PSC 111.53(1)(a)8.
8. The heat rates over the range of operating capacity for each generating unit.
PSC 111.53(1)(b)
(b) The need for the proposed facility in terms of demand and energy.
PSC 111.53(1)(c)
(c) The economic aspects of the proposed facility, including all of the following:
PSC 111.53(1)(c)1.
1. The estimated capital cost of the generating facility and all related facilities, broken down by major plant accounts. All cost escalation factors used in the estimate shall be identified.
PSC 111.53(1)(c)2.
2. The projected unit fuel cost, in cents per million Btu, both for the first year of operation and levelized in nominal terms over the life of the unit or facility. All cost escalation factors used in the estimate shall be identified.
PSC 111.53(1)(c)3.
3. The estimated annual production cost, calculated as operating, maintenance and fuel costs for the first year of operation and levelized in nominal terms over the life of the facility. All cost escalation factors used and other significant supporting data shall be included.
PSC 111.53(1)(c)4.
4. The estimated annual total cost, calculated as capital and production costs for the first year of operation, in mills per net kWh generated, and levelized in nominal terms over the life of the facility. All cost escalation factors used and other significant supporting data shall be included.
PSC 111.53(1)(c)5.
5. The estimated useful life of facility, based on depreciation rates established by the commission.
PSC 111.53(1)(d)
(d) The alternative sources of supply considered, including information about all of the following alternatives:
PSC 111.53(1)(d)2.
2. Any alternative whose energy source has a higher priority ranking under s.
1.12 (4) (b) to
(d), Stats., than the fuel proposed to used for the facility.
PSC 111.53(1)(d)3.
3. For any facility that will use a combustible energy resource but not provide cogeneration, an explanation regarding why cogeneration is not feasible.
PSC 111.53(1)(e)
(e) A description of the alternatives considered, a description of the siting process, and a list of the factors considered in choosing and ranking the alternatives.
PSC 111.53(1)(em)
(em) Information demonstrating how brownfields, as defined in s.
16.287 (1) (a), Stats., and interpreted by the commission, were considered as site alternatives.
PSC 111.53(1)(f)
(f) Except as provided in
sub. (2) (b), site-related information for each of two proposed power plant sites, including all of the following:
PSC 111.53(1)(f)1.
1. The regulatory approvals required for construction and operation of the facility.
PSC 111.53(1)(f)2.
2. The construction schedule and timeline, showing construction activities and permitting expectations from the beginning of construction to the in-service date.
PSC 111.53(1)(f)3.
3. The availability of transportation for fuel delivery and requirements for gas pipeline construction. If a certificate of authority under s.
196.49, Stats., is required to construct the gas pipeline, the location, termini, length in miles, size of pipe, and pressure.
PSC 111.53(1)(f)4.
4. Any required transmission line construction, agreements for use of the transmission system to deliver plant power, transmission losses, and effects on system reliability. If a certificate of authority under s.
196.49, Stats., is required to construct the transmission line, the location of termini, length in miles, and voltage for each transmission line.
PSC 111.53(1)(f)5.
5. Other auxiliary facilities, including fuel storage and water storage.
PSC 111.53(1)(f)9.
9. If a CPCN is needed for construction of transmission lines as part of this application, the required information under
s. PSC 111.55.
PSC 111.53(1)(g)
(g) Any additional information the commission may request, including information necessary for it to make the determinations listed in s.
196.491 (3) (d), Stats., or to prepare an environmental assessment or an environmental impact statement under s.
1.11, Stats.
PSC 111.53(2)(a)(a) An application for a wholesale merchant plant need not include the information identified in
sub. (1) (b) to
(d). In addition, an application for a wholesale merchant plant that will be owned, controlled, or operated by an affiliated interest of a public utility, shall include any additional information required by the commission in order to make a determination under s.
196.491 (3m) (a), Stats.
PSC 111.53(2)(b)
(b) Based on the pre-application consultation required under
s. PSC 111.51 (2) (b), an application for a generation facility may include the detailed information listed under
sub. (1) (f) for only one site if none of the needed infrastructure improvements would constitute a major action significantly affecting the quality of the human environment under s.
1.11 (2) (c), Stats., and the application is for any of the following:
PSC 111.53(2)(b)1.
1. Construction of a cogeneration facility located at the steam host's existing industrial plant, if the cogeneration facility will be a qualifying facility under
18 CFR 292.205.
PSC 111.53(2)(b)2.
2. Modifying, rebuilding, replacing or repowering, as defined under s.
79.005 (4), Stats., an existing generating facility at its current location.
PSC 111.53(2)(b)3.
3. Construction of a generating facility proposed to be located on an existing brownfield site, as defined in s.
16.287 (1) (a), Stats., and interpreted by the commission, or on the site of a former or existing large electric generating facility.
PSC 111.53 Note
Note: See sub. (1) (e) concerning information that must be included about both the site in sub. (2) (b) and any alternatives.
PSC 111.53 History
History: Cr.
Register, June, 2000, No. 534, eff. 7-1-00;
CR 07-044: am. (1) (e) and (f) (intro.), cr (1) (em), (2) (b) 1. and 3., renum. (2) (b) 1. to be (2) (b) (intro.) and am., r. and recr. (2) (b) 2.
Register May 2008 No. 629, eff. 6-1-08; correction to (1) (em), (2) (b) 3. made under s.
13.92 (4) (b) 7., Stat.,
Register January 2012 No. 673.
PSC 111.55
PSC 111.55 CPCN applications for high-voltage transmission lines. A CPCN application for a high-voltage transmission line is not complete until the applicant has filed all of the following information with the commission:
PSC 111.55(1)
(1) Need. The need for the proposed project, including all planning criteria, assumptions, historical outage data, stability, and power-flow studies that address need.
PSC 111.55(2)
(2) Design. The physical design characteristics, including structure type, design span length, conductor size and type, foundation type, operating voltage, and feasibility of future increases in operating voltage.
PSC 111.55(3)
(3) Basis for design selection. The basis for selection of physical design characteristics.
PSC 111.55(4)
(4) EMF levels. The estimated magnetic field levels.
PSC 111.55(5)
(5) Substation design. The substation design or modifications to existing substations.
PSC 111.55(6)
(6) Owners and investors. The names and addresses of owners and investors, and percent of ownership.
PSC 111.55(7)
(7) Construction schedule and approvals. The construction schedule and required regulatory approvals.
PSC 111.55(8)
(8) Additional information. Any additional information the commission may request, including information necessary for it to make the determinations listed in s.
196.491 (3) (d), Stats., or to prepare an environmental assessment or environmental impact statement under s.
1.11, Stats.
PSC 111.55(9)
(9) Tariff filings. Whether an open-access tariff has been filed with the FERC.
PSC 111.55(10)
(10) Proposed routes. Except as otherwise submitted under this section, proposed routes and the pertinent factors considered in choosing them, including engineering, economic, safety, reliability and environmental considerations. All of the following information shall be filed for each of the proposed routes:
PSC 111.55(10)(e)
(e) Water resources, including wetlands, lakes, rivers, and streams.
PSC 111.55(10)(g)
(g) Endangered, threatened, and special concern species and communities.
PSC 111.55(10)(L)
(L) Communication towers, VHF omnidirectional range plus tactical air navigation (VORTAC) stations, and airports.
PSC 111.55(10)(q)
(q) Information demonstrating how the transmission line siting priorities in s.
1.12 (6), Stats., were considered.
PSC 111.55 History
History: Cr.
Register, June, 2000, No. 534, eff. 7-1-00;
CR 07-044: am. (10) (intro.), cr. (10) (q)
Register May 2008 No. 629, eff. 6-1-08.
PSC 111.56
PSC 111.56 Expedited review. An applicant requesting expedited review of a high voltage transmission line application under s.
196.491 (3b), Stats., shall include all of the following in its application:
PSC 111.56(1)
(1) All the information required under
s. PSC 111.55, except that the detailed information required under
s. PSC 111.55 (10) is required only for the route the applicant proposes to construct.
PSC 111.56(2)
(2) Information and documentation describing in detail why the application should receive expedited review.
PSC 111.56 History
History: CR 07-044: cr.
Register May 2008 No. 629, eff. 6-1-08.
PSC 111.61
PSC 111.61 Purpose. The purpose of this subchapter is to implement s.
196.371, Stats.
PSC 111.61 History
History: CR 05-079: cr.
Register May 2006 No. 605, eff. 6-1-06.
PSC 111.62(1)
(1) A public utility may apply for an order fixing financial parameters under s.
196.371, Stats.
PSC 111.62(2)
(2) An electric generating facility proposed to be constructed by a public utility cannot qualify for fixed financial parameters unless the public utility submits an application for fixed financial parameters before or simultaneously with the application for a certificate, as defined in s.
196.371 (1), Stats.
PSC 111.62(3)
(3) An electric generating facility proposed to be purchased by a public utility cannot qualify for fixed financial parameters unless the public utility submits an application for fixed financial parameters before or simultaneously with the application for authority to purchase the electric generating facility.
PSC 111.62 History
History: CR 05-079: cr.
Register May 2006 No. 605, eff. 6-1-06.
PSC 111.63
PSC 111.63 Information required. A public utility desiring fixed financial parameters shall provide all of the following information in its application: