NR 747.70 NR 747.70Monitoring the progress of the scope of work in the bid.
NR 747.70(1)(1)Notification of progress.
NR 747.70(1)(a)(a) The consulting firm holding the contract required in s. NR 747.69 (1) (a) shall report to the department, in a format prescribed by the department, the progress toward completing the scope of work defined in the bid specifications, at each of the following points:
NR 747.70(1)(a)1. 1. Three months after entering into the contract.
NR 747.70(1)(a)2. 2. Twelve months after beginning the work in the successful bid, except as provided in subd. 6.
NR 747.70(1)(a)3. 3. Twelve months after submitting the previous report required under this subsection, except as provided in subd. 6.
NR 747.70(1)(a)4. 4. No later than 10 days after encountering a change in circumstances, as specified in sub. (3).
NR 747.70(1)(a)5. 5. At any other frequency directed by the department.
NR 747.70(1)(a)6. 6. No later than 30 days after completing the work.
NR 747.70(1)(b) (b) For occurrences that are not covered under s. 101.144 (2) (b), Stats., the department shall send the DNR a copy of the reports received under par. (a).
NR 747.70 Note Note: This paragraph is no longer effective and is subject to future repeal. Section 101.144, Stats., was repealed by 2013 Wis. Act 20. The “department" in this paragraph refers to the department of safety and professional services, which no longer has responsibility for occurrences under this section.
NR 747.70 Note Note: See s. NR 747.71 (5) for special requirements for existing sites.
NR 747.70(2) (2)Failure to make progress. If the department determines that the consulting firm is failing to make adequate progress to complete the scope of work defined in the bid specifications for an amount not exceeding the reimbursement cap determined under s. NR 747.68 (7), the department shall so notify the responsible party and may reduce the reimbursement to accurately reflect the work completed.
NR 747.70 Note Note: See s. NR 747.71 (5) for special requirements for existing sites.
NR 747.70(3) (3)Change of circumstances.
NR 747.70(3)(a)(a) For occurrences under the direction of the department, the department may review and modify the reimbursement cap, and may reinitiate the public bidding process in s. NR 747.68, based on a change in circumstances, if any of the following have occurred:
NR 747.70(3)(a)1. 1. Substantial new contamination has been discovered on the site. Substantial contamination must increase remediation costs to either obtain closure or complete a defined scope of work. New contamination is contamination not previously identified, such as contamination in a broader area or deeper depth than previously identified.
NR 747.70(3)(a)2. 2. Abnormal weather, previously unknown geologic conditions, or previously unknown subsurface structures have been encountered that directly affect the activities described in the least costly qualified bid identified under s. NR 747.68 (3).
NR 747.70(3)(b) (b) For occurrences under the direction of the department, the department may review and modify the reimbursement cap, and the department may reinitiate the public bidding process in s. NR 747.68, based on a change of circumstances, if any of the events in par. (a) 1. and 2. have occurred.
NR 747.70 Note Note: See s. NR 747.71 (5) for special requirements for existing sites.
NR 747.70(4) (4)Disqualification from further work on a project.
NR 747.70(4)(a)(a) Grounds for disqualification. The department may disqualify any individual or firm from performing further work on a project, if the individual or firm has done any of the following:
NR 747.70(4)(a)1. 1. Failed to complete a substantive portion of the defined scope of work within the corresponding portion of the reimbursement cap.
NR 747.70(4)(a)2. 2. Failed to complete the scope of work in a bid in a timely manner.
NR 747.70(4)(a)3. 3. Failed to meet requirements in department rules on the project.
NR 747.70(4)(a)4. 4. Failed to do either of the following:
NR 747.70(4)(a)4.a. a. Pay subcontractors within a contracted timeline, after receiving payment for them.
NR 747.70(4)(a)4.b. b. Obtain lien waivers on or before the date of the final payment by the responsible party or the PECFA program, from all subcontractors paid under subd. 4. a.
NR 747.70(4)(a)5. 5. Failed to execute a contract with a responsible party as required in s. NR 747.69 (1).
NR 747.70(4)(a)6. 6. Failed to commence work within 45 days after executing a contract, as required in s. NR 747.69 (3).
NR 747.70 Note Note: See s. NR 747.71 (5) for special requirements for existing sites.
NR 747.70(4)(b) (b) In making disqualification decisions under this section, the department shall only excuse failures that are shown to be due to factors which are beyond the control of a bidding individual or firm, such as a responsible party's inability to obtain financing.
NR 747.70(4)(c) (c) Period of disqualification. The period of disqualification shall be 6 months for the first disqualification, 12 months for the second disqualification, and 24 months for any successive disqualification.
NR 747.70 Note Note: The department may consider disqualification from further work as a contributing factor when applying other disciplinary actions to any individual or firm.
NR 747.70(4)(d) (d) Written notice of disqualification. The department shall provide written notification to any individual or firm disqualified from performing further work on a project. The notification shall specify the reasons for the disqualification, the period of the disqualification, and the right to appeal the department's decision. The notification shall inform the disqualified party that costs for any work on the occurrence during the disqualification, except as otherwise authorized by the department, will not be reimbursed.
NR 747.70(4)(e) (e) Appeals by disqualified individuals or firms.
NR 747.70(4)(e)1.1. An individual or firm that receives a notice of disqualification under this section may appeal as provided in s. NR 747.53.
NR 747.70(4)(e)2. 2. The department shall hold a hearing for an appeal filed under subd. 1. no later than 30 days after receipt of the appeal.
NR 747.70(4)(f) (f) Rebidding or selection of next-lowest, qualified bid. Where an individual or firm has been disqualified under this section, the department may either redirect the scope of work through the entire public bidding process in s. NR 747.68, or reinitiate that process at the bid evaluation stage in s. NR 747.68 (3).
NR 747.70(4)(g) (g) Corrective action by disqualified individual or firm. The department may require an individual or firm that has previously been disqualified to take corrective action specified by the department, to protect owners or operators and the PECFA fund from failure to carry out the work specified in the public bidding process in s. NR 747.68.
NR 747.70 History History: CR 04-058: cr. Register February 2006 No. 602, eff. 5-1-06; correction in (1) (a), (2), (3) (a) (intro.), 2., (b), (4) (a) 5., 6., (e) 1., (f), (g) made under s. 13.92 (4) (b) 7., Stats., Register December 2011 No. 672; corrections in (1) (a) (intro.), (b), (2), (3) (a) (intro.), 2., (b), (4) (a) 3., 5., 6., (e) to (g) made under s. 13.92 (4) (b) 6., 7., Stats., Register October 2013 No. 694.
NR 747.71 NR 747.71Special requirements for existing sites.
NR 747.71(1)(1)Definition. For the purposes of this section, a site investigation in progress is any investigation that began but was not completed before May 1, 2006.
NR 747.71(2) (2)Notifications and initial investigation progress reports for investigations in progress. For site investigations in progress on May 1, 2006, the notification form in s. NR 747.60 (1) and the first investigation progress report under s. NR 747.62 for each occurrence shall be submitted no later than 60 days after that date.
NR 747.71(3) (3)Subsequent requirements. Upon submittal of the notification and report under sub. (2), all of the requirements in s. NR 747.62 shall apply, except the requirement for submitting the initial investigation progress report.
NR 747.71 Note Note: The department forms required in this chapter are available from the Wisconsin DNR, Bureau for Remediation & Redevelopment, P.O. Box 7921, Madison WI 53707-7921, or at http://dnr.wi.gov/topic/brownfields/pecfa.html.
NR 747.71(4) (4)Occurrences with previously completed site investigations. An occurrence for which a site investigation was completed prior to May 1, 2006 shall be subject to the public bidding process in s. NR 747.68 when so determined by the department under s. NR 747.325 or 747.623.
NR 747.71(5) (5)Occurrences with reimbursement caps determined through previous public bidding. For occurrences with reimbursements caps determined through the public bidding process under s. 292.63 (3) (cp), Stats., prior to May 1, 2006, all of the requirements in s. NR 747.70 shall apply, except as follows:
NR 747.71(5)(a) (a) The consulting firm performing the work in the bid specifications shall submit the initial progress report required in s. NR 747.70 (1) (a) 1. 3 months after May 1, 2006.
NR 747.71(5)(b) (b) The consulting firm performing the work in the bid specifications shall submit the progress report required in s. NR 747.70 (1) (a) 2. 12 months after May 1, 2006.
NR 747.71(5)(c) (c) Reimbursement for the progress reports required in s. NR 747.70 (1) (a) shall be in addition to the reimbursement that was previously established through the public bidding process, but may not exceed the reimbursement which is specified for these reports in the department's schedule of usual and customary costs, as established under s. NR 747.325.
NR 747.71(5)(d) (d) The reimbursement cap used in s. NR 747.70 (2) shall be the reimbursement cap determined through the public bidding that preceded May 1, 2006.
NR 747.71(5)(e)1.1. For occurrences under the direction of the department, the department may review and modify the reimbursement cap prescribed in par. (d), and may reinitiate competitive bidding through the public bidding process in s. NR 747.68, if the modification is necessary to obtain compliance with s. 292.63 (3) (c) 3., Stats., and with enforcement standards.
NR 747.71(5)(e)2. 2. For occurrences under the direction of the department, the department may review and modify the reimbursement cap prescribed in par. (d), and the department may reinitiate competitive bidding through the public bidding process in s. NR 747.68, if the modification is necessary to obtain compliance with s. 292.63 (3) (c) 3., Stats., and with enforcement standards.
NR 747.71 Note Note: Under s. 292.63 (3) (c) 3., Stats., a responsible party must “Conduct all remedial action activities at the site of the discharge from the petroleum product storage system or home oil tank system necessary to restore the environment to the extent practicable and minimize the harmful effects from the discharge as required under s. 292.11, Stats."
NR 747.71(5)(f) (f) Section NR 747.70 (4) (a) 5. and 6. does not apply.
NR 747.71 History History: CR 04-058: cr. Register February 2006 No. 602, eff. 5-1-06; correction in (2), (3), (4), (5) (intro.), (a), (b), (c), (d), (e) 1., 2., (f) made under s. 13.92 (4) (b) 7., Stats., Register December 2011 No. 672; corrections in (2) to (4), (5) (a) to (f) made under s. 13.92 (4) (b) 6., 7., Stats., Register October 2013 No. 694.