Compound meters shall have a percent registration between 97 and 103 throughout the range of normal test flow limits. At flows within the change-over flow range, the percent registration shall not be less than 90%.
PSC 185.65(4)
(4) Turbine meters shall have a percent registration between 97 and 103 throughout the range of normal test flow limits and a percent registration of at least 95% at the minimum test flow.
PSC 185.65(5)
(5) For meter installations with remote reading devices the above accuracy requirements apply to the metering accuracy of the complete installation.
PSC 185.65 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.71
PSC 185.71 Meter testing facilities and equipment. PSC 185.71(1)(1)
Each utility furnishing metered water service shall own or provide, through contract or otherwise, adequate equipment and facilities to provide for testing all of its water meters in compliance with this chapter.
PSC 185.71(2)
(2) The meter testing facility shall, to the extent practical, simulate the actual service condition of inlet pressure and outlet pressure. It shall be provided with the necessary fittings, including a quick-acting valve for controlling the starting and stopping of the test, and a device for regulating the flow of water through the meter under test within the requirements of this chapter.
PSC 185.71(3)
(3) The overall accuracy of the test equipment and test procedures shall be sufficient to enable the testing of service meters within the requirements of this chapter and regulations. In any event, the inherent overall accuracy of the equipment shall permit tests with an overall error of not to exceed 0.5% at normal test flows and 1.0% at the stated minimum test flow.
PSC 185.71 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.72
PSC 185.72 Calibration of meter testing equipment. PSC 185.72(1)(1)
Volumetric standards shall be accompanied by a dated certificate of accuracy from an approved laboratory or agency. For any weight standard used, the scales shall be tested periodically by an approved agency and a record maintained of the results of the test.
PSC 185.72(2)
(2) A reference meter used for testing domestic or larger meters may be used only if the referenced meter has been tested and calibrated during the preceding 6 months. A record shall be kept of the 2 latest tests of any reference meter. (See also s.
PSC 185.73 (1).)
PSC 185.72 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.73(1)(1)
The test of any customer meter shall consist of a comparison of its accuracy with that of a standard of known accuracy. Where the test standard consists of a previously calibrated reference or service meter, the test results for the customer meter shall be adjusted to compensate for the inaccuracies of the reference meter at the particular flow rates.
PSC 185.73(2)
(2) A utility shall test a meter “as found," or before repair, and, unless the meter must be retained under s.
PSC 185.77 (3), “as left," or after repair.
PSC 185.73(3)
(3) The volume of water through the meter at each test flow point shall be sufficient to produce at least one revolution of the test dial except at the “minimum test flow" point when said volume of water shall produce at least one-half revolution of the test dial.
PSC 185.73(4)
(4) A meter not meeting the accuracy or other requirements of s.
PSC 185.61 or
185.65 shall, unless the meter must be retained under s.
PSC 185.77 (3), be repaired or rebuilt to meet those requirements before further use.
PSC 185.73 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97;
CR 13-033: am. (2), (4)
Register July 2015 No. 715, eff. 8-1-15.
PSC 185.74(1)(1)
Tests. The minimum test flow and “normal test flow limits" as used herein refer to those listed in s.
PSC 185.65. The stated test flows apply for both As Found and As Left tests.
PSC 185.74(2)
(2)
POSITIVE DISPLACEMENT METERS. (See s.
PSC 185.65 (2).) For each test, the percent registration shall be determined at each of the following test flows:
PSC 185.74(2)(b)
(b) Two test flows within the normal test flow limits, one to be approximately at the maximum registration and the other to be at a flow as high as practicable within the normal test flow limits.
PSC 185.74(3)
(3)
COMPOUND METERS. For each test it shall be determined whether or not the by-pass unit operates at the minimum test flow and, in addition, the percent registration shall be determined at each of the following test flows as determined from accuracy curves for the particular type and size of meter:
PSC 185.74(3)(b)
(b) A flow near the point of minimum registration within the change-over range;
PSC 185.74(3)(c)
(c) At least 3 flows within the normal test flow limits of the current unit, one of which is to be at the flow for maximum registration, one at approximately 50% of such flow but above the change-over range, and one at as high a flow as practicable.
PSC 185.74(4)
(4)
TURBINE METERS. For each test the percent registration shall be determined at each of the following test flows:
PSC 185.74(4)(b)
(b) At least 3 flows within the normal test flow limits, one of which is to be at or near the lower limit, another as near as practicable to the upper limit, and one at an intermediate flow rate.
PSC 185.74 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.75
PSC 185.75 Required tests of customer meters. Meters shall be tested by the utility at the following times:
PSC 185.75(4)
(4) When damaged or otherwise suspected of being inaccurate;
PSC 185.75(5)
(5) If a meter is removed while a usage dispute is pending.
PSC 185.75 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97;
CR 01-033: am. (5),
Register October 2001 No. 550, eff. 11-1-01.
PSC 185.751
PSC 185.751 Alternate sample-testing plan for “before-use" test for 5/8-, 3/4-, and 1-inch meters. PSC 185.751(2)
(2) Meters as received from the supplier without a certificate of accuracy shall be divided into lots of 36 or less. Each lot shall consist of meters of the same make, type, and size.
PSC 185.751(3)
(3) A random-selected sample of 4 meters from each lot shall be selected and tested.
PSC 185.751(4)
(4) If any of the tested meters in a given lot fail to meet the accuracy requirements of s.
PSC 185.65 (2) for new meters, either the entire lot shall be rejected, or the utility shall test all meters in the lot, rejecting or correcting those found to be inaccurate.
PSC 185.751(5)
(5) Records shall be maintained showing the identification numbers of all meters in each lot and the test results for the meters tested per s.
PSC 185.19.
PSC 185.751 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.76(1)(1)
Customer meters (“in-use" meters) shall be tested as frequently as is necessary to maintain their accuracies within requirements set forth in s.
PSC 185.65. Unless otherwise authorized by the commission, each utility shall observe a test schedule such that the intervals between tests do not exceed the following:
-
See PDF for table PSC 185.76(2)
(2) Where local water conditions are such that meters shall not retain the required accuracy for the periods indicated, appropriate shorter test intervals shall be observed and may be specifically required by the commission.
PSC 185.76(3)
(3) Where local water conditions permit and with specific commission approval, the test interval for 5/8-, 3/4-, and 1-inch meters may be extended. This contemplates that the utility shall demonstrate that the accuracy of its meters shall be retained for such period.
PSC 185.76(4)
(4) For 3- and 4-inch meters, the above test interval may be extended to 4 years where the utility shall demonstrate that the accuracy of its meters shall be retained for this period.
PSC 185.76(5)
(5) In lieu of testing every meter as required under sub.
(1), a utility may satisfy the requirements of this section by testing meters according to s.
PSC 185.761.
PSC 185.76(6)
(6) When system losses are less than the prescribed percentages under s.
PSC 185.85 (4), a utility in lieu of testing every meter as required under sub.
(1), may satisfy the requirements of this section for 5/8, 3/4, and 1-inch meters by adopting a new meter replacement program that results in each meter being replaced within 20 years of the original date of installation.
PSC 185.76 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97;
CR 01-033: cr. (6),
Register October 2001 No. 550, eff. 11-1-01.
PSC 185.761
PSC 185.761 Alternative sample-testing plan for in-use meters. PSC 185.761(1)(1)
As an alternative to testing 100% of meters that require testing under s.
PSC 185.76, a utility may test a population sample equal to 25% of the total to be tested of each meter size. This test sample shall be a random selection of the total to be tested and each meter size test shall be conducted independently. If 10% or more of the test sample does not meet the accuracy requirements of s.
PSC 185.35, the utility shall test all meters of that size in accordance with s.
PSC 185.76.
PSC 185.761(2)
(2) Meters testing inaccurately under sub.
(1) shall be repaired prior to being returned to service. The test sample selected shall be rescheduled for testing under the intervals set forth in s.
PSC 185.76 (1). The meters not selected shall be rescheduled for testing at an interval not exceeding one-half the test intervals set forth in s.
PSC 185.76 (1).
PSC 185.761 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.77(1)(1)
Request tests. Each utility shall promptly make an accuracy test without charge of any metering installation upon request of the customer if 24 months or more have elapsed since the last customer requested test of the meter in the same location. If less than 24 months have elapsed, an amount equal to one-half the estimated cost of the meter test shall be advanced to the utility by the customer. The amount shall be refunded if the test shows the meter to be over-
or under-registering by more than 2%. A report giving the results of the test shall be made to the customer and a complete original test record shall be kept on file in the office of the utility. Upon request, the test shall be made in the presence of the customer during normal business hours.
PSC 185.77(2)
(2)
Referee tests. Any customer may request to have an official test of the meter observed by the commission.
PSC 185.77(3)(a)(a)
Definitions. For purposes of this subsection, “as found" means retained, filled with water and capped without any other adjustments being made since the last test was performed.
PSC 185.77(3)(b)
(b)
After a customer requested test. When a utility performs a customer requested test on a customer's meter under sub.
(1) or when the commission requests that a meter be tested, the utility shall keep the tested meter, in “as found" condition, at a designated location on the utility's premises for at least one full billing period plus four weeks after the test result report is issued so that the meter is available should another meter test be requested. If the meter tests as accurate, the utility may choose to keep the tested meter installed at the customer's premises for the designated time period rather than storing it at the utility's premises.
PSC 185.77(3)(c)
(c)
After a referee test. When a utility or third party retests a customer's meter under sub.
(2), the utility shall keep the tested meter, in “as found" condition, at a designated location on the utility's premises for at least 10 business days after the test result report is issued so that the meter is available should further testing or review be needed. If the meter tests as accurate, the utility may choose to keep the tested meter installed at the customer's premises for the designated time period rather than storing it at the utility's premises.
PSC 185.77(3)(d)
(d)
When a complaint or dispute occurs. When a utility receives a complaint under s.
PSC 185.42 or is notified about a dispute under s.
PSC 185.39 involving a meter-related issue, the utility shall keep the meter, in “as tested" condition, at a designated location on the utility's premises for at least one full billing period plus four weeks after the complaint or dispute and any appeal of that dispute is resolved so that the meter is available should testing be requested. If the meter was tested during the complaint or dispute process, and it tested as accurate, the utility may choose to keep the tested meter installed at the customer's premises for the designated time period rather than storing it at the utility's premises.
PSC 185.77 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97;
CR 13-033: am. (title), renum. 185.77 to (1) and am., cr. (1) (title), renum. 185.78 to (2), cr. (3)
Register July 2015 No. 715, eff. 8-1-15; correct numbering of (3) (c), (d) under s.
13.92 (4) (b) 1., Stats.,
Register July 2015 No. 715.
PSC 185.79
PSC 185.79 Remote outside meter (ROM) and automatic meter reading (AMR) system tests. PSC 185.79(1)(1)
The ROM and AMR systems shall be tested each time the associated meter is tested. If the total recorded consumption of the ROM agrees with that of the base meter or the AMR system read and the base meter read are the same, no further testing of the ROM or AMR systems is needed.
PSC 185.79(2)
(2) The test of metering installations with remotes shall be sufficient to demonstrate that the accuracy of the meter-remote combination meets the requirements of s.
PSC 185.65.
PSC 185.79(3)
(3) As an alternative to subs.
(1) and
(2), a utility may receive approval and place on file with the commission a remote testing schedule which is specifically designed to meet the needs of the remote metering system used by the utility.
PSC 185.79 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.795
PSC 185.795 Electrical safety. Jumpering meter settings. Under certain abnormal conditions, a dangerous voltage may appear across the meter setting when the water line is electrically opened as by removal of the meter. Before a water meter is removed (or the interior piping leading to the service otherwise opened), an appropriate electrical jumper shall be connected across the meter setting or proposed opening in the piping to maintain electrical continuity. If the water supply piping is used as a ground for the building's electrical service, the electrical jumper shall not be removed until a meter is again set or the piping closed. The utility shall inform the customer that the electrical jumper shall not be removed until a meter is again set or the piping closed.
PSC 185.795 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.81(1)(1)
Every water public utility shall provide water of such quality that it complies with state and federal requirements for drinking water.
PSC 185.81(2)
(2) Each water utility system shall be designed and operated so that the water supplied to all customers is reasonably free from objectionable taste, color, odor, and sand or other sediment.
PSC 185.81 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.
PSC 185.82(1)(1)
Under conditions of normal heavy system demand the residual pressure at the meter outlet shall not be less than 20 p.s.i.g. For typical residential customers, normal conditions of use shall mean a flow rate of not less than 12 gallons per minute. This standard assumes that the customer's portion of the service lateral is of normal, adequate design, and in good condition. This standard shall ordinarily require that the distribution main pressure at the corporation stop connection be at least 35 p.s.i.g. The utility is to establish minimum specifications for the service lateral to assure that excessive pressure drop does not occur in the lateral because of its length or for other cause.
PSC 185.82(2)
(2) The maximum pressure at the meter shall not exceed 125 p.s.i.g. The maximum pressure at the meter shall not exceed 100 p.s.i.g. for new systems and, to the extent practical, major additions to existing systems.
PSC 185.82(3)
(3) Each utility shall have at least one permanently installed pressure gauge on its system and shall have access to indicating and recording pressure gauges to check pressure levels.
PSC 185.82(4)
(4) Each utility shall make such pressure tests or surveys as to assure that the pressure limitations of subs.
(1) and
(2) are being met.
PSC 185.82 History
History: Cr.
Register, January, 1997, No. 493, eff. 2-1-97.