This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 125.06(2) (2) The department shall notify the municipality of the preliminary determination of eligibility.
NR 125.06(3) (3) The department may not assign a priority rating under ss. NR 125.09 and 125.10 until after the complete grant application is received by the department.
NR 125.06 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; r. and recr. Register, April, 1989, No. 400, eff. 5-1-89.
NR 125.07 NR 125.07Grant applications. To be considered for a grant award, a municipality shall submit an application to the department. A municipality may submit an application only after the project is completed and paid for by the municipality. An application shall be completed on forms provided by the department and shall include the following, as applicable:
NR 125.07(1) (1)Authorizing resolution. A certified copy of a resolution of the municipality's governing body authorizing the filing of the grant application by municipality's authorized representative. The authorized representative shall be an official or employee of the municipality.
NR 125.07(2) (2)Project description. A description of the construction or list of the equipment for which grant funding is requested. The description shall include an explanation of why the project was needed.
NR 125.07(3) (3)State plan and specifications approval. A copy of the department letter approving plans and specifications for the project if plan approval is required under s. 281.41, Stats.
NR 125.07(4) (4)State facilities plan approval. For compliance maintenance planning projects, a copy of the department letter approving the facilities plan as required under ss. NR 110.08 and 110.09 and s. 281.41, Stats.
NR 125.07(5) (5)Bidding documents. For projects which require competitive bidding under ch. 59, 60, 61, 62 or 66, Stats.:
NR 125.07(5)(a) (a) A copy of the bid advertisement.
NR 125.07(5)(b) (b) A copy of the bid tabulation.
NR 125.07(5)(c) (c) A copy of the successful bid proposal.
NR 125.07(5)(d) (d) A copy of the resolution or meeting minutes of the municipality's governing body awarding the contract to the lowest responsible bidder or, if the contract was not awarded to the lowest responsible bidder, justification for disqualification of the lowest bid.
NR 125.07(6) (6)Construction contracts. A copy of any signed construction contracts and change orders relating to the project.
NR 125.07(7) (7)Municipal labor or material costs. For a project which includes labor or materials provided by the municipality:
NR 125.07(7)(a) (a) A listing of the labor costs including the employee's name, work performed, dates worked, hours worked each day and wages paid.
NR 125.07(7)(b) (b) A listing of any materials or equipment provided by the municipality including a description of the item, size of unit, number of units, where used or installed, date installed, date installed and cost per item.
NR 125.07(8) (8)Engineering and technical services. A copy of the signed engineering contract or other basis for engineering costs and technical services.
NR 125.07(9) (9)Proof of satisfactory completion.
NR 125.07(9)(a)(a) A statement signed by the municipal representative certifying that all claims, liens, disputes, etc., have been settled with contractors, engineers, property owners or other involved persons, or providing an explanation of any outstanding problems.
NR 125.07(9)(b) (b) A statement signed by the municipality and consulting engineer, as appropriate, certifying that the municipality has complied with all department conditions and that the project was completed in accordance with state approved plans and specifications.
NR 125.07(9)(c) (c) A description of any significant changes from the original approved plans and specifications.
NR 125.07(10) (10)Proof of payment.
NR 125.07(10)(a)(a) A statement signed by the municipal representative certifying that all costs in connection with the project have been paid.
NR 125.07(10)(b) (b) A listing of all payments to contractors and engineers when such payments are claimed as eligible costs. The list shall include the name of payee, date of payment, voucher number, and check number.
NR 125.07(10)(c) (c) A copy of invoices for all eligible costs.
NR 125.07(10)(d) (d) A copy of both sides of all canceled checks used for payment.
NR 125.07(11) (11)Operation and maintenance. A written statement from the department district or area engineer certifying that the operation, maintenance, testing and reporting of the municipal wastewater treatment plant meets all state and federal requirements pertaining to the project.
NR 125.07(12) (12)Other information. Other information as requested by the department to determine the eligibility of a project or to determine the eligible costs.
NR 125.07(13) (13)Compliance maintenance projects. Applications for compliance maintenance planning grants shall include documents required under subs. (1), (2), (4), (7), (8), (9) (a), (10) and (12).
NR 125.07 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; r. and recr. Register, April, 1989, No. 400, eff. 5-1-89; corrections in (3) and (4) made under s. 13.93 (2m) (b) 7., Stats., Register, May, 2001, No. 545.
NR 125.08 NR 125.08Departmental processing of applications.
NR 125.08(1)(1)Project number assignment. Upon receipt of an application, the department will assign a project number in chronological order of receipt. The project number will be used on all documents and correspondence relating to the project.
NR 125.08(2) (2)Initial review. The department will review the application and accompanying supporting documents in sufficient detail to assure completeness and whether the proposed project is eligible as pursuant to s. NR 125.03. Applications which are incomplete may be returned to the applicant for the appropriate information. Applicants having projects which are determined to be ineligible will be notified of such determination.
NR 125.08(3) (3)Obsolete applications. The application and supporting materials must be current and correct before the project can be placed on the priority list or before the state grant offer can be made. Generally information that is more than one year old is considered out of date and must be resubmitted or recertified as being up to date.
NR 125.08 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76.
NR 125.09 NR 125.09Priority designation.
NR 125.09(1) (1)Priority categories. After June 30, 1988 and before July 1, 1990 the department shall give priority for available funding as follows:
NR 125.09(1)(a) (a) The department shall give first priority to funding annual payments to municipalities required under s. 281.55 (8), Stats.
NR 125.09(1)(b) (b) The department shall give second priority to funding applications for compliance maintenance planning.
NR 125.09(1)(c) (c) The department shall give third priority to funding applications for small improvement projects.
NR 125.09(2) (2)Priority within categories. Priority within each category shall be determined by the point rating system under sub. (3). Projects shall be rated for priority for grants in descending order of the sum of the points. In the case of a tie in the point rating, the completed application received by the department at the earlier date shall be given the higher priority.
NR 125.09(3) (3)Point rating system. In ranking projects for priority for grants, financial capacity will be considered. A combined maximum of 30 points is assigned to these 3 measures of financial capacity and will be computed in accordance with the following table: - See PDF for table PDF
NR 125.09 Note * Based on the most recent Wisconsin department of revenue publications, “ Long Term Indebtedness of Wisconsin Political Subdivisions" and “Taxes, Aids and Shared Taxes" and confirmation of its applicability by department investigation.
NR 125.09 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; am. Register, November, 1976, No. 251, eff. 12-1-76; renum. (1) to be (3), cr. (1), am. (2), Register, April, 1989, No. 400, eff. 5-1-89; correction in (1) (a) made under s. 13.93 (2m) (b) 7., Stats., Register, May, 2001, No. 545.
NR 125.10 NR 125.10Priority list, closing date. The department shall determine the amount of money needed to fund complete applications received by the department prior to April 1 of each year.
NR 125.10(1) (1) If the amount of money available for grants is not sufficient to fully fund all applications, the department shall determine the priority rating of each application in accordance with s. NR 125.09. The department shall award grants for projects with the highest priority ratings until available funds are depleted.
NR 125.10(2) (2) If the amount of money available for grants is sufficient, a priority list will not be compiled. The department shall award grants for all eligible applications received prior to April 1. The department may award any surplus funds which would otherwise lapse at the end of the state fiscal year on a first-come, first-served basis for applications received on or after April 1.
NR 125.10(3) (3) Applications which are not funded in one fiscal year due to shortage of funds may be considered for funding in the following fiscal year.
NR 125.10 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; r. and recr. Register, April, 1989, No. 400, eff. 5-1-89.
NR 125.11 NR 125.11Grant awards.
NR 125.11(1) (1) A grant awarded under this chapter shall be made on forms prepared by the department. The award shall be signed by the authorized representative of the department and shall list the conditions to which the award is subject.
NR 125.11(2) (2) A grant may not be awarded for any project unless the project meets all department requirements and has priority for available funds under ss. NR 125.09 and 125.10.
NR 125.11(3) (3) A grant award may not exceed 25% of the eligible cost, or $15,000, whichever is less.
NR 125.11(4) (4) The authorized representative of the municipality shall accept the grant award by signing the award document and returning it to the department. The department may terminate a grant award if the award is not accepted within 45 days of the date of issuance by the department.
NR 125.11 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; am. (2), Register, October, 1976, No. 250, eff. 11-1-76; renum. (3) to be (4) and cr. (3), Register, November, 1976, No. 251, eff. 12-1-76; r. and recr. Register, April, 1989, No. 400, eff. 5-1-89.
NR 125.12 NR 125.12Payment procedure. Final payment will be made only after the project is fully functional and final inspection and audit and evidence of satisfactory operation and maintenance. The total state grant will be based on the final audited eligible costs.
NR 125.12 History History: Cr. Register, July, 1976, No. 247, eff. 8-1-76; r. (1), Register, April, 1989, No. 400, eff. 5-1-89.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.