NR 810.20 History
History: CR 09-073: cr.
Register November 2010 No. 659, eff. 12-1-10.
NR 810.21
NR 810.21 Unattended water treatment plant operation. Water treatment plants may be operated remotely or by use of on site supervisory control and data acquisition (SCADA) systems provided the water distribution system has sufficient storage, as determined by engineering analysis, to allow response and resolution to problems. Unattended water treatment plants treating for acute contaminants shall be provided with:
NR 810.21(1)
(1) Alarms for all critical features including:
NR 810.21(2)
(2) An operations manual describing alarms, operator responses to alarms, quality control and challenge testing for the communication and control systems, operation and maintenance of the control systems, and identifying primary and secondary responders.
NR 810.21(3)
(3) A flow diagram showing the location of critical features, alarms, and automated controls.
NR 810.21(4)
(4) Manual override of all treatment plant operations and functions.
NR 810.21(5)
(5) Daily on-site operator visits to verify plant operation and security.
NR 810.21(6)
(6) Designation of standby operators during times of unattended operation.
NR 810.21(8)
(8) Continuous disinfectant residual and turbidity monitoring where appropriate.
NR 810.21(9)
(9) Water suppliers for public water systems using surface water and groundwater under the direct influence of surface water shall:
NR 810.21(9)(a)
(a) Submit a report describing the items required in
sub. (2) to the department for review and approval.
NR 810.21(9)(b)
(b) Demonstrate the operation of the treatment plant by the SCADA system for a period of 6 months.
NR 810.21(9)(c)
(c) Provide a list of alarms generated during the demonstration period along with a request for approval to operate unattended.
NR 810.21 History
History: CR 09-073: cr.
Register November 2010 No. 659, eff. 12-1-10.
NR 810.22
NR 810.22 Emergency well operation. An emergency well is a well that is not routinely used. The well owner may obtain a written extended well abandonment agreement with the department to allow a normally unused or standby well to remain operational and to delay well abandonment provided that the well owner agrees in writing to the following requirements:
NR 810.22(1)
(1) The well water entering the distribution system may not exceed any bacteriological or nitrate drinking water standards.
NR 810.22(2)
(2) The well water may not contain any volatile organic or synthetic organic contaminant levels exceeding the maximum contaminant level or MCL that could lead to further water quality degradation of the groundwater.
NR 810.22(3)
(3) The well owner agrees to a 5 year cycle of reevaluation. Where the agreement is continued, it shall be renewed in writing every 5 years.
NR 810.22(4)
(4) A 6-year cycle for water quality monitoring is established.
NR 810.22(5)
(5) Bacteriological testing is conducted quarterly from the well.
NR 810.22(6)
(6) Nitrate is monitored annually from the well.
NR 810.22(7)
(7) The well meets current well construction and pump installation standards.
NR 810.22(8)
(8) The water supplier shall notify all customers of the use of the well if the water quality exceeds primary drinking water standards.
NR 810.22(9)
(9) The well owner agrees to televise any well in excess of 70 years old at least once every 15 years.
NR 810.22(10)
(10) The water system will restrict the use of the well if the water quality exceeds the primary drinking water standards to emergency use of no more than 2 days per quarter. The department may authorize an extended period of use for an individual event if contacted by the water supplier.
NR 810.22 History
History: CR 09-073: cr.
Register November 2010 No. 659, eff. 12-1-10.
NR 810.23
NR 810.23 Water system security and emergency operations. NR 810.23(1)(1)
Water system security. Water system buildings and infrastructure access points above ground, such as reservoir hatches, lines used to pump to waste, doors and valve chambers, shall have adequate locks and be secured when not occupied or in use. Security measures that may be taken include: the installation of security fences, hardened or protected locks, exterior warning lights, exterior motion detectors, surveillance cameras; door, window, and hatch intrusion alarms, room motion sensors, steel doors, minimizing the size of windows, eliminating windows or using hardened window materials or iron, steel bars, or mesh over windows. Any security alarms installed shall be connected to telemetry control, SCADA systems, and monitored alarm systems where they are used.
NR 810.23(2)
(2) Emergency operations. Water suppliers for each community water system shall develop a plan to prepare for, respond to, mitigate and recover from all types of emergency situations, including terrorism, sabotage, natural disasters such as floods and tornadoes, loss of system-wide pressure, and overfeed of chemicals.
NR 810.23(2)(a)
(a) Municipal water systems shall have an emergency operation plan including, at a minimum:
NR 810.23(2)(a)3.
3. Any mutual aid agreements the water utility has with other communities for sharing personnel, equipment and other resources during an emergency.
NR 810.23(2)(b)
(b) Other-than-municipal water systems shall have an emergency operation plan including at a minimum:
NR 810.23(2)(b)1.
1. A list of plumbers, electricians or other contractors that would be available to respond in emergency situations.
NR 810.23 History
History: CR 09-073: cr.
Register November 2010 No. 659, eff. 12-1-10.
NR 810.24
NR 810.24 Water system capacity. All new community and non-transient non-community water systems shall develop and maintain adequate financial, managerial and technical capacity to meet the requirements of this chapter and
42 USC 300f to
300j-26. New community and non-transient non-community water systems are defined as those constructed after September 1, 1999, or those that upgrade system type after that date to become a community or nontransient noncommunity water system.
NR 810.24 Note
Note: 42 USC 300f to
300j-26 is entitled the federal Safe Drinking Water Act.
NR 810.24(1)
(1) New system capacity evaluation. No new community or non-transient non-community water system may commence operation after September 1, 1999, unless the owner of the proposed water system first demonstrates to the satisfaction of the department that the water system shall have and shall maintain adequate financial, managerial and technical capacity to meet the requirements of this chapter and the requirements of
42 USC 300f to
300j-26. Additions to water systems constructed prior to September 1, 1999, are exempt from this requirement unless the additions resulted in an upgrade in system type.
NR 810.24 Note
Note: 42 USC 300f to
300j-26 is entitled the federal Safe Drinking Water Act.
NR 810.24(2)
(2) Capacity evaluation submittal. To demonstrate financial, managerial and technical capacity to the department, before beginning construction of a water system, the owner of a proposed community or non-transient non-community water system shall submit to the department a system capacity evaluation that includes all of the following:
NR 810.24(2)(a)
(a) A written description of the water system design that includes all of the following:
NR 810.24(2)(a)1.
1. For groundwater systems, the proposed well construction and the name of the water-bearing formation.
NR 810.24(2)(a)2.
2. For surface water systems, the name of the source water body and the intake length and intake location.
NR 810.24(2)(a)8.
8. Location of any pressure reducing valves or pressure booster stations.
NR 810.24(2)(b)
(b) Evaluation of the potential for the water quality to be out of compliance with any of the primary or secondary standards of this chapter. For groundwater systems, this evaluation shall be based on a review of water quality information available from nearby existing wells or on the results of water quality monitoring from a test well. For surface water systems, this evaluation shall be based on water quality monitoring from the surface water.
NR 810.24(2)(c)
(c) Anticipated average and maximum daily water use for the proposed water system.
NR 810.24(2)(d)
(d) For groundwater systems, a site assessment that includes all of the following:
NR 810.24(2)(d)1.
1. The separation distances between the well and potential sources of contamination within the proposed wellhead protection area.
NR 810.24(2)(d)4.
4. The location of the well in relation to the 100-year flood elevation.
NR 810.24(2)(e)
(e) For surface water systems, a source water assessment that includes the identification of potential sources of contamination in relation to the intake and the susceptibility of the water system to contamination.
NR 810.24(2)(f)
(f) Anticipated number of industrial, commercial and residential water services.
NR 810.24(2)(g)
(g) Initial and projected customer population and service area.
NR 810.24(2)(h)
(h) Information for the identification, location and contact of the water system designer including the name, address, and telephone number of the system designer and designer's firm.
NR 810.24(2)(i)
(i) Status of all department permits and approvals related to the construction of the water system.
NR 810.24(2)(j)
(j) Information for the identification, location and contact of the water system owner including the name, address and telephone number of the water system owner and the extent of the owner's responsibility for the water system.
NR 810.24(2)(k)
(k) Information for the identification, location and contact of the water system manager including the name, address and telephone number of the system manager.
NR 810.24(2)(L)
(L) Information for the identification, location, and contact of the water system operator including the name, address and telephone number of the water system's certified operator as defined in
s. NR 114.03 (2). If a certified operator has not been selected prior to submitting the capacity evaluation, a timetable for hiring an operator shall be included as part of the capacity evaluation in lieu of the information for the identification, location and contact of the water system operator. The water system may not be placed into operation until the department is provided with the information for the identification, location and contact of the water system operator required in this paragraph.
NR 810.24(2)(m)
(m) A plan identifying all sample locations for all monitoring required under the Safe Drinking Water Act.
NR 810.24(2)(n)
(n) Description of the operational procedures required by this chapter,
chs. NR 809 and
811 and
PSC 185 related to wellhead protection, well abandonment, cross-connection control, operational reporting, meter testing, hydrant and valve exercising and operator certification.
NR 810.24(2)(o)
(o) Description of the rate or fee mechanism for other-than-municipal water systems.
NR 810.24(2)(p)
(p) Copy of the public service commission certificate authorizing the construction and operation, and estimating rates, for municipal water systems regulated by the public service commission.
NR 810.24(2)(q)
(q) Description of the method of payment for the construction and operation of the water system for non-transient non-community water systems.
NR 810.24(2)(r)
(r) Statement from the water system owner on the financial capacity of the water system to meet the requirements of this chapter.
NR 810.24(3)
(3) Capacity evaluation form. The capacity evaluation shall be submitted on a form provided by the department or in a format approved by the department.
NR 810.24 Note
Note: Capacity evaluation forms may be obtained from the department bureau of drinking water and groundwater at no charge by writing to Bureau of Drinking Water and Groundwater, Box 7921, Madison, WI 53707.
NR 810.24(4)
(4) Required qualifications. The information in
sub. (2) (a) to
(e) shall be prepared by a professional engineer for municipal water systems and by a professional engineer or licensed well driller for other-than-municipal or non-transient non-community water systems.
NR 810.24(5)
(5) Waiver procedure for non-community water systems. The department may waive the requirement for the owner to supply information on well construction, well location, water quality monitoring, and operational procedures listed in
sub. (2) (a) to
(n) for non-community water systems provided that the owner acknowledges in writing conformance to the requirements for well construction, well location, water quality monitoring, and water system operation contained in this chapter and
ch. NR 812.
NR 810.24(6)
(6) Engineering or design report. A single engineering or design report may be submitted to satisfy the requirements of
s. NR 811.09 (3) and
(4) and the capacity evaluation required by
sub. (2).