BMC is the average baseline mercury concentration of fuel, in pounds per mmBtu, contained in the fuels combusted in the EGU during the baseline determination year
Fuel Hgannual is the total mass of mercury contained in the fuel determined in subd. 1.
HIi is the total amount of fuel, in mmBtu, consumed each hour i, during the baseline determination year
h is the total number of hours fuel is consumed during the baseline determination year
NR 446.185(1)(f)3. 3. Calculate the baseline mercury emissions according to Equation 12 as the baseline mercury concentration times the 3-year average of annual fuel consumption, in mmBtu, for the baseline determination year and 2 years prior to the baseline determination year.
- See PDF for diagram PDF   Equation 12
where:
BME is the baseline mercury emissions for the EGU in pounds
BMC is the baseline mercury concentration for the EGU determined in subd. 2., in pounds per mmBtu.
HIi is the amount of fuel, in mmBtu combusted in the EGU for each hour i during each year y
h is the total number of hours fuel is combusted in the EGU during each year
NR 446.185(1)(g) (g) When determining annual allowable mercury emissions for achieving compliance on a unit-by-unit basis, use one of the following equations as applicable:
NR 446.185(1)(g)1. 1. For a percent reduction mercury emission limitation, Equation 13.
- See PDF for diagram PDF   Equation 13
where:
Hgallowable is the mass of mercury emissions allowed for the EGU for the compliance year
BME is the baseline emissions for the EGU as determined in par. (f) 3.
Hg CE is the applicable requirement for percent mercury emission reduction divided by 100.
NR 446.185(1)(g)2. 2. For a mercury output emission limitation, Equation 14.
- See PDF for diagram PDF Equation 14
where:
Hgallowable is the mass of mercury emissions allowed for the compliance year
GEOGWh is the annual gross energy output of the EGU, in GWh, as determined in s. NR 446.18 (4) for the compliance year
BMC is the baseline mercury concentration determined in par. (f) 2. for the EGU in pounds per mmBtu
Hg CE is the applicable requirement for percent mercury control removal divided by 100
HIi is the amount of fuel, in mmBtu combusted each hour i, in the baseline determination year
h is the total number of hours fuel is combusted during the calendar year designated for measuring baseline emissions data under par. (c)
EGWh is the annual gross electric output, in GWh, for the baseline determination year calculated according to s. NR 446.18 (4) (a)
NR 446.185(2) (2)Alternative SO2 compliance determination.
NR 446.185(2)(a)(a) The owner or operator of a coal-fired EGU may demonstrate compliance with the SO2 emission limitation in s. NR 446.14 (1) by demonstrating a minimum SO2 control efficiency equal to or greater than 90% removal of sulfur from fuels combusted in the EGU each year, excluding startup and shutdown, using a method approved by the department.
NR 446.185(2)(b) (b) If electing to demonstrate compliance according to par. (a), the owners or operators of a coal-fired EGU shall submit an SO2 compliance demonstration procedure for department approval no later than October 1, 2013. The compliance procedure shall include test methods to determine sulfur removal from fuel and operating and parametric monitoring procedures to ensure continuous operation of control equipment consistent with maintaining the required control efficiency.
NR 446.185(3) (3)Alternative methods and procedures. The owner or operator of a coal-fired EGU may use methods and procedures in determining annual allowable emissions as approved by the department to account for any of the following:
NR 446.185(3)(a) (a) The contribution to mercury emissions by non-fuel materials inherent to pollution control processes. The contribution to the annual allowable emissions may not exceed the amount calculated when substituting annual mercury content of non-fuel materials for annual fuel mercury content in Equation 7 in s. NR 446.18 (5) (a) 1.
NR 446.185(3)(b) (b) When monitoring or implementing control equipment for a stack serving multiple EGUs.
NR 446.185 History History: CR 07-036: cr. Register November 2008 No. 635, eff. 12-1-08; correction in (3) made under s. 13.92 (4) (b) 1., Stats., Register November 2008 No. 635; CR 13-089: am. (1) (b) Register July 2014 No. 703, eff. 8-1-14.
NR 446.19 NR 446.19 Evaluation reports.
NR 446.19(1) (1) The department shall report to the natural resources board by August 31, 2013. This report shall include:
NR 446.19(1)(a) (a) An evaluation of the scientific and technology developments in relation to the control or reduction of mercury emissions.
NR 446.19(1)(b) (b) An evaluation of whether the mercury requirements in this subchapter are achievable, given the scientific and technological developments.
NR 446.19(1)(c) (c) Recommendations for revisions to this subchapter or other actions including additional compliance flexibility to achieve the mercury emission reduction requirement in s. NR 446.14 (1) (c) 3., given the scientific and technological developments.
NR 446.19(2) (2) In addition to the report required under sub. (1), the department shall report to the natural resources board within 6 months of the date of promulgation of a federal regulation under section 111 or 112 of the Act (42 USC 7411 or 7412) or the enactment of a federal law that has mercury reduction requirements for the mercury emission sources affected by this subchapter. The report shall include a comparison of the federal requirements and the requirements of this subchapter along with recommendations for revisions to this subchapter or other actions.
NR 446.19(3) (3) The natural resources board shall review these reports and, if they include recommendations for rule revisions or other actions, determine whether the department should proceed with actions based on the recommendations.
NR 446.19 History History: CR 07-036: cr. Register November 2008 No. 635, eff. 12-1-08.
subch. IV of ch. NR 446 Subchapter IV — Mercury Emission Standards for Other Sources
NR 446.20 NR 446.20 Mercury emission limits. No person may cause, allow or permit emissions of mercury:
NR 446.20(1) (1) In quantities greater than 2.3 kg (5.1 lbs) per 24-hour period from mercury cell chlor-alkali plants, or mercury ore processing facilities.
NR 446.20(2) (2) In quantities greater than 3.2 kg (7.1 lbs) per 24-hour period from sludge incineration plants, sludge drying plants, or a combination of these that process wastewater treatment plant sludges.
NR 446.20 History History: Renum. from NR 154.19 (3) (a), Register, September, 1986, No. 369, eff. 10-1-86; am. (intro.), Register, May, 1992, No. 437, eff. 6-1-92; am. (2), Register, May, 1994, No. 461, eff. 6-1-94; CR 01-081: (1) and (2) renum. from NR 446.03 (2) and (3) Register September 2004 No. 585, eff. 10-1-04; CR 07-036: renum. from NR 446.14, am. (1) and (2) Register November 2008 No. 635, eff. 12-1-08.
NR 446.21 NR 446.21 Stack sampling.
NR 446.21(1)(1) Mercury ore processing facilities.
NR 446.21(1)(a)(a) Unless a waiver of emission testing is requested and obtained from the department, each owner or operator of a facility processing mercury ore on which construction or modification commenced after February 1, 1984 shall test emissions from the source in accordance with Method 101 within 90 days after startup.
NR 446.21(1)(b) (b) The department shall be notified at least 30 days prior to a stack or performance test to afford it the opportunity to have a representative present to witness the testing procedures. The notice shall include a test plan in accordance with s. NR 439.07.
NR 446.21(1)(c) (c) Samples shall be taken over such a period as is necessary to accurately determine the maximum emissions which will occur in a 24-hour period. No changes in the operation may be made which would potentially increase emissions above that determined by the most recent source test until the new emission level has been estimated by calculation and the results reported to the department.
NR 446.21(1)(d) (d) All samples shall be analyzed, and mercury emissions shall be determined within 30 days after the source test. Each determination shall be reported to the department by registered letter dispatched before the close of the next business day following the determination.
NR 446.21(1)(e) (e) Records of emission test results and other data needed to determine total emissions shall be retained at the source and made available for inspection by a department representative for a minimum of 2 years.
NR 446.21(2) (2)Mercury chlor-alkali plants—hydrogen and end box ventilation gas streams.
NR 446.21(2)(a)(a) Unless a waiver of emission testing is requested and obtained from the department, each owner or operator of a mercury chlor-alkali cell on which construction or modification commenced after February 1, 1984 shall test emissions from hydrogen streams in accordance with Method 102 and from end-box gas streams in accordance with Method 101 within 90 days after startup.
NR 446.21(2)(b) (b) The department shall be notified at least 30 days in advance of stack or performance tests to afford it the opportunity to have a representative present to witness the testing procedures. The notice shall include a test plan in accordance with s. NR 439.07.
NR 446.21(2)(c) (c) Samples shall be taken over such a period as is necessary to accurately determine the maximum emissions which will occur in a 24-hour period. No changes in the operation may be made which would potentially increase emissions above that determined by the most recent source test until the new emission level has been estimated by calculation and the results reported to the department.
NR 446.21(2)(d) (d) All samples shall be analyzed, and mercury emissions shall be determined within 30 days after the source test. All determinations shall be reported to the department by registered letter dispatched before the close of the next business day following the determination.
NR 446.21(2)(e) (e) Records of emissions test results and other data needed to determine total emissions shall be retained at the source and made available for inspection by a department representative for a minimum of 2 years.
NR 446.21(3) (3)Mercury chlor-alkali plants—cell room ventilation system.
NR 446.21(3)(a)(a) Stationary sources using mercury chlor-alkali cells may test cell room emissions in accordance with par. (b), or demonstrate compliance with par. (d) and assume ventilation emissions of 1.3 kg (2.9 lbs) per day of mercury.
NR 446.21(3)(b) (b) Unless a waiver of emission testing is requested and obtained from the department, each owner or operator of a new or modified chlor-alkali plant shall pass all cell room air in forced gas streams through stacks suitable for testing and shall test emissions from the cell room in accordance with Method 101 within 90 days after startup.
NR 446.21(3)(c) (c) The department shall be notified at least 30 days in advance of stack or performance tests to afford it the opportunity to have a representative present to witness the testing procedures. The notice shall provide a test plan in accordance with s. NR 439.07.
NR 446.21(3)(d) (d) An owner or operator may carry out U.S. environmental protection agency approved design, maintenance and housekeeping practices.
NR 446.21 Note Note: A list of approved practices is provided in appendix A of “Review of National Emission Standards for Mercury," EPA-450/3-84-014, December 1984, incorporated by reference in s. NR 484.05 (9).
NR 446.21(4) (4)Sludge incineration and drying plants.
NR 446.21(4)(a)(a) Unless a waiver of emission testing is requested and obtained from the department, each owner or operator of sludge incineration plants and drying plants on which construction or modification commenced after February 1, 1984 shall test emissions from the source within 90 days of startup. The tests shall be conducted in accordance with Method 101A, using the procedures in par. (f).
NR 446.21(4)(b) (b) The department shall be notified at least 30 days in advance of stack or performance tests to afford it the opportunity to have a representative present to witness the testing procedures. The notice shall include a test plan in accordance with s. NR 439.07.
NR 446.21(4)(c) (c) Samples shall be taken over such a period as is necessary to determine accurately the maximum emissions which will occur in a 24-hour period. No changes may be made in the operation which would potentially increase emissions above the level determined by the most recent stack tests until the new emission level has been estimated by calculation and the results reported to the department.
NR 446.21(4)(d) (d) All samples shall be analyzed, and mercury emissions shall be determined within 30 days after the stack test. All determinations shall be reported to the department by registered letter dispatched before the close of the next business day following the determination.
NR 446.21(4)(e) (e) Records of emission test results and other data needed to determine total emissions shall be retained at the source and shall be made available for inspection by a department representative for a minimum of 2 years.
NR 446.21(4)(f) (f) If an owner or operator uses Method 105, the following procedures shall be adhered to:
NR 446.21(4)(f)1. 1. The sludge shall be sampled after dewatering and before incineration or drying, at a location that provides a representative sample of the sludge that is charged to the incinerator or dryer. Eight consecutive grab samples shall be obtained at intervals of between 45 and 60 minutes and thoroughly mixed into one sample. Each of the 8 grab samples shall have a volume of at least 200 milliliters but not more than 400 milliliters. A total of 3 composite samples shall be obtained within an operating period of 24 hours. When the 24-hour operating period is not continuous, the total sampling period may not exceed 72 hours after the first grab sample is obtained. Samples may not be exposed to any condition that may result in mercury contamination or loss.
NR 446.21(4)(f)2. 2. The maximum 24-hour period sludge incineration or drying rate shall be determined by use of a flow rate measurement device that can measure the mass rate of sludge charged to the incinerator or dryer with an accuracy of plus or minus 5% over its operating range. Other methods of measuring sludge mass charging rates may be used if they have received prior approval by the department.
NR 446.21(4)(f)3. 3. The handling, preparation and analysis of sludge samples shall be accomplished in accordance with Method 105.
NR 446.21(4)(f)4. 4. The mercury emissions shall be determined by use of the following equation: - See PDF for diagram PDF - See PDF for table PDF
NR 446.21(4)(f)5. 5. No changes in the operation of a plant may be made after a sludge test has been conducted which would potentially increase emissions above the level determined by the most recent sludge test, until the new emissions level has been estimated by calculation and the results reported to the department.
NR 446.21(4)(f)6. 6. All sludge samples shall be analyzed for mercury content within 30 days after the sludge sample is collected. Each determination shall be reported to the department by registered letter dispatched before the close of the next business day following the determination.
NR 446.21(4)(f)7. 7. Records of sludge sampling, charging rate determination and other data needed to determine mercury content of wastewater treatment plant sludges shall be retained at the source and made available for inspection by a department representative for a minimum of 2 years.
NR 446.21 History History: Renum. from NR 154.19 (3) (b), and am., Register, September, 1986, No. 369, eff. 10-1-86; am. (1) (b), (2) (b), (3) (c) and (4) (b), Register, May, 1992, No. 437, eff. 6-1-92; am. (1) (a), (2) (a), (3) (b) and (d) and (4) (a), (f) (intro.), 3. and 4., Register, May, 1994, No. 461, eff. 6-1-94; CR 01-081: renum. from NR 446.04 Register September 2004 No. 585, eff. 10-1-04; CR 07-036: renum. from NR 446.15, am. (3) (a) Register November 2008 No. 635, eff. 12-1-08.
NR 446.22 NR 446.22 Monitoring of emissions and operations.
NR 446.22(1)(1) All wastewater treatment plant sludge incineration and drying plants for which mercury emissions exceed 1.6 kg (3.5 lbs) per 24-hour period, demonstrated either by stack sampling or sludge sampling according to s. NR 446.21 (4), shall monitor mercury emissions at intervals of at least once per year in accordance with Method 105 and the procedures specified in s. NR 446.21 (4) (f). The results of monitoring shall be reported to the department by registered letter dispatched before the close of the next business day following the monitoring. The results shall be retained at the source and shall be made available for inspection by a department representative for a minimum of 2 years.
NR 446.22(2) (2) The owner or operator of each mercury cell chlor-alkali plant—hydrogen and end-box ventilation gas streams shall:
NR 446.22(2)(a) (a) Perform a mercury emission test that demonstrates compliance with the emission limits in s. NR 446.20 (1) on the hydrogen stream by Method 102 and on the end-box stream by Method 101 for the purpose of establishing limits for parameters to be monitored, within one year after June 1, 1994 or within one year of startup for a plant with initial startup after February 1, 1984.
NR 446.22(2)(b) (b) Monitor and record manually or automatically at least once every 15 minutes during the tests specified in par. (a) all of the following control device parameters, except as provided in par. (c):
NR 446.22(2)(b)1. 1. The exit gas temperature from uncontrolled streams.
NR 446.22(2)(b)2. 2. The outlet temperature of the gas stream for the final cooling system when no control devices other than coolers and demisters are used.
Loading...