NR 255.03 Monitoring and reporting requirements. Compliance with the maximum monthly average effluent limitations and pretreatment standards listed in the tables for each regulated process is required regardless of the number of samples analyzed and averaged. The maximum monthly average effluent limitations and pretreatment standards listed in the tables for each regulated process shall be the basis for monthly average discharge limits in direct discharge permits and for pretreatment standards.
NR 255.03 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.04
NR 255.04 Compliance date for PSES. The compliance date for pretreatment standards for existing sources is March 9, 1987.
NR 255.04 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.10
NR 255.10 Applicability; description of the cadmium subcategory. This subchapter applies to the discharge of pollutants to waters of the state and the introduction of pollutants into POTWs from manufacturing cadmium anode batteries.
NR 255.10 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.11
NR 255.11 Effluent limitations representing the degree of effluent reduction attainable by the application of the best practicable control technology currently available. NR 255.11(1)(1) Except as provided in
40 CFR 125.30 to
125.32, any existing source subject to this subchapter shall achieve the following effluent limitations representing the degree of effluent reduction attainable by the application of BPT:
-
See PDF for table
1 Within the range of 7.5 to 10.0 at all times.
NR 255.11(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 1 to 10.
NR 255.11 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87;
correction in (1) made under s. 13.92 (4) (b) 7., Stats., Register April 2013 No. 688. NR 255.12
NR 255.12 Effluent limitations representing the degree of effluent reduction attainable by the application of the best available technology economically achievable. NR 255.12(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 11 to 18.
NR 255.12 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87;
correction in (1) made under s. 13.92 (4) (b) 7., Stats., Register April 2013 No. 688. NR 255.13
NR 255.13 New source performance standards. NR 255.13(1)(1) The discharge of wastewater pollutants from any new source subject to this subchapter may not exceed the following standards:
-
See PDF for table
1 Within the range of 7.5 to 10.0 at all times.
NR 255.13(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 19 to 26.
NR 255.13 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.14
NR 255.14 Pretreatment standards for existing sources. NR 255.14(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 27 to 34.
NR 255.14 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87;
correction in (1) made under s. 13.92 (4) (b) 7., Stats., Register April 2013 No. 688.
NR 255.15
NR 255.15 Pretreatment standards for new sources. NR 255.15(2)
(2) There may be no discharge allowance for process waste-water pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 35 to 42.
NR 255.15 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.20
NR 255.20 Applicability; description of the calcium subcategory. This subchapter applies to the discharge of pollutants to waters of the state and the introduction of pollutants into POTWs from manufacturing calcium anode batteries.
NR 255.20 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.23
NR 255.23 New source performance standards. There may be no discharge allowance for process wastewater pollutants from any battery manufacturing new source subject to this subchapter.
NR 255.23 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.25
NR 255.25 Pretreatment standards for new sources. There may be no discharge allowance for process wastewater pollutants into a POTW from any battery manufacturing new source subject to this subchapter.
NR 255.25 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.30
NR 255.30 Applicability; description of the lead subcategory. This subchapter applies to the discharge of pollutants to waters of the state and the introduction of pollutants into POTWs from manufacturing lead anode batteries.
NR 255.30 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.31
NR 255.31 Effluent limitations representing the degree of effluent reduction attainable by the application of the best practicable control technology currently available. NR 255.31(1)(1) Except as provided in
40 CFR 125.30 to
125.32, any existing source subject to this subchapter shall achieve the following effluent limitations representing the degree of effluent reduction attainable by the application of BPT:
-
See PDF for table
1 Within the range of 7.5 to 10.0 at all times.
NR 255.31(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 43 to 53.
NR 255.31 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87;
correction in (1) made under s. 13.92 (4) (b) 7., Stats., Register April 2013 No. 688.
NR 255.32
NR 255.32 Effluent limitations representing the degree of effluent reduction attainable by the application of the best available technology economically achievable. NR 255.32(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 54 to 62.
NR 255.32 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87;
correction in (1) made under s. 13.92 (4) (b) 7., Stats., Register April 2013 No. 688.
NR 255.33
NR 255.33 New source performance standards. NR 255.33(1)(1) The discharge of wastewater pollutants from any new source subject to this subchapter may not exceed the following standards:
-
See PDF for table
1 Within the range of 7.5 to 10.0 at all times.
1 Within the range of 7.5 to 10.0 at all times.
NR 255.33(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 63 to 71.
NR 255.33 History
History: Cr.
Register, November, 1987, No. 383, eff. 12-1-87.
NR 255.34
NR 255.34 Pretreatment standards for existing sources. NR 255.34(2)
(2) There may be no discharge allowance for process wastewater pollutants from any battery manufacturing operation other than those battery manufacturing operations listed in tables 72 to 80.
NR 255.34(3)
(3) In cases where battery employe shower wastewater containing concentrations of lead exceeding 0.20 mg/l is combined with process wastewaters prior to treatment, the control authority may, under and notwithstanding the provisions of
s. NR 211.12, exercise its discretion and classify battery employe shower wastewater as an unregulated rather than a dilute (F
D) wastestream, for the purpose of applying the combined wastestream formula. Before the control authority may exercise its discretion to classify such a stream as an unregulated stream, the battery manufacturer must provide engineering, production, and sampling and analysis information sufficient to allow a determination by the control authority on how the stream should be classified.