This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 665.1054 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1055 NR 665.1055Standards: sampling connection systems.
NR 665.1055(1)(1)Equip each sampling connection system with a closed-purge, closed-loop or closed-vent system. The system shall collect the sample purge for return to the process or for routing to the appropriate treatment system. Gases displaced during filling of the sample container are not required to be collected or captured.
NR 665.1055(2) (2)Each closed-purge, closed-loop or closed-vent system required in sub. (1) shall meet one of the following requirements:
NR 665.1055(2)(a) (a) It returns the purged process fluid directly to the process line.
NR 665.1055(2)(b) (b) It collects and recycles the purged process fluid.
NR 665.1055(2)(c) (c) It is designed and operated to capture and transport all the purged process fluid to a waste management unit that complies with the applicable requirements of ss. NR 665.1085 to 665.1087 or a control device that complies with s. NR 665.1060.
NR 665.1055(3) (3)In-situ sampling systems and sampling systems without purges are exempt from subs. (1) and (2).
NR 665.1055 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1056 NR 665.1056Standards: open-ended valves or lines.
NR 665.1056(1)(a) (a) Equip each open-ended valve or line with a cap, blind flange, plug or a second valve.
NR 665.1056(1)(b) (b) The cap, blind flange, plug or second valve shall seal the open end at all times except during operations requiring hazardous waste stream flow through the open-ended valve or line.
NR 665.1056(2) (2)Operate each open-ended valve or line equipped with a second valve in a manner such that the valve on the hazardous waste stream end is closed before the second valve is closed.
NR 665.1056(3) (3)When a double block and bleed system is being used, the bleed valve or line may remain open during operations that require venting the line between the block valves but shall comply with sub. (1) at all other times.
NR 665.1056 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1057 NR 665.1057Standards: valves in gas or vapor service or in light liquid service.
NR 665.1057(1)(1)Monitor each valve in gas or vapor or light liquid service monthly to detect leaks by the methods specified in s. NR 665.1063 (2) and comply with subs. (2) to (5), except as provided in subs. (6) to (8) and ss. NR 665.1061 and 665.1062.
NR 665.1057(2) (2)If an instrument reading of 10,000 ppm or greater is measured, a leak is detected.
NR 665.1057(3)(a)(a) Any valve for which a leak is not detected for 2 successive months may be monitored the first month of every succeeding quarter, beginning with the next quarter, until a leak is detected.
NR 665.1057(3)(b) (b) If a leak is detected, monitor the valve monthly until a leak is not detected for 2 successive months.
NR 665.1057(4)(a)(a) When a leak is detected, repair it as soon as practicable, but no later than 15 calendar days after the leak is detected, except as provided in s. NR 665.1059.
NR 665.1057(4)(b) (b) Make a first attempt at repair no later than 5 calendar days after each leak is detected.
NR 665.1057(5) (5)First attempts at repair include, but are not limited to, the following best practices where practicable:
NR 665.1057(5)(a) (a) Tightening of bonnet bolts.
NR 665.1057(5)(b) (b) Replacement of bonnet bolts.
NR 665.1057(5)(c) (c) Tightening of packing gland nuts.
NR 665.1057(5)(d) (d) Injection of lubricant into lubricated packing.
NR 665.1057(6) (6)Any valve that is designated, as described in s. NR 665.1064 (7) (b), for no detectable emissions, as indicated by an instrument reading of less than 500 ppm above background, is exempt from sub. (1) if the valve meets all of the following requirements:
NR 665.1057(6)(a) (a) It has no external actuating mechanism in contact with the hazardous waste stream.
NR 665.1057(6)(b) (b) It is operated with emissions less than 500 ppm above background determined by the method specified in s. NR 665.1063 (3).
NR 665.1057(6)(c) (c) It is tested for compliance with par. (b) initially upon designation, annually and at other times requested by the department.
NR 665.1057(7) (7)Any valve that is designated, as described in s. NR 665.1064 (8) (a), as an unsafe-to-monitor valve is exempt from sub. (1) if the owner or operator does all of the following:
NR 665.1057(7)(a) (a) Determines that the valve is unsafe to monitor because monitoring personnel would be exposed to an immediate danger as a consequence of complying with sub. (1).
NR 665.1057(7)(b) (b) Adheres to a written plan that requires monitoring of the valve as frequently as practicable during safe-to-monitor times.
NR 665.1057(8) (8)Any valve that is designated, as described in s. NR 665.1064 (8) (b), as a difficult-to-monitor valve is exempt from sub. (1) if all of the following requirements are met:
NR 665.1057(8)(a) (a) The owner or operator of the valve determines that the valve cannot be monitored without elevating the monitoring personnel more than 2 meters above a support surface.
NR 665.1057(8)(b) (b) The hazardous waste management unit within which the valve is located was in operation before June 1, 1995.
NR 665.1057(8)(c) (c) The owner or operator of the valve follows a written plan that requires monitoring of the valve at least once per calendar year.
NR 665.1057 Note Note: The equivalent federal RCRA regulations have a compliance date of June 1, 1990, based on when those rules took effect. The Wisconsin rules, initially promulgated in CR 94-076, became effective on June 1, 1995.
NR 665.1057 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1058 NR 665.1058Standards: pumps and valves in heavy liquid service, pressure relief devices in light liquid or heavy liquid service and flanges and other connectors.
NR 665.1058(1)(1)Monitor pumps and valves in heavy liquid service, pressure relief devices in light liquid or heavy liquid service and flanges and other connectors within 5 days by the method specified in s. NR 665.1063 (2) if evidence of a potential leak is found by visual, audible, olfactory or any other detection method.
NR 665.1058(2) (2)If an instrument reading of 10,000 ppm or greater is measured, a leak is detected.
NR 665.1058(3)(a)(a) When a leak is detected, repair it as soon as practicable, but not later than 15 calendar days after it is detected, except as provided in s. NR 665.1059.
NR 665.1058(3)(b) (b) Make the first attempt at repair no later than 5 calendar days after each leak is detected.
NR 665.1058(4) (4)First attempts at repair include, but are not limited to, the best practices described under s. NR 665.1057 (5).
NR 665.1058(5) (5)Any connector that is inaccessible or is ceramic or ceramic-lined (e.g., porcelain, glass or glass-lined) is exempt from sub. (1) and from s. NR 665.1064.
NR 665.1058 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1059 NR 665.1059Standards: delay of repair.
NR 665.1059(1)(1)Delay of repair of equipment for which leaks have been detected shall be allowed if the repair is technically infeasible without a hazardous waste management unit shutdown. In such a case, repair the equipment before the end of the next hazardous waste management unit shutdown.
NR 665.1059(2) (2)Delay of repair of equipment for which leaks have been detected shall be allowed for equipment that is isolated from the hazardous waste management unit and that does not continue to contain or contact hazardous waste with organic concentrations at least 10 percent by weight.
NR 665.1059(3) (3)Delay of repair for valves shall be allowed if all of the following conditions are met:
NR 665.1059(3)(a) (a) The owner or operator determines that emissions of purged material resulting from immediate repair are greater than the emissions likely to result from delay of repair.
NR 665.1059(3)(b) (b) When repair procedures are effected, collect and destroy or recover the purged material in a control device complying with s. NR 665.1060.
NR 665.1059(4) (4)Delay of repair for pumps shall be allowed if all of the following conditions are met:
NR 665.1059(4)(a) (a) The repair requires use of a dual mechanical seal system that includes a barrier fluid system.
NR 665.1059(4)(b) (b) The repair is completed as soon as practicable, but not later than 6 months after the leak was detected.
NR 665.1059(5) (5)Delay of repair beyond a hazardous waste management unit shutdown shall be allowed for a valve if valve assembly replacement is necessary during the hazardous waste management unit shutdown, valve assembly supplies have been depleted and valve assembly supplies had been sufficiently stocked before the supplies were depleted. Repair may not be delayed beyond the next hazardous waste management unit shutdown unless the next hazardous waste management unit shutdown occurs sooner than 6 months after the first hazardous waste management unit shutdown.
NR 665.1059 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1060 NR 665.1060Standards: closed-vent systems and control devices.
NR 665.1060(1)(1)Owners and operators of closed-vent systems and control devices subject to this subchapter shall comply with s. NR 665.1033.
NR 665.1060(2)(a)(a) The owner or operator of an existing facility who can not install a closed-vent system and control device to comply with this subchapter on the effective date that the facility becomes subject to this subchapter shall prepare an implementation schedule that includes dates by which the closed-vent system and control device will be installed and in operation. Install the controls as soon as possible, but the implementation schedule may allow up to 30 months after the effective date that the facility becomes subject to this subchapter for installation and startup.
NR 665.1060(2)(b) (b) Any units that begin operation after June 1, 1995, and are subject to this subchapter when operation begins, shall comply with the rules immediately (i.e., shall have control devices installed and operating on startup of the affected unit; the 30-month implementation schedule does not apply).
NR 665.1060(2)(c) (c) The owner or operator of any facility in existence on the effective date of a department rule amendment that renders the facility subject to this subchapter shall comply with this subchapter as soon as practicable but no later than 30 months after the amendment's effective date. When control equipment required by this subchapter can not be installed and begin operation by the effective date of the amendment, prepare an implementation schedule that includes specific calendar dates for award of contracts or issuance of purchase orders for the control equipment, initiation of on-site installation of the control equipment, completion of the control equipment installation and performance of any testing to demonstrate that the installed equipment meets the applicable standards of this subchapter. Enter the implementation schedule in the operating record or in a permanent, readily available file located at the facility.
NR 665.1060(2)(d) (d) Owners and operators of facilities and units that become newly subject to this subchapter after August 1, 2006 due to an action other than those described in par. (c) shall comply with all applicable requirements immediately (i.e., shall have control devices installed and operating on the date the facility or unit becomes subject to this subchapter; the 30-month implementation schedule does not apply).
NR 665.1060 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06.
NR 665.1061 NR 665.1061Alternative standards for valves in gas or vapor service or in light liquid service: percentage of valves allowed to leak.
NR 665.1061(1)(1)An owner or operator subject to s. NR 665.1057 may elect to have all valves within a hazardous waste management unit comply with an alternative standard which allows no greater than 2 percent of the valves to leak.
NR 665.1061(2) (2)An owner or operator who decides to comply with the alternative standard of allowing 2 percent of valves to leak shall meet all of the following requirements:
NR 665.1061(2)(a) (a) Conduct a performance test as specified in sub. (3) initially upon designation, annually and at other times requested by the department.
NR 665.1061(2)(b) (b) If a valve leak is detected, repair it according to s. NR 665.1057 (4) and (5).
NR 665.1061(3) (3)Conduct performance tests according to all of the following:
NR 665.1061(3)(a) (a) Monitor all valves subject to s. NR 665.1057, within the hazardous waste management unit, within one week by the methods specified in s. NR 665.1063 (2).
NR 665.1061(3)(b) (b) If an instrument reading of 10,000 ppm or greater is measured, a leak is detected.
NR 665.1061(3)(c) (c) Determine the leak percentage by dividing the number of valves subject to s. NR 665.1057 for which leaks are detected, by the total number of valves subject to s. NR 665.1057 within the hazardous waste management unit.
NR 665.1061 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06; CR 16-007: r. (2) (a), renum. (2) (b), (c) to (2) (a), (b), r. (4) Register July 2017 No. 739, eff. 8-1-17.
NR 665.1062 NR 665.1062Alternative standards for valves in gas or vapor service or in light liquid service: skip period leak detection and repair.
NR 665.1062(1)(1)An owner or operator subject to s. NR 665.1057 may elect for all valves within a hazardous waste management unit to comply with one of the alternative work practices specified in sub. (2) (b) and (c).
NR 665.1062(2)(a)(a) An owner or operator shall comply with the requirements for valves in s. NR 665.1057, except as described in pars. (b) and (c).
NR 665.1062(2)(b) (b) After 2 consecutive quarterly leak detection periods with the percentage of valves leaking equal to or less than 2 percent, an owner or operator may begin to skip one of the quarterly leak detection periods (i.e., monitor for leaks once every 6 months) for the valves subject to s. NR 665.1057.
NR 665.1062(2)(c) (c) After 5 consecutive quarterly leak detection periods with the percentage of valves leaking equal to or less than 2 percent, an owner or operator may begin to skip 3 of the quarterly leak detection periods (i.e., monitor for leaks once every year) for the valves subject to s. NR 665.1057.
NR 665.1062(2)(d) (d) If the percentage of valves leaking is greater than 2 percent, the owner or operators shall monitor monthly in compliance with s. NR 665.1057, but may again elect to use this section after meeting s. NR 665.1057 (3) (a).
NR 665.1062 History History: CR 05-032: cr. Register July 2006 No. 607, eff. 8-1-06; CR 16-007: renum. (1) (a) to (1), r. (1) (b) Register July 2017 No. 739, eff. 8-1-17.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.