NR 182.103(8)
(8) “
Baseline concentration" or “baseline water quality” means the concentration of a substance in groundwater or surface water as determined by monitoring at or near a proposed facility, practice, or activity before the facility has been constructed or the practice or activity has commenced.
NR 182.103(9)
(9) “
Closure" means those actions to be taken by the owner or operator of a mining waste site or facility to prepare the site for long-term care and to make it suitable for other uses.
NR 182.103(10)
(10) “Closure plan" means a written report and supplemental engineering plans detailing those actions that will be taken by the owner or operator to effect proper closure of a nonferrous mining waste facility.
NR 182.103(11)
(11) “Closing" means the time at which a nonferrous mining waste site or facility ceases to accept wastes, and includes those actions taken by the owner or operator of the facility to prepare the site for long-term care and make it suitable for other uses.
NR 182.103(12)
(12) “Completeness" means a determination by the department that the minimum submittal requirements as established by this chapter for a plan or report have been met.
NR 182.103(12m)
(12m) “Composite liner” or “composite capping system” means a liner or capping system consisting of 2 low permeability components installed in direct and uniform contact, with the upper component consisting of a geomembrane material and the lower component consisting of compacted low permeability soils or compacted fine-grained soils combined with a geosynthetic clay liner.
NR 182.103(13)
(13) “Construct" means to engage in construction and closure activities for a new or expanded mining waste facility including any of the following:
NR 182.103(13)(b)
(b) Preparation and construction of facility base grade, leachate collection systems, liner systems, and final cover systems.
NR 182.103(13)(d)
(d) Replacement, expansion, remodeling, alteration, or extension of existing structures.
NR 182.103(13)(e)
(e) Acquisition and installation of equipment associated with new, expanded, or remodeled structures.
NR 182.103(14)
(14) “Construction documentation report" means a written report submitted under the seal of a licensed professional engineer documenting that a nonferrous mining waste disposal site or facility has been constructed in substantial compliance with a department approved plan of operation and this chapter.
NR 182.103(15)
(15) “Department" means the department of natural resources.
NR 182.103(16)
(16) “Depth of useable groundwater” means the depth into the Precambrian bedrock, as determined by the department, below which the groundwater is not reasonably capable of being used or made suitable for human consumption and is not hydrologically connected to other sources of groundwater that are suitable for human consumption.
NR 182.103(17)
(17) “Design capacity" means the total volume in cubic yards of waste that can be placed in a waste site, including the volume of any daily or intermediate cover material utilized in the facility, but not including final cover or topsoil.
NR 182.103(19)
(19) “Disposal" means the discharge, deposit, injection, dumping, or placing of any mining or prospecting waste into or on any land or water so that the mining and prospecting waste or any constituent of the waste may enter the environment or be emitted into the air or discharged into any waters, including groundwaters.
NR 182.103(21)
(21) “Establish" means to bring a mining waste disposal site or facility into existence, in compliance with applicable approvals and rules of the department.
NR 182.103(22)
(22) “Expand an existing site or facility" means to dispose of nonferrous mining waste on land not previously licensed, to dispose of mining waste not in accordance with a department issued plan approval, if one exists, or to dispose of mining waste in a manner significantly different from past operations.
NR 182.103(23)
(23) “Facility" means any land or appurtenances to the land used for the storage or disposal of nonferrous mining wastes, but does not include land or appurtenances used in the production or transportation of mining wastes, such as the concentrator, haul roads, or tailings pipelines, that are permitted under ch.
NR 131 or
132.
NR 182.103(24)
(24) “Feasibility report" means a report for a specific nonferrous mining waste disposal site or facility that describes the facility, surrounding area, and proposed operation in terms of land use, topography, soils, geology, hydrology, groundwater, surface water, proposed waste quantities and characteristics, and preliminary site or facility design concepts.
NR 182.103(25)
(25) “Fill area" means the area of a facility proposed to receive or that is receiving direct placement of nonferrous mining waste.
NR 182.103(26)
(26) “Floodplain" means land that has been, prior to January 1, 2022, or may be after January 1, 2022, as determined by the department, covered by flood water during the regional flood as defined in ch.
NR 116 and includes the floodway and the flood fringe as defined in ch.
NR 116.
NR 182.103(27)
(27) “Freeboard" means the height of the crest of the dam above the adjacent liquid surface within the impoundment.
NR 182.103(27g)
(27g) “Geomembrane" means a highly impermeable membrane made from plastic or rubber-based material by polymerization.
NR 182.103(27r)
(27r) “Geosynthetic clay liner” or “GCL” means factory manufactured geosynthetic product consisting of a layer of bentonite contained between geotextiles that are attached by adhesion, stitch bonding or needlepunching or a layer of bentonite attached to a geomembrane by adhesion.
NR 182.103(28)
(28) “Groundwater" means any waters of the state, as defined in s.
281.01 (18), Stats., occurring in a saturated subsurface geological formation of rock or soil.
NR 182.103(29)
(29) “Groundwater quality" means the chemical, physical, biological, thermal, or radiological quality of groundwater at a site or within an underground aquifer.
NR 182.103(30)
(30) “Groundwater standard" means a preventive action limit, alternative concentration limit, or enforcement standard established in accordance with ch.
NR 140 and this chapter.
NR 182.103(31)
(31) “Inactive dam" means a dam and associated settling area that is no longer being used for disposal of wastewater or tailings, or both, and that has been reclaimed in an approved manner.
NR 182.103(33)
(33) “Leachate" means water or other liquid that has percolated through or contacted nonferrous mining waste materials.
NR 182.103(34)
(34) “Licensed professional engineer" means a professional engineer registered with or licensed by the Wisconsin department of safety and professional services.
NR 182.103(35)
(35) “Licensed professional geologist" means a professional geologist registered with or licensed by the Wisconsin department of safety and professional services.
NR 182.103(36)
(36) “Limits of filling" means the outermost limit at which waste from a facility has been disposed of or approved or proposed for disposal.
NR 182.103(39)
(39) “Mine" means an excavation at or below the earth's surface made to extract nonferrous metallic minerals.
NR 182.103(42)(a)(a) “Mining waste" or “nonferrous mining waste” means any refuse, sludge, or other discarded material, including solid, liquid, semi-solid, or contained gaseous material, resulting from nonferrous metallic mineral prospecting or mining, or from the cleaning, preparation or concentration of nonferrous metallic minerals during prospecting or mining operations.
NR 182.103(42)(b)
(b) “Mining waste” include tailings, waste rock, mine overburden, and waste treatment sludges.
NR 182.103(42)(c)
(c) “Mining waste” does not include topsoil and mine overburden not disposed of in a waste site, but placed in a facility permitted under ch.
NR 131 or
132, to be returned to the mine site or used in the reclamation process, and does not include merchantable by-products.
NR 182.103(42)(d)
(d) “Mining waste” does not include trees and other vegetation removed from the mining site during site preparation and facility construction.
NR 182.103(43)
(43) “Monitoring" means all procedures used to systematically inspect and collect data on the performance of a facility relating to leachate and gas production or the effect on the quality of the air, groundwater, surface water, unsaturated zone, or soils.
NR 182.103(44)
(44) “Non-mining solid waste” means solid waste generated as part of a nonferrous prospecting or mining operation that is not mining waste and includes materials such as discarded vegetation, tires, barrels, sanitary waste, and various other solid waste materials defined in ch.
NR 500, including construction and demolition waste, garbage, commercial solid waste and municipal solid waste.
NR 182.103(45)
(45) “Operator" means the person who is responsible for the overall operation of a nonferrous mining waste facility or for part of a nonferrous mining waste facility.
NR 182.103(46)
(46) “Ore" means a naturally occurring material from which nonferrous metallic minerals can be recovered at a profit.
NR 182.103(47)
(47) “Overburden" means any unconsolidated geologic material such as till, sand and gravel, or weathered bedrock that may be removed during mining.
NR 182.103(48)
(48) “Owner" means any person who owns a nonferrous mining waste facility or part of a nonferrous mining waste facility whether individually, jointly, or through subsidiaries, agents, employees, or contractors.
NR 182.103(49)
(49) “Person" means an individual, trust, firm, cooperative, institution, joint stock company, corporation, including a government corporation, partnership, association, state, municipality, commission, political subdivision of a state, interstate body, or federal or state department, agency, or instrumentality.
NR 182.103(50)
(50) “Plan of operation" means a report submitted for a nonferrous mining waste disposal site or facility that describes its location, design, construction, sanitation, operation, maintenance, closing, and long-term care.
NR 182.103(51)
(51) “Pollution" means the contaminating or rendering unclean or impure the air, land, or waters of the state, or making the same injurious to public health, harmful for commercial or recreational use, or deleterious to fish, bird, animal, or plant life.
NR 182.103(53)
(53) “Proof of financial responsibility" means a deposit or other financial instrument in compliance with ss.
289.41 and
293.51 (1g), Stats., ensuring that sufficient funds will be available to comply with the closure and long-term care requirements of this chapter and the approved plan of operation.
NR 182.103(55)
(55) “Reclamation plan" means the proposal for the reclamation of the nonferrous prospecting or mining site, including the closure of a mining waste disposal site or facility, that is approved by the department under s.
293.45 or
293.49, Stats., and ch.
NR 131 or
132 as part of the prospecting or mining permit.
NR 182.103(57)
(57) “Soil" means material that has been physically and chemically derived from the bedrock by nature.
NR 182.103(59)
(59) “Statistically significant change" means an amount of change determined by the use of valid statistical procedures for measuring significance at a level of 0.05.
NR 182.103(60)
(60) “Storage" means the temporary placement of nonferrous mining waste in such a manner as to not constitute ultimate disposal, in compliance with a mining permit or prospecting permit and plans approved under this chapter.
NR 182.103(61)
(61) “Tailings" means waste material resulting from the washing, concentration, chemical extraction or treatment of crushed ore.
NR 182.103(62)
(62) “Termination" means the final actions taken by an owner or operator of a nonferrous mining waste facility when formal responsibilities for long-term care cease.
NR 182.103(63)
(63) “Topsoil" means natural loam, sandy loam, silt loam, silt clay loam, or clay loam humus-bearing soils or other material that will easily produce and sustain dense growths of vegetation capable of preventing wind and water erosion of the material itself and other materials beneath.
NR 182.103(65)
(65) “Waste rock" means consolidated rock that has been removed during mining or prospecting but is not of sufficient value at the time of removal to constitute an ore.
NR 182.103(66)
(66) “
Waste site" or “waste sites and facilities" means any land or appurtenances used for the storage or disposal of nonferrous mining waste, but does not include land or appurtenances used in the production or transportation of nonferrous mining waste, such as the concentrator, haul roads, or tailings pipelines, which are permitted under ch.
NR 131 or
132.
NR 182.103(67)
(67) “Well" means any drillhole or other excavation or opening constructed for the purpose of obtaining or monitoring groundwater.
NR 182.103(68)
(68) “Well nest" means 2 or more wells installed within 10 feet of each other at the ground surface and constructed to varying depths.
NR 182.103(69)
(69) “Wetland" means an area where water is at, near, or above the land surface long enough to be capable of supporting aquatic or hydrophytic vegetation and that has soils indicative of wet conditions.
NR 182.103 History
History: CR 20-043: cr. Register December 2021 No. 792, eff. 1-1-22; correction in (15), (51) made under s. 35.17, Stats., Register December 2021 No. 792. NR 182.104
NR 182.104 General submittal requirements. Unless otherwise specified in this chapter, all submittals for review and approval of any feasibility report, plan of operation, construction documentation report, or closure plan shall include the following:
NR 182.104(1)
(1)
Paper and electronic copies. Unless otherwise specified, an applicant shall submit 5 paper copies and one electronic copy of the plan or report prepared pursuant to the appropriate section of this chapter, and an additional reproducible digital or electronic copy of any plan sheets or drawings submitted as a part of the plan or report. The paper copies and electronic copies shall be submitted to the department's waste and materials management program in Madison unless otherwise specified by the department. The complete electronic copy of the report and the separate digital or electronic copy of any plan sheets or drawings shall be provided in formats and on media acceptable to the department.
NR 182.104(2)
(2)
Cover letter. An applicant shall prepare a letter detailing the desired department action or response in reference to the submittal.
NR 182.104(3)(a)(a) An applicant shall prepare and submit the reports and plan sheets under the seal of a licensed professional engineer. In addition, the applicant shall include the following certification:
“I, __________________________, hereby certify that I am a licensed professional engineer in the State of Wisconsin in accordance with the requirements of ch.
A-E 4, Wis. Adm. Code; that this document has been prepared in accordance with the Rules of Professional Conduct in ch.
A-E 8, Wis. Adm. Code; and that, to the best of my knowledge, all information contained in this document is correct and the document was prepared in compliance with all applicable requirements ch.
NR 182, Wis. Adm. Code."
NR 182.104(3)(b)
(b) An applicant shall prepare feasibility reports, plans of operation, site investigation, and any other reports that require interpretation of geology or hydrogeology under the seal of a licensed professional geologist. In addition, an applicant shall include the following certification:
“I, __________________, hereby certify that I am a licensed professional geologist in the State of Wisconsin in accordance with the requirements of ch.
GHSS 2, Wis. Adm. Code; that the preparation of this document has not involved any unprofessional conduct as detailed in ch.
GHSS 5, Wis. Adm. Code; and that, to the best of my knowledge, all information contained in this document is correct and the document was prepared in compliance with all applicable requirements in ch.
NR 182, Wis. Adm. Code."
NR 182.104(4)
(4)
Technical procedures. An applicant shall use the current standard procedures as specified by ASTM International, USGS, U.S. environmental protection agency's standard methods for the examination of water and wastewater, or other equivalent or appropriate methods approved by the department to complete all technical procedures used to investigate a mining waste facility. An applicant shall specify the test procedures used in the report. An applicant shall explain in detail, with reasons provided, any deviation from a standard method used in the report.
NR 182.104(5)
(5)
Visuals. An applicant shall provide maps, figures, photographs and tables to clarify information or conclusions. The visuals shall be legible and submitted in reproducible printed form and electronic format, specified by the department. All paper copies of maps, plan sheets, drawings, isometrics, cross-sections and aerial photographs shall meet all of the following requirements:
NR 182.104(5)(a)
(a) Printed visual materials may not be larger than 32 inches by 44 inches and may not be smaller than 8 1/2 inches by 11 inches. Printed photographs may not be smaller than 4 inches by 6 inches. Engineering plans shall be drawn on standard 24 inch by 36-inch plan sheets, except that if facility details cannot be adequately depicted on standard plan sheets at a 1:100 scale, the engineering plans may be drawn on 30 inch by 42 inch plan sheets.
NR 182.104(5)(b)
(b) Be of appropriate scale to show all required details in sufficient clarity.
NR 182.104(5)(c)
(c) Be numbered, referenced in the narrative, titled, have a legend of all symbols used, contain horizontal and vertical scales, where applicable, and specify drafting or origination dates.