This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
ATCP 93.410(9)(b) (b) Any of the following existing aboveground double-wall tanks storing Class IIIB products shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity:
ATCP 93.410(9)(b)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(9)(b)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(10)(a) (a) Any of the following double-wall aboveground tanks that are installed on or after November 1, 2019, shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity, and which automatically shuts off flow when the quantity of liquid in the tank reaches 95 percent of the tank's capacity, except this requirement does not apply to the tanks addressed in sub. (9) (a):
ATCP 93.410(10)(a)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(10)(a)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(10)(b) (b) Any of the following existing aboveground double-wall tanks shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity, and which automatically shuts off flow when the quantity of liquid in the tank reaches 95 percent of the tank's capacity, except this requirement does not apply to the tanks addressed in sub. (9) (b):
ATCP 93.410(10)(b)1. 1. Tanks using tight-connect delivery.
ATCP 93.410(10)(b)2. 2. Tanks located remote from the fill point that use delivery nozzles with latch-open devices.
ATCP 93.410(11) (11) Any single-wall aboveground tank which is not addressed in subch. III and which either is existing by November 1, 2019, or is installed on or after that date shall be provided with overfill prevention equipment which notifies the person filling the tank, with both an audible and a visual signal, that the liquid level has reached 90 percent of the tank's capacity.
ATCP 93.410(12) (12) Overfill prevention equipment shall be tested before it is placed into service to ensure it is set to activate at the levels specified in this section and that it will activate when the contained liquid reaches those levels. This testing shall be performed in accordance with one of the following:
ATCP 93.410(12)(a) (a) Requirements developed by the manufacturer, if the manufacturer has developed testing requirements.
ATCP 93.410(12)(b) (b) An approved standard developed by a nationally recognized association or independent testing laboratory.
ATCP 93.410(12)(c) (c) Requirements determined by the department to be no less protective of human health and the environment than the requirements listed in this subsection.
ATCP 93.410(13)(a) (a) Operators shall utilize the procedures and equipment as specified in PEI RP600 for preventing overfilling of new and existing shop-built aboveground tanks.
ATCP 93.410(13)(b) (b) Fuel-delivery persons shall utilize the procedures in PEI RP600 for preventing overfilling of new and existing shop-built aboveground tanks, and may not interfere with equipment that is intended to prevent overfilling.
ATCP 93.410 Note Note: PEI RP600 does not mandate installation of equipment, but instead addresses how to effectively use the equipment that is provided, as required by other sections and referenced standards in this chapter.
ATCP 93.410 Note Note: Under ss. ATCP 93.470 and ATCP 93.585 (2) (b), fuel-delivery persons must immediately inform the owner or operator of any spilling or overfilling which occurs during the delivery procedure and which may result in or be a release. Requirements for the owner or operator to report, investigate, and clean up any spills and overfills are contained in ss. ATCP 93.575 to 93.585.
ATCP 93.410 Note Note: Overfill-prevention requirements for bulk plant tanks are in PEI RP800, and corresponding requirements for hazardous liquid tanks containing substances that are not flammable or combustible are in s. ATCP 93.350.
ATCP 93.410 Note Note: API RP 1007, Loading and Unloading of MC 306/DOT 406 Cargo Tank Motor Vehicles, is a guideline for use by truck drivers and other personnel that includes specific steps for unloading tank trucks into aboveground and underground tanks in a safe and efficient manner which protects the environment. It is available at http://publications.api.org.
ATCP 93.410 History History: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19; correction in (6) (a) made under s. 35.17, Stats., and correction in (10) (a), (11) made under s. 13.92 (4) (b) 14., Stats., Register October 2019.
ATCP 93.420 ATCP 93.420Secondary containment.
ATCP 93.420(1)(1)Application. Aboveground storage tanks using secondary containment as a method of spill control shall comply with the secondary containment requirements in NFPA 30 section 22.11 and this section, except this requirement does not apply to any of the following tanks:
ATCP 93.420(1)(a) (a) Tanks covered in ss. ATCP 93.610 (1) to (3) and 93.630.
ATCP 93.420 Note Note: Sections ATCP 93.610 (1) to (3) and 93.630 cover tank wagons, movable tanks, tank vehicles, and aboveground farm tanks.
ATCP 93.420(1)(b) (b) Tanks storing Class IIIB liquids other than used oil.
ATCP 93.420 Note Note: Federal regulations, such as the Spill Prevention Control and Countermeasure requirements in 40 CFR part 112, may also apply to these tanks and be more restrictive but are not enforced by the department.
ATCP 93.420(1)(c) (c) Tanks storing Class IIIB liquids that are not in the same diked area as a tank containing Class I, II, or IIIA liquids.
ATCP 93.420(2) (2)Dike systems for tanks.
ATCP 93.420(2)(a) (a) Weather exposure. Where a dike system is used to provide secondary containment for a tank system that is exposed to the weather, the dike system shall be constructed in accordance with NFPA 30 section 22.11; ACI 350.2R, if concrete is used; and this subsection.
ATCP 93.420(2)(b) (b) Capacity. The capacity of a dike system open to the weather shall be 25 percent larger than required under NFPA 30 section 22.11.1.2 or 22.11.2.2.
ATCP 93.420(2)(c) (c) Construction. The walls and floor of the dike system shall be constructed of earth, solid masonry, steel, precast concrete, engineered poured concrete, or other materials approved by the department.
ATCP 93.420(2)(d) (d) Sealing. Dike systems with the walls and floor made of steel or poured or precast concrete shall have all cracks, seams, and joints sealed to be liquid-tight.
ATCP 93.420(2)(e) (e) New earthen or masonry dikes.
ATCP 93.420(2)(e)1.1. New dike systems that have walls or floor made of earth or masonry shall be lined with a synthetic material having a permeability of no faster than 10 -6 centimeters per second for the substance stored, except as provided in subd. 2.
ATCP 93.420(2)(e)2.a.a. Tanks included in either subd. 2. b. or c. may have dike systems designed by an engineer, with the walls and floor made of clay material having a permeability of no faster than 10-6 centimeters per second for the substance stored. The dike system shall be designed to maintain the permeability for a minimum of 35 years.
ATCP 93.420(2)(e)2.b. b. Tanks that have a double bottom which includes interstitial monitoring.
ATCP 93.420(2)(e)2.c. c. Single-bottom tanks that are constructed to ensure that any leaks from the bottom will drain to a conspicuous location and be contained there.
ATCP 93.420(2)(e)3. 3. All piping shall be routed over the top of the dike wall.
ATCP 93.420 Note Note: A method to achieve compliance with subd. 2. c. could include placing a tank over coarse aggregate that rests on a concrete base which is configured to provide the specified drainage and containment.
ATCP 93.420 Note Note: As applied under s. ATCP 93.440 (2) and (3), API 653 requires routine inspection of field-erected tanks, and STI SP001 requires periodic inspection of shop-built tanks for evidence of leaks.
ATCP 93.420(2)(f) (f) Existing earthen or masonry dikes.
ATCP 93.420(2)(f)1. 1. Tanks may be installed within an existing dike system that has walls or floor made of earth or masonry only if all of the following conditions are met:
ATCP 93.420(2)(f)1.a. a. The dike system complies with par. (b).
ATCP 93.420(2)(f)1.b. b. The new tanks comply with par. (e) 2. b. or c.
ATCP 93.420(2)(f)1.c. c. All other tanks within the dike system have overfill protection as specified in NFPA 30 section 21.7.1.
ATCP 93.420(2)(f)2. 2. An existing dike system that has walls or floor made of earth or masonry may be expanded with materials which are similar to the materials in the existing walls and floor. After that expansion, tanks may be installed within the dike system only if all of the conditions in subd. 1. a. to c. are met.
ATCP 93.420(2)(f)3. 3. Tanks within an existing dike system that has walls or floor made of earth or masonry may be converted from storing an unregulated substance to storing a regulated substance only if all of the following conditions are met:
ATCP 93.420(2)(f)3.a. a. The dike system complies with par. (b).
ATCP 93.420(2)(f)3.b. b. The converted tanks comply with par. (e) 2. b. or c.
ATCP 93.420(2)(f)3.c. c. All other tanks within the dike system have overfill protection as specified in NFPA 30 section 21.7.1.
ATCP 93.420(2)(f)4. 4. All new or replacement piping shall be routed over the top of the dike wall.
ATCP 93.420(2)(g) (g) Approval and installation of synthetic liners. Synthetic liners shall be approved in accordance with s. ATCP 93.130 and installed under the direct supervision of a qualified representative of the manufacturer
ATCP 93.420(2)(h) (h) Testing and maintenance. All new and existing synthetic liners and their seams shall be tested and maintained in accordance with the manufacturer's recommendations.
ATCP 93.420(2)(i) (i) Inspection of seams. Dike systems shall be constructed and maintained such that the liquid-tight seams can be visually inspected, except as provided in pars. (j) and (k).
ATCP 93.420(2)(j) (j) Seam exceptions. The following dike systems are not required to have seams that can be visually inspected:
ATCP 93.420(2)(j)1. 1. Concrete or steel systems that are coated with a liquid-proof sprayed coating.
ATCP 93.420(2)(j)2. 2. Systems using an additional synthetic liner.
ATCP 93.420(2)(j)3. 3. Systems using a synthetic liner that is covered with earthen material.
ATCP 93.420(2)(k) (k) Existing seams. For existing dike systems, the seams directly under the tank are not required to be visible for inspection.
ATCP 93.420(2)(L) (L) Separation. A separation of at least 2 feet shall be provided between any new tank and the toe of any new or existing dike wall, and a minimum of 3 inches shall be provided between the bottom of any new tank and the dike floor, to allow for visual inspection of the exterior tank surface — except this 3-inch requirement does not apply to tanks that comply with par. (e) 2. b. or c., or where otherwise approved by the department.
ATCP 93.420(2)(m) (m) Drainage. Permanent containment structures shall be designed with a manually controlled drainage system to permit the drainage of liquids resulting from leaks, spills, and precipitation, such as a manually controlled pump or siphon or a manually controlled dike valve.
ATCP 93.420(2)(n) (n) Dike maintenance. Dikes shall be maintained in accordance with API 2610 and s. ATCP 93.400 (8) (e).
ATCP 93.420(3) (3)Secondary containment tanks.
ATCP 93.420(3)(a) (a) The department may accept secondary containment tanks of any size as providing acceptable secondary containment, except where dike systems are specifically required by this chapter.
ATCP 93.420(3)(b) (b) Secondary containment tanks shall be provided with an approved method of interstitial leak detection.
ATCP 93.420(3)(c) (c) For electronic interstitial monitoring, the sensor shall be of a normally-closed type.
ATCP 93.420(3)(d) (d) Interstitial leak detection devices shall be tested for operability and functionality at installation.
ATCP 93.420(4) (4)Piping. All underground piping connected to an aboveground tank shall comply with the secondary containment requirements in s. ATCP 93.400 (3).
ATCP 93.420(5) (5)Transfer operations. In order to prevent a spill from moving beyond the loading or unloading area, any tank which has a capacity of 5,000 gallons or more and which is involved in transfer operations for bulk loading and unloading of tank cars or tank vehicles at facilities that refine, process, distribute, or manufacture liquids regulated under this code shall be provided with a catchment basin or treatment facility to contain the maximum capacity of the largest compartment of a tank car or tank vehicle loaded or unloaded at the facility.
ATCP 93.420 Note Note: This transfer requirement does not apply to transfers of used oil or fuel oil for heating or other burning purposes.
ATCP 93.420 Note Note: For further information on industry practices for preventing or detecting releases with aboveground storage systems, and for protecting groundwater, surface water and soil in the event of a liquid release, see API Publication 340 — Liquid Release Prevention and Detection Measures for Aboveground Storage Facilities.
ATCP 93.420 History History: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19.
ATCP 93.425 ATCP 93.425Tank lining of aboveground storage tanks.
ATCP 93.425(1)(1)The installation or repair of tank linings or coatings for aboveground storage tanks shall comply with API 652 and this section.
ATCP 93.425(2) (2) The interior lining or coating of aboveground storage tanks or the repair of such linings or coatings shall be supervised and conducted by persons as required by the material manufacturer.
ATCP 93.425(3) (3) Any openings cut for tank lining or similar purposes shall comply with API 653 for field-erected tanks and STI SP031 for shop-built tanks.
ATCP 93.425 History History: CR 17-092: cr. Register October 2019 No. 766, eff. 11-1-19.
ATCP 93.430 ATCP 93.430Vehicle collision protection.
ATCP 93.430(1)(1)Permanent vehicle collision protection shall be provided for any new or existing tank or system component that could result in a release of product when damaged, in any area where impact due to speed, turning, or backing of any type of motorized or self-propelled vehicle is likely to occur, except for tanks covered in ss. ATCP 93.610 (1) to (3) and 93.630.
ATCP 93.430 Note Note: Sections ATCP 93.610 (1) to (3) and 93.630 cover tank wagons, movable tanks, tank vehicles, and aboveground farm tanks.
ATCP 93.430 Note Note: Vehicle collision protection is required for tanks located outside or inside a building in motorized-vehicle or self-propelled-equipment traffic areas, where impact resulting from vehicle speed, turning or backing is a risk factor. For example, vehicle collision protection is required for tanks located adjacent to traffic areas that accommodate public and fleet fueling, service and delivery vehicles, self-propelled construction and service equipment, and forklift equipment.
ATCP 93.430 Note Vehicle collision protection is not required for tanks adjacent to vehicle and equipment service bays where traffic patterns and speed would not be expected to impact the tank system.
ATCP 93.430 Note Vehicle collision protection is generally not required at a terminal where roadways are clearly defined, access is restricted to authorized personnel, and vehicle drivers are familiar with the layout of the facilities.
ATCP 93.430(2) (2) At least 24 inches of clearance shall be provided between a vehicle impact barrier and the tank or system component to be protected.
ATCP 93.430(3) (3) Impact barriers shall be designed to protect the tank or component from impact damage by the force of the largest vehicle routinely in the traffic area traveling at 5 miles per hour or at the average traveling speed, if higher than 5 miles per hour, except as provided in sub. (4).
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.