NR 463.18(3)
(3) Annual compliance certifications. For the purpose of annual certifications of compliance required by
s. NR 439.03 (1) (c), the owner or operator shall certify continuing compliance based upon, but not limited to, both of the following conditions:
NR 463.18(3)(a)
(a) Any and all periods of excess emissions, as defined in
sub. (2) (a), that occurred during the year were reported.
NR 463.18(3)(b)
(b) All monitoring, recordkeeping and reporting requirements were met during the year.
NR 463.18 History
History: CR 04-023: cr.
Register December 2008 No. 636, eff. 1-1-09.
NR 463.19(1)(a)
(a) The owner or operator shall maintain files of all information, including all reports and notifications, required by
s. NR 460.09 (2) and this subchapter.
NR 463.19(1)(b)
(b) The owner or operator shall retain each record for at least 5 years following the date of each occurrence, measurement, maintenance, corrective action, report or record. The most recent 2 years of records shall be retained at the facility. The remaining 3 years of records may be retained off site.
NR 463.19(1)(c)
(c) The owner or operator may retain records on microfilm, computer disks, magnetic tape or microfiche.
NR 463.19(1)(d)
(d) The owner or operator may report required information on paper or on a labeled computer disk using commonly available and department compatible computer software.
NR 463.19(2)
(2) In addition to the general records required by
s. NR 460.09 (2), the owner or operator of a new or existing affected source, including an emission unit in a secondary aluminum processing unit, shall maintain records of all of the following:
NR 463.19(2)(a)
(a) For each affected source and emission unit with emissions controlled by a fabric filter or a lime-injected fabric filter each of the following as applicable:
NR 463.19(2)(a)1.
1. If a bag leak detection system is used, the number of total operating hours for the affected source or emission unit during each 6-month reporting period, records of each alarm, the time of the alarm, the time corrective action was initiated and completed and a brief description of the cause of the alarm and the corrective actions taken.
NR 463.19(2)(a)2.
2. If a continuous opacity monitoring system is used, records of opacity measurement data, including records where the average opacity of any 6-minute period exceeds 5%, with a brief explanation of the cause of the emissions, the time the emissions occurred, the time corrective action was initiated and completed and the corrective action taken.
NR 463.19(2)(a)3.
3. If an aluminum scrap shredder is subject to visible emission observation requirements, records of all observations made using Method 9 in Appendix A to
40 CFR part 60, incorporated by reference in
s. NR 484.04 (13), including records of any visible emissions during a 30-minute daily test, with a brief explanation of the cause of the emissions, the time the emissions occurred, the time corrective action was initiated and completed and the corrective action taken.
NR 463.19(2)(b)
(b) For each affected source with emissions controlled by an afterburner, both of the following:
NR 463.19(2)(b)1.
1. Records of 15-minute block average afterburner operating temperature, including any period when the average temperature in any 3-hour block period falls below the compliant operating parameter value with a brief explanation of the cause of the excursion and the corrective action taken.
NR 463.19(2)(c)
(c) For each scrap dryer, delacquering kiln or decoating kiln and group 1 furnace, subject to D&F and HCl emission standards with emissions controlled by a lime-injected fabric filter, records of 15-minute block average inlet temperatures for each lime-injected fabric filter, including any period when the 3-hour block average temperature exceeds the compliant operating parameter value +14
°C (+25
°F), with a brief explanation of the cause of the excursion and the corrective action taken.
NR 463.19(2)(d)
(d) For each affected source and emission unit with emissions controlled by a lime-injected fabric filter, the requirements in
subd. 1. and either
subd. 2. or
3.:
NR 463.19(2)(d)1.
1. Records of inspections at least once every 8-hour period verifying that lime is present in the feeder hopper or silo and flowing, including any inspection where blockage is found, with a brief explanation of the cause of the blockage and the corrective action taken, and records of inspections at least once every 4-hour period for the subsequent 3 days. If flow monitors, pressure drop sensors or load cells are used to verify that lime is present in the hopper and flowing, records of all monitor or sensor output including any event where blockage was found, with a brief explanation of the cause of the blockage and the corrective action taken.
NR 463.19(2)(d)2.
2. If the lime feeder setting is monitored, records of daily inspections of feeder setting, including records of any deviation of the feeder setting from the setting used in the performance test, with a brief explanation of the cause of the deviation and the corrective action taken.
NR 463.19(2)(d)3.
3. If the lime addition rate for a noncontinuous lime injection system is monitored pursuant to the approved alternative monitoring requirements in
s. NR 463.15 (22), records of the time and mass of each lime addition during each operating cycle or time period used in the performance test and calculations of the average lime addition rate in lb/ton of feed or charge.
NR 463.19(2)(e)
(e) For each group 1 furnace, with or without add-on air pollution control devices, or in-line fluxer, records of 15-minute block average weights of gaseous or liquid reactive flux injection, total reactive flux injection rate and calculations, including records of the identity, composition and weight of each addition of gaseous, liquid or solid reactive flux, including records of any period the rate exceeds the compliant operating parameter value and corrective action taken.
NR 463.19(2)(g)
(g) For each affected source and emission unit subject to an emission standard in kg/Mg (lb/ton) of feed or charge, records of feed or charge, or throughput, weights for each operating cycle or time period used in the performance test.
NR 463.19(2)(h)
(h) Approved site-specific monitoring plan for a group 1 furnace without add-on air pollution control devices with records documenting conformance with the plan.
NR 463.19(2)(i)
(i) Records of all charge materials for each thermal chip dryer, dross-only furnace, and group 1 melting and holding furnaces without air pollution control devices processing only clean charge.
NR 463.19(2)(j)
(j) Operating logs for each group 1 sidewell furnace with add-on air pollution control devices documenting conformance with operating standards for maintaining the level of molten metal above the top of the passage between the sidewell and hearth during reactive flux injection and for adding reactive flux only to the sidewell or a furnace hearth equipped with a control device for PM, HCl and D&F emissions.
NR 463.19(2)(k)
(k) For each in-line fluxer for which the owner or operator has certified that no reactive flux was used, one of the following:
NR 463.19(2)(k)1.
1. Operating logs which establish that no source of reactive flux was present at the in-line fluxer.
NR 463.19(2)(k)3.
3. Operating logs which document each flux gas, agent or material used during each operating cycle.
NR 463.19(2)(L)
(L) Records of all charge materials and fluxing materials or agents for a group 2 furnace.
NR 463.19(2)(m)
(m) Records of monthly inspections for proper unit labeling for each affected source and emission unit subject to labeling requirements.
NR 463.19(2)(n)
(n) Records of annual inspections of emission capture and collection and closed vent systems.
NR 463.19(2)(o)
(o) Records for any approved alternative monitoring or test procedure.
NR 463.19(2)(p)
(p) Current copy of all required plans, including any revisions, with records documenting conformance with the applicable plan, including all of the following:
NR 463.19(2)(p)3.
3. Site-specific secondary aluminum processing unit emission plan, if applicable.
NR 463.19(2)(q)
(q) For each secondary aluminum processing unit, records of total charge weight, or if the owner or operator chooses to comply on the basis of aluminum production, total aluminum produced for each 24-hour period and calculations of 3-day, 24-hour rolling average emissions.
NR 463.19 History
History: CR 04-023: cr.
Register December 2008 No. 636, eff. 1-1-09.
NR 463.20
NR 463.20 Applicability of general provisions. The requirements of the general provisions in
ch. NR 460 that are applicable to the owner or operator subject to the requirements of this subchapter are shown in
ch. NR 460 Appendix RRR.
NR 463.20 History
History: CR 04-023: cr.
Register December 2008 No. 636, eff. 1-1-09; correction made under s.
13.92 (4) (b) 1., Stats.,
Register December 2008 No. 636;
correction made under s. 35.17, Stats., Register June 2015 No. 714. NR 463.21
NR 463.21 What this subchapter covers. NR 463.21(1)
(1)
What is the purpose of this subchapter? This subchapter establishes national emission standards for hazardous air pollutants (NESHAP) for iron and steel foundries. This subchapter also establishes requirements to demonstrate initial and continuous compliance with the emissions limitations, work practice standards and operation and maintenance requirements in this subchapter.
NR 463.21(2)
(2) Am I subject to this subchapter? You are subject to this subchapter if you own or operate an iron and steel foundry that is, or is part of, a major source of hazardous air pollutant (HAP) emissions. Your iron and steel foundry is a major source of HAP for purposes of this subchapter if it emits or has the potential to emit any single HAP at a rate of 10 tons or more per year or any combination of HAP at a rate of 25 tons or more per year or if it is located at a facility that emits or has the potential to emit any single HAP at a rate of 10 tons or more per year or any combination of HAP at a rate of 25 tons or more per year.
NR 463.21(3)
(3) What parts of my foundry does this subchapter cover? NR 463.21(3)(a)(a) The affected source is a new or existing iron and steel foundry.
NR 463.21(3)(b)
(b) This subchapter covers emissions from metal melting furnaces, scrap pre-heaters, pouring areas, pouring stations, automated conveyor and pallet cooling lines, automated shakeout lines and mold and core making lines. This subchapter also covers fugitive emissions from foundry operations.
NR 463.21(3)(c)
(c) An affected source is existing if you commenced construction or reconstruction of the affected source before December 23, 2002.
NR 463.21(3)(d)
(d) An affected source is new if you commenced construction or reconstruction of the affected source on or after December 23, 2002. An affected source is reconstructed if it meets the definition of “reconstruction'' in
s. NR 463.22.
NR 463.21(4)
(4) When do I have to comply with this subchapter? NR 463.21(4)(a)(a) Except as specified in
par. (b), if you have an existing affected source, you shall comply with each emissions limitation, work practice standard and operation and maintenance requirement in this subchapter that applies to you no later than April 23, 2007. Major source status for existing affected sources shall be determined no later than April 23, 2007.
NR 463.21(4)(b)
(b) If you have an existing affected source, you shall comply with the work practice standards in
s. NR 463.23 (2) (b) or
(c), as applicable, no later than April 22, 2005.
NR 463.21(4)(c)
(c) If you have a new affected source for which the initial startup date is on or before April 22, 2004, you shall comply with each emissions limitation, work practice standard and operation and maintenance requirement in this subchapter that applies to you by April 22, 2004.
NR 463.21(4)(d)
(d) If you have a new affected source for which the initial startup date is after April 22, 2004, you shall comply with each emissions limitation, work practice standard and operation and maintenance requirement in this subchapter that applies to you upon initial startup.
NR 463.21(4)(e)
(e) If your iron and steel foundry is an area source that becomes a major source of HAP, you shall meet the requirements of
s. NR 460.05 (3) (c).
NR 463.21 Note
Note: Several of these notifications must be submitted before the compliance date for your affected source.
NR 463.21 History
History: CR 06-110: cr.
Register July 2007 No. 619, eff. 8-1-07.
NR 463.22
NR 463.22 What definitions apply to this subchapter? For terms not defined in this section, the definitions contained in
chs. NR 400 and
460 apply to the terms in this subchapter, with definitions in
ch. NR 460 taking precedence over definitions in
ch. NR 400. If this section defines a term which is also defined in
ch. NR 400 or
460, the definition in this section applies in this subchapter. In this subchapter:
NR 463.22(1)
(1) “Automated conveyor and pallet cooling line" means any dedicated conveyor line or area used for cooling molds received from pouring stations.
NR 463.22(2)
(2) “Automated shakeout line" means any mechanical process unit designed for and dedicated to separating a casting from a mold. These mechanical processes include shaker decks, rotary separators and high-frequency vibration units. Automated shakeout lines do not include manual processes for separating a casting from a mold, such as personnel using a hammer, chisel, pick ax, sledge hammer or jackhammer.
NR 463.22(3)
(3) “Bag leak detection system" means a system that is capable of continuously monitoring relative particulate matter loadings in the exhaust of a baghouse to detect bag leaks and other upset conditions. A bag leak detection system includes an instrument that operates on triboelectric, electrodynamic, light scattering, light transmittance or other effect to continuously monitor relative particulate matter loadings.
NR 463.22(4)
(4) “Binder chemical" means a component of a system of chemicals used to bind sand together into molds, mold sections and cores through chemical reaction as opposed to pressure.
NR 463.22(5)
(5) “Capture system" means the collection of components used to capture gases and fumes released from one or more emissions points and then convey the captured gas stream to a control device or to the atmosphere. A capture system may include the following components as applicable to a given capture system design: duct intake devices, hoods, enclosures, ductwork, dampers, manifolds, plenums and fans.
NR 463.22(6)
(6) “Cold box mold or core making line" means a mold or core making line in which the formed aggregate is hardened by catalysis with a gas.
NR 463.22(7)
(7) “Combustion device" means an afterburner, thermal incinerator or scrap preheater.
NR 463.22(8)
(8) “Conveyance" means the system of equipment that is designed to capture pollutants at the source, convey them through ductwork and exhaust them using forced ventilation. A conveyance may include control equipment designed to reduce emissions of the pollutants. Emissions that are released through windows, vents or other general building ventilation or exhaust systems are not considered to be discharged through a conveyance.
NR 463.22(9)
(9) “Cooling" means the process of molten metal solidification within the mold and subsequent temperature reduction prior to shakeout.
NR 463.22(10)
(10) “Cupola" means a vertical cylindrical shaft furnace that uses coke and forms of iron and steel such as scrap and foundry returns as the primary charge components and melts the iron and steel through combustion of the coke by a forced upward flow of heated air.
NR 463.22(11)
(11) “Deviation" means any instance in which an affected source or an owner or operator of an affected source fails to meet any of the following:
NR 463.22(11)(a)
(a) Any requirement or obligation established by this subchapter, including any emission limitation, operating limit, work practice standard or operation and maintenance requirement.
NR 463.22(11)(b)
(b) Any term or condition that is adopted to implement an applicable requirement in this subchapter and that is included in the operating permit for any iron and steel foundry required to obtain an operating permit.
NR 463.22(11)(c)
(c) Any emission limitation, operating limit or work practice standard in this subchapter during startup, shutdown or malfunction, regardless of whether or not the failure is permitted by this subchapter.
NR 463.22(12)
(12) “Electric arc furnace" means a vessel in which forms of iron and steel, such as scrap and foundry returns, are melted through resistance heating by an electric current flowing through the arcs formed between the electrodes and the surface of the metal and also flowing through the metal between the arc paths.
NR 463.22(13)
(13) “Electric induction furnace" means a vessel in which forms of iron and steel, such as scrap and foundry returns, are melted though resistance heating by an electric current that is induced in the metal by passing an alternating current through a coil surrounding the metal charge or surrounding a pool of molten metal at the bottom of the vessel.
NR 463.22(14)
(14) “Emissions limitation" has the meaning given in s.
285.01 (16), Stats., and includes any operating limit specified in this subchapter.
NR 463.22(15)
(15) “Exhaust stream" means gases emitted from a process through a conveyance, as defined in
sub. (8).
NR 463.22(16)
(16) “Free organic liquids" means material that fails the paint filter test by Method 9095A, “Paint Filter Liquids Test", Revision 1, December 1996, as published in EPA Publication SW–846 “Test Methods for Evaluating Solid Waste, Physical/Chemical Methods", incorporated by reference in
s. NR 484.06 (4) (e). If any portion of the material passes through and drops from the filter within the 5-minute test period, the material contains free liquids.
NR 463.22(17)
(17) “Fresh acid solution" means a sulfuric acid solution used for the control of triethylamine emissions that has a pH of 2.0 or less.
NR 463.22(18)
(18) “Fugitive emissions" means any pollutant released to the atmosphere that is not discharged through a conveyance, as defined in
sub. (8).
NR 463.22(19)
(19) “Furan warm box mold or core making line" means a mold or core making line in which the binder chemical system used is that system commonly designated as a furan warm box system by the foundry industry.
NR 463.22(20)
(20) “Iron and steel foundry" means a facility or portion of a facility that melts one or more of the following: scrap, ingot or other forms of iron and steel, and pours the resulting molten metal into molds to produce final or near final shape products for introduction into commerce. Research and development facilities and operations that only produce non-commercial castings are not included in this definition.
NR 463.22(21)
(21) “Metal melting furnace" means a cupola, electric arc furnace or electric induction furnace that converts one or more of the following: scrap, foundry returns and other solid forms of iron and steel to a liquid state. Metal melting furnace does not include a holding furnace, an argon oxygen decarburization vessel or ladle that receives molten metal from a metal melting furnace, and to which metal ingots or other material may be added to adjust the metal chemistry.
NR 463.22(22)
(22) “Mold or core making line" means the collection of equipment that is used to mix an aggregate of sand and binder chemicals, form the aggregate into final shape and harden the formed aggregate. A mold or core making line does not include a line for making green sand molds or cores.