This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 330.03(2) (2) The federal energy regulatory commission shall be notified of the time and date of the inspection for each of the dams regulated by that agency. Members of the public interested in the signing and portage requirements for specific dams shall be notified of the time and date of the inspection for such dams, if they have filed in writing with the department a request for such notification and the specific dam or dams in which they are interested.
NR 330.03(3) (3) After the inspections, the department shall issue an order with completion date to the owner of the dam specifying:
NR 330.03(3)(a) (a) Warning signs and devices required at the dam; and
NR 330.03(3)(b) (b) Portage requirements and signs at the dam.
NR 330.03(4) (4) As soon as practicable after the completion date set forth in the order, the department shall conduct a follow-up inspection to determine compliance with the order. If the order has been satisfied, the department shall confirm this fact in writing to the owner of the dam. Failure of the dam owner to comply with the order shall be grounds for an appropriate enforcement action.
NR 330.03(5) (5) Decisions made under this section and s. NR 330.06 may be reviewed pursuant to the provisions of ch. 227, Stats.
NR 330.03 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
NR 330.04 NR 330.04Devices and portage standards.
NR 330.04(1) (1) Standards for signs and devices required by these rules shall conform to the waterway marking system set forth in s. NR 5.09.
NR 330.04(1)(a) (a) Placement.
NR 330.04(1)(a)1.1. Signs or devices advising boaters of a dam. These signs and devices shall be legible a minimum of 300 feet upstream from the dam.
NR 330.04(1)(a)2. 2. Signs or devices shall be placed downstream of gated spillways and/or powerhouses to advise boaters of potentially dangerous, rapidly changing currents. Placement sites may be on the dam, powerhouse, shore or proximate boat landings. These signs and devices shall be legible a minimum of 300 feet downstream from the dam.
NR 330.04(1)(a)3. 3. The department may order the installation of suitable warning devices to be used at remote operated, gated spillways during the opening and closing of the gates.
NR 330.04(1)(a)4. 4. Portage information signs shall be placed at the portage takeout points and at such intervals as are necessary to provide adequate information to anyone portaging the dam.
NR 330.04(1)(b) (b) Portages.
NR 330.04(1)(b)1.1. A portage shall be a clear access route around a dam and its appurtenances, on which a boat and supplies can be carried without unreasonable obstruction, danger or difficulty. Portages shall be of the shortest reasonable distance considering topography, safety, location of buildings and obstructions and protection of dam embankments from erosion.
NR 330.04(1)(b)2. 2. A single portage around a series of closely spaced dams on a stream may be provided by the dam owner or owners, in lieu of individual portages, by the provisions of a conveyance around the series of dams. Information regarding this conveyance shall be provided at the takeout points at the upstream and downstream dams in the series.
NR 330.04 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
NR 330.05 NR 330.05Signs and devices specifications.
NR 330.05(1)(1)Uniform aids to navigation. Signs, markers and devices required under this chapter shall conform with s. NR 5.09.
NR 330.05(2) (2)Signs and proportions of signs, letters and numerals.
NR 330.05(2)(a)(a) Minimum sign size shall be 2 feet by 2 feet, outside dimensions.
NR 330.05(2)(b)1.1. Border width shall be 1/12 L; L = Length of sign side.
NR 330.05(2)(b)2. 2. Letter and numerals shall be: 3/10 L; L = Length of sign side.
NR 330.05 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
NR 330.06 NR 330.06Dams not inspected pursuant to s. NR 330.03.
NR 330.06(1)(1) Dams not inspected pursuant to s. NR 330.03 (1) may be inspected by the department and ordered to comply with the signing and portage requirements of this chapter upon its own motion, or upon written request of any interested member of the public.
NR 330.06 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
NR 330.07 NR 330.07Scenic and historic dams. The department may issue a variance from the provisions of this chapter for dams on designated wild and scenic waterways and dams that have been designated as historic landmarks by state or federal agencies.
NR 330.07 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
NR 330.08 NR 330.08Severability and construction. Should any section, paragraph, phrase, sentence, clause or word of this chapter be declared invalid or unconstitutional for any reason, the validity of the remainder of the chapter will not be affected thereby. Nothing in this chapter shall be construed as limiting any authority granted by law to the department to regulate dams. The exemption of any dam from the portage requirements of this chapter should not be construed as limiting the rights of the public around any exempted dam.
NR 330.08 History History: Cr. Register, November, 1979, No. 287, eff. 12-1-79.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.