This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 135.19(4)(a) (a) A description of the proposed earthwork and reclamation, including final slope angles, high wall reduction, benching, terracing and other structural slope stabilization measures and if necessary a site-specific engineering analysis performed by a registered professional engineer as provided by s. NR 135.10 (1) and (2).
NR 135.19(4)(b) (b) The methods of topsoil or topsoil substitute material removal, storage, stabilization and conservation that will be used during reclamation.
NR 135.19(4)(c) (c) A plan or map which shows anticipated topography of the reclaimed site and any water impoundments or artificial lakes needed to support the anticipated future land use of the site.
NR 135.19(4)(d) (d) A plan or map which shows surface structures, roads and related facilities after the cessation of mining.
NR 135.19(4)(e) (e) The estimated cost of reclamation for each stage of the project or the entire site if reclamation staging is not planned.
NR 135.19(4)(f) (f) A revegetation plan which shall include timing and methods of seed bed preparation, rates and kinds of soil amendments, seed application timing, methods and rates, mulching, netting and any other techniques needed to accomplish soil and slope stabilization.
NR 135.19(4)(g) (g) Quantifiable standards for revegetation adequate to show that a sustainable stand of vegetation has been established which will support the approved post-mining land use. Standards for revegetation may be based on the percent vegetative cover, productivity, plant density, diversity or other applicable measures.
NR 135.19(4)(h) (h) A plan and, if necessary, a narrative showing erosion control measures to be employed during reclamation activities. These shall address how reclamation activities will be conducted to minimize erosion and pollution of surface and groundwater.
NR 135.19(4)(i) (i) A description of any areas which will be reclaimed on an interim basis sufficient to qualify for the waiver pursuant to s. NR 135.41 and which will be subsequently disturbed prior to final reclamation. Descriptions shall include an identification of the proposed areas involved, methods of reclamation to comply with the standards in subch. II and timing of interim and final reclamation.
NR 135.19(4)(j) (j) A description of how the reclamation plan addresses the long-term safety of the reclaimed mining site. The description shall include a discussion of site-specific safety measures to be implemented at the site and include measures that address public safety with regard to adjacent land uses.
NR 135.19 Note Note: Safety measures include visual warnings, physical barriers, slope modifications such as reclamation blasting, scaling of the rock face, creation of benches. Other measures may be employed if found to be equivalent by a registered professional engineer.
NR 135.19 Note Note: Some of the information required by this subsection may be combined; i.e., a single map may show anticipated post-mining topography required by par. (c) as well as structures and roads as required by par. (d).
NR 135.19(5) (5)Criteria for successful reclamation. The reclamation plan shall contain criteria for assuring successful reclamation in accordance with s. NR 135.13.
NR 135.19(6) (6)Certification of reclamation plan. The operator shall provide a signed certification that reclamation will be carried out in accordance with the reclamation plan. If the operator does not own the land, the landowner or lessor, if different from the operator or owner, shall also provide signed certification that they concur with the reclamation plan and will allow its implementation.
NR 135.19(7) (7)Approval. The regulatory authority shall approve, approve conditionally or deny the reclamation plan in writing in accordance with s. NR 135.21 (1) Conditional approvals shall be issued according to s. NR 135.21 (2), and denials of permit applications shall be made according to s. NR 135.22.
NR 135.19 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00; CR 06-024: am. (1), (2) (a), (e), (4) (a) and (7), cr. (4) (j), renum. (6) (a) to be (6) and am., r. (6) (b) Register November 2006 No. 611, eff. 12-1-06; correction in (3) (b) made under s. 13.92 (4) (b) 7., Stats., Register August 2011 No. 668.
NR 135.20 NR 135.20 Public notice and right of hearing.
NR 135.20(1)(1)Public notice.
NR 135.20(1)(a)(a) A regulatory authority that has received an application to issue a reclamation permit shall publish a public notice of the application no later than 30 days after receipt of a complete application or request.
NR 135.20(1)(b) (b) The notice shall briefly describe the mining and reclamation planned at the nonmetallic mining site. The notice shall be published as a class 1 notice pursuant to s. 985.07 (1), Stats., in the official newspaper of the regulatory authority, or if the department is the regulatory authority in the official newspaper of the county in which the nonmetallic mining site is located. The notice shall mention the opportunity for public hearing pursuant to this section and shall give the locations at which the public may review the application request and all supporting materials including the reclamation plan.
NR 135.20(1)(c) (c) Unless the department is the regulatory authority, copies of the notice shall be forwarded by the regulatory authority to the county or applicable municipal zoning board, the county and applicable local planning organization, the county land conservation officer, and owners of land within 300 feet of the boundaries of the parcel or parcels of land on which the site is located. If the department is the regulatory authority, copies of the notice shall be forwarded to all counties and municipalities in which the site is located.
NR 135.20(2) (2)Local hearing. A county or municipal regulatory authority shall provide for opportunity for a public informational hearing on an application or request to issue a nonmetallic mining reclamation permit as follows:
NR 135.20(2)(a) (a) If there is a zoning-related hearing on the nonmetallic mine site, the regulatory authority shall provide the opportunity at this hearing to present testimony on reclamation-related matters. This opportunity shall fulfill the requirement for public hearing for a nonmetallic mining reclamation permit required by this section. The regulatory authority shall consider the reclamation-related testimony in the zoning-related hearing in deciding on a permit application pursuant to this chapter.
NR 135.20(2)(b)1.1. If there is no opportunity for a zoning-related hearing on the nonmetallic mine site as described in par. (a), opportunity for public hearing required by this section shall be provided as follows. Any person residing within, owning property within, or whose principal place of business is within 300 feet of the boundary of the parcel or parcels of land in which the nonmetallic mining site is located or proposed may request a public informational hearing. The regulatory authority shall hold a public hearing if requested by any of these persons within 30 days of the actual date of public notice under sub. (1). This public informational hearing shall be held no sooner than 30 days nor later than 60 days after being requested. The hearing shall be conducted as an informational hearing for the purpose of explaining and receiving comment from affected persons on the nature, feasibility and effects of the proposed reclamation. Procedures for the public informational hearing shall be described in the applicable reclamation ordinance.
NR 135.20(2)(b)2. 2. The subject matter and testimony at this informational hearing, if it is held separately from any zoning-related hearing where the opportunity exists for testimony on reclamation pursuant to par. (a), shall be limited to reclamation of the nonmetallic mine site.
NR 135.20(3) (3)Hearing on reclamation permit applications to the department.
NR 135.20(3)(a)(a) Where the department is the regulatory authority, it shall provide an opportunity for public informational hearing on an application to issue a nonmetallic mining reclamation permit.
NR 135.20(3)(b) (b) Any person who resides within, owns property within or whose principal place of business is within 300 feet of the nonmetallic mining site may request a public informational hearing. The department shall hold a public hearing if requested by any of these persons within 30 days of the actual date of public notice under sub. (1), which shall be held no sooner than 30 days and no later than 60 days after being requested and shall be conducted as an informational hearing for the purpose of explaining and receiving comment from affected persons on the nature, feasibility, effects and other relevant aspects of the proposed nonmetallic mining and reclamation. The informational hearing shall be conducted using the procedures for a noncontested case hearing pursuant to ch. NR 2.
NR 135.20(3)(c) (c) The subject matter and testimony at this informational hearing shall be limited to reclamation of the nonmetallic mine site.
NR 135.20 Note Note: Informational hearings are limited to reclamation of the nonmetallic mining site. Regulatory authority staff conducting the hearings should make it clear that the hearings may not cover non-reclamation matters because they are beyond the scope of ch. NR 135 reclamation. Non-reclamation matters are those related to zoning or subject to other local authority. These matters may include but are not limited to: traffic, setbacks, blasting, dewatering, hours of operation, noise or dust control or the question of whether to use the land for mining.
NR 135.20 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00; CR 06-024: am. (1), (2) (intro.) and (3) (a), r. (4) Register November 2006 No. 611, eff. 12-1-06.
NR 135.21 NR 135.21 Reclamation permit issuance.
NR 135.21(1)(1)Permit issuance. Unless denied pursuant to s. NR 135.22, the regulatory authority shall approve in writing an application submitted pursuant to s. NR 135.18 (1) to issue a nonmetallic mining reclamation permit for a proposed nonmetallic mine. The regulatory authority may issue a reclamation permit subject to conditions in sub. (2) if appropriate. The permit decision shall be made no sooner than 30 nor later than 90 days following receipt of the complete reclamation permit application and reclamation plan that meets the requirements of s. NR 135.19 pursuant to this subchapter, unless a public hearing is held pursuant to s. NR 135.20. If a public hearing is held, the regulatory authority shall issue the reclamation permit, subject to conditions pursuant to sub. (2) if appropriate, or shall deny the permit as provided in s. NR 135.22, no later than 60 days after completing the public hearing.
NR 135.21(2) (2)Conditions. The regulatory authority may issue a reclamation permit or approve a reclamation plan subject to general or site-specific conditions if needed to assure compliance with the nonmetallic mining reclamation requirements of this chapter. The approvals may not include conditions that are not related to reclamation. One required condition of the issued permit shall be that the new mine obtain financial assurance pursuant to s. NR 135.40 prior to beginning mining.
NR 135.21 Note Note: It is not appropriate for the regulatory authority to impose conditions on a reclamation permit, or the approval of a reclamation plan that address matters not directly related to nonmetallic mining reclamation. These matters may include but are not limited to: traffic, setbacks, blasting, dewatering, hours of operation, noise or dust control or the question of whether to use the land for mining.
NR 135.21(3) (3)Cooperative issuance by multiple authorities. If more than one regulatory authority has jurisdiction over a single nonmetallic mining site, the regulatory authorities shall cooperatively issue a single reclamation permit for the nonmetallic mining site. Any unresolvable issues may be referred to the department under s. NR 135.52.
NR 135.21 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00; CR 06-024: r. (1), renum. (2) to (4) to be (1) to (3) and am. Register November 2006 No. 611, eff. 12-1-06.
NR 135.22 NR 135.22 Denial of application for reclamation permit.
NR 135.22(1)(1)An application to issue a nonmetallic mining reclamation permit shall be denied, within the time frame for permit issuance specified in s. NR 135.21, if the regulatory authority finds any of the following:
NR 135.22(1)(a) (a) The applicant has, after being given an opportunity to make corrections, failed to provide an adequate permit application, reclamation plan, financial assurance or any other submittal required by this chapter or the applicable reclamation ordinance to the regulatory authority.
NR 135.22(1)(b) (b) The proposed nonmetallic mining site cannot be reclaimed in compliance with the reclamation standards contained in the applicable reclamation ordinance, this chapter or subch. I of ch. 295, Stats.
NR 135.22(1)(c)1.1. The applicant, or its agent, principal or predecessor has, during the course of nonmetallic mining in Wisconsin within 10 years of the permit application or modification request being considered shown a pattern of serious violations of this chapter or of federal, state or local environmental laws related to nonmetallic mining reclamation.
NR 135.22(1)(c)2. 2. The following may be considered in making this determination of a pattern of serious violations:
NR 135.22(1)(c)2.a. a. Results of judicial or administrative proceedings involving the operator or its agent, principal or predecessor.
NR 135.22(1)(c)2.b. b. Suspensions or revocations of nonmetallic mining reclamation permits pursuant to this chapter.
NR 135.22(1)(c)2.c. c. Forfeitures of financial assurance.
NR 135.22(1)(d) (d) A denial under this subsection shall be in writing and shall contain documentation of reasons for denial.
NR 135.22(2) (2)A regulatory authority's decision to deny an application to issue a reclamation permit may be reviewed under s. NR 135.30.
NR 135.22 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00.
NR 135.23 NR 135.23 Automatic permitting and expedited permit review.
NR 135.23(1)(1)Automatic permitting of borrow sites for local transportation projects.
NR 135.23(1)(a) (a) The regulatory authority shall automatically issue an expedited permit under this subsection if the borrow site:
NR 135.23(1)(a)1. 1. Will be opened and reclaimed under contract with a municipality within a period not exceeding 36 months;
NR 135.23(1)(a)2. 2. Is a nonmetallic mine which is intended to provide stone, soil, sand or gravel for the construction, reconstruction, maintenance or repair of a highway, railroad, airport facility or other transportation facility under contract with a municipality;
NR 135.23(1)(a)3. 3. Is regulated and will be reclaimed under contract with a municipality in accordance with the requirements of the department of transportation concerning the restoration of nonmetallic mining sites;
NR 135.23(1)(a)4. 4. Is not a commercial source;
NR 135.23(1)(a)5. 5. Will be constructed, operated and reclaimed in accordance with applicable zoning requirements, if any, and;
NR 135.23(1)(a)6. 6. Is not otherwise exempt from the requirements of this chapter under s. NR 135.02 (3).
NR 135.23(1)(b) (b) The applicant shall notify the regulatory authority of the terms and conditions of the contract with respect to reclamation of the proposed borrow site.
NR 135.23(1)(c) (c) The applicant shall provide evidence to the regulatory authority to show that the borrow site and its reclamation will comply with applicable zoning requirements, if any.
NR 135.23(1)(d) (d) The regulatory authority shall accept the contractual provisions incorporating requirements of the department of transportation in lieu of a reclamation plan under s. NR 135.19.
NR 135.23(1)(e) (e) The regulatory authority shall accept the contractual provisions in lieu of the financial assurance requirements in s. NR 135.40.
NR 135.23(1)(f) (f) The public notice and hearing provisions of s. NR 135.20 do not apply to nonmetallic mining sites that are issued automatic permits under this subsection.
NR 135.23 Note Note: Local public notice and hearing requirements, if any, regarding zoning decisions still apply.
NR 135.23(1)(g) (g) The annual fees under s. NR 135.39 shall apply, however, the regulatory authority may not charge a plan review fee or an expedited plan review fee. Notwithstanding s. NR 135.39 (4) (b) and (c), the total annual fee including the department share shall not exceed the amount in Table 3 of s. NR 135.39.
NR 135.23(1)(h) (h) The regulatory authority shall issue the automatic permit within 7 days of the receipt of a complete application.
NR 135.23(1)(i) (i) If the borrow site is used to concurrently supply materials for other than the local transportation project, the automatic permitting in this subsection still applies provided the site will reclaimed under a contractual obligation with the municipality in accordance with the department of transportation requirements.
NR 135.23(1)(j) (j) Notwithstanding s. NR 135.36, the operator of a borrow site under this subsection is required to submit only the information in an annual report necessary to identify the borrow site and to determine the applicable annual fee.
NR 135.23(2) (2)Expedited permitting.
NR 135.23(2)(a) (a) An applicant may request expedited permit review by proceeding in accordance with par. (b) or (c).
NR 135.23(2)(b) (b) An applicant may submit a request for expedited review with payment of the fee required under s. NR 135.39 (4). This request shall state the need for expedited review and the date by which the expedited review is requested.
NR 135.23(2)(c) (c) An applicant may submit a request for an expedited review if the applicant requires a reclamation permit to perform services under contract with a municipality. This request for expedited review shall state the need for expedited review and shall include a copy of the applicable sections of the contract and the date by which the expedited review is requested.
NR 135.23(2)(d) (d) Following receipt of a request under this subsection, the regulatory authority shall inform the applicant of the estimated date for decision on issuance of the permit. If the applicant then elects not to proceed with the expedited review, the fee paid pursuant to par. (b) shall be returned.
NR 135.23(2)(e) (e) The expedited review process may not waive the requirements of this subchapter for public notice and hearing. This section does not impose an obligation upon the regulatory authority to act upon a permit application under this section by a specific date.
NR 135.23 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00.
NR 135.24 NR 135.24 Permit modification.
NR 135.24(1)(1)By the regulatory authority. If a regulatory authority finds that, because of changing conditions, the nonmetallic mining site no longer is in compliance with this chapter or the applicable reclamation ordinance, it shall issue an order modifying the permit in accordance with s. NR 135.43. This modifying order may require the operator to amend or submit new application information, reclamation plan, proof of financial assurance or other information needed to ensure compliance with this chapter or the applicable reclamation ordinance.
NR 135.24(2) (2)By the operator. If an operator desires to modify a nonmetallic mining reclamation permit or reclamation plan, the operator shall submit an application to modify the permit or plan to the regulatory authority. The application shall be subject to the requirements of this subchapter. The regulatory authority that issued the permit shall take action on the application to modify it in accordance with the standards and procedures contained in this subchapter.
NR 135.24(3) (3)Review. All actions by the regulatory authority pursuant to this section may be reviewed under s. NR 135.30.
NR 135.24 History History: Cr. Register, September, 2000, No. 537, eff. 12-1-00.
NR 135.25 NR 135.25 Permit suspension and revocation.
NR 135.25(1)(1)Grounds. A regulatory authority may suspend or revoke a nonmetallic mining permit issued pursuant to this chapter if it finds that the operator has done any of the following:
NR 135.25(1)(a) (a) Failed to submit a satisfactory reclamation plan within the time frames specified in this subchapter.
NR 135.25(1)(b) (b) Failed to submit or maintain financial assurance as required by this chapter.
NR 135.25(1)(c) (c) Failed on a repetitive and significant basis to follow the approved reclamation plan.
NR 135.25(2) (2)Suspension. If the regulatory authority makes any of the findings in sub. (1), it may suspend a nonmetallic mining reclamation permit for up to 30 days. During the time of suspension, the operator may not conduct nonmetallic mining at the site, except for reclamation or measures to protect human health and the environment as ordered by the regulatory authority pursuant to s. NR 135.43.
NR 135.25(3) (3)Revocation. If a regulatory authority makes any of the findings in sub. (1), it may revoke a nonmetallic mining reclamation permit. Upon permit revocation, the operator shall forfeit the financial assurance it has provided pursuant to s. NR 135.40 to the regulatory authority. The regulatory authority may use forfeited financial assurance to reclaim the site to the extent needed to comply with this chapter and the applicable reclamation ordinance.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.