This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
ATCP 93.100(1)(b) (b) Plan review and approval is not required for any of the following:
ATCP 93.100(1)(b)1. 1. Oil-burning installations for a 1- or 2-family dwelling which are located aboveground or in a basement, and which have a capacity of less than 1,100 gallons.
ATCP 93.100(1)(b)2. 2. Integral fuel supply tanks of a motor vehicle, aircraft, watercraft, mobile power plant or mobile heating plant.
ATCP 93.100(1)(b)3. 3. Aboveground tanks which have a capacity of less than 1,100 gallons and which store Class IIIB liquids other than used oil.
ATCP 93.100(1)(b)4. 4. Reconfiguration of product piping that is located aboveground, from storage tanks supplying a regulated substance to a manufacturing, industrial or blending process.
ATCP 93.100(1)(b)5. 5. Tank wagons, tank vehicles, or movable tanks that are used for vehicle fueling operations under subch. VI.
ATCP 93.100(1)(b)6. 6. Aboveground tank systems that store hazardous liquids which are not also flammable or combustible liquids, if the construction is supervised by a qualified engineer.
ATCP 93.100 Note Note: See s. ATCP 93.140 for registration requirements for tanks that store federally regulated hazardous substances. Section ATCP 93.350 requires aboveground hazardous substance tank systems to be designed by a qualified engineer.
ATCP 93.100(1)(b)7. 7. Portable tanks that are not used as fixed tanks.
ATCP 93.100(1)(b)8. 8. Tanks that are located at an EPA superfund site.
ATCP 93.100(1)(b)9. 9. Aboveground tanks which are used at a farm premises or construction project in accordance with s. ATCP 93.630, and which meet all of the following conditions:
ATCP 93.100(1)(b)9.a. a. Have a capacity of less than 1,100 gallons.
ATCP 93.100(1)(b)9.b. b. Are located at least 40 feet from either the buildings and structures listed in s. ATCP 93.630 (2) (a), or important buildings or structures.
ATCP 93.100 Note Note: See s. ATCP 93.630 (3) for administrative requirements for ASTs located at farms and construction projects.
ATCP 93.100(1)(b)10. 10. Fuel supply tanks which are used for a mobile power plant or mobile heating plant and which meet all of the following requirements:
ATCP 93.100(1)(b)10.a. a. The tank system is built and operated in accordance with a national standard.
ATCP 93.100(1)(b)10.b. b. The tank system is intended to be at the site for a period of 24 months or less.
ATCP 93.100(1)(b)10.c. c. The tank system has an aggregate capacity of less than 1,100 gallons.
ATCP 93.100(1)(b)10.d. d. The tank system does not use any Class I liquids.
ATCP 93.100(1)(b)11. 11. Where the department determines that the review of a specific application, modification or contractor activity would not meet the regulatory oversight objective for technical plan review and approval.
ATCP 93.100(1)(c) (c) Notwithstanding pars. (a) and (b), if the department determines that the review of a specific application, modification or special equipment meets the regulatory oversight objective of this chapter, a plan review and written approval from the authorized agent or the department shall be obtained.
ATCP 93.100(2) (2)Plans, specifications and information. Plans, specifications and information submitted to the authorized agent or the department for review and approval shall contain all of the following:
ATCP 93.100(2)(a) (a) Plans that are clear and legible and submitted per department requirements along with fees and a completed installation application.
ATCP 93.100(2)(b)1.1. The name of the owner.
ATCP 93.100(2)(b)2. 2. The name of the person, firm or corporation proposing the installation, if other than the owner.
ATCP 93.100(2)(b)3. 3. The address of the facility, including the names of adjacent streets and highways.
ATCP 93.100(2)(bm) (bm) A statement summarizing the scope of the project.
ATCP 93.100(2)(c)1.1. A plot plan, drawn to a minimum scale of one inch equals 20 feet, indicating the location of the installation with respect to property lines; adjoining streets or alleys; fences, including those installed over or through any part of the system; and other buildings on the same property. The plot plan shall indicate the location of buildings; other tanks; loading and unloading points; utilities; sanitary or storm sewers; water mains; water service piping; community and private potable water wells or other potable water source on the subject property; any private potable water wells on adjacent property that are within 100 feet of the tank, piping or dispenser; and any offsite community wells that are within 1,200 feet of the tank, piping or dispenser.
ATCP 93.100(2)(c)1m. 1m. For installations where cathodic protection will be installed, buried metal underground structures and components within 200 feet, such as culverts and guy wire anchor points, should be included in the plot plan.
ATCP 93.100 Note Note: See s. ATCP 93.260 for minimum separating distances between tank systems and potable water supply sources.
ATCP 93.100 Note Note: Chapter NR 116 requires municipalities to prohibit any storage of materials that are buoyant, flammable, explosive or injurious to animal, plant or aquatic life, in floodway areas of floodplains.
ATCP 93.100(2)(c)2. 2. The class of construction of each building or room in a building that contains a storage tank shall also be indicated.
ATCP 93.100(2)(d) (d) The location, size and capacity of each tank and the following information on the contents of the tank:
ATCP 93.100(2)(d)1. 1. The name of the stored liquid.
ATCP 93.100(2)(d)2. 2. The flammability or combustibility classification of the stored liquid.
ATCP 93.100 Note Note: Flammability and combustibility classifications are established in NFPA 30 sections 4.3.1 and 4.3.2, and are expressed as a Roman numeral and a letter, such as IB or IIIA.
ATCP 93.100(2)(d)3. 3. Whether the stored liquid is classified in any of the following hazard categories as defined in the applicable model fire code adopted by reference under ch. SPS 314:
ATCP 93.100(2)(d)3.a. a. Explosive or pyrophoric.
ATCP 93.100(2)(d)3.b. b. Oxidizer or organic peroxide.
ATCP 93.100(2)(d)3.c. c. Unstable or water reactive.
ATCP 93.100(2)(d)3.d. d. Toxic or highly toxic.
ATCP 93.100(2)(d)3.e. e. Cryogenic or corrosive to living tissue.
ATCP 93.100(2)(e) (e) The location of all piping runs and spacing between all tanks and piping.
ATCP 93.100(2)(f) (f) The type of tank supports and clearances, including clearances between tanks.
ATCP 93.100(2)(g) (g) The type of venting and pressure relief used and combined capacity of all venting and relief valves on each aboveground tank.
ATCP 93.100(2)(h) (h) The location of fill, gauge and vent pipes and other openings for the tank.
ATCP 93.100(2)(i) (i) The location of burners, tanks, pumps, piping and control valves and the relative elevations of any areas within the building where heavier-than-air vapors can accumulate.
ATCP 93.100(2)(j) (j) The distances to dispensers, sizes of islands and traffic flow patterns or vehicle routes around or through the facility.
ATCP 93.100(2)(k) (k) Information and specifications describing the design and placement of leak detection systems.
ATCP 93.100(2)(L)1.1. Information regarding the type and operation of corrosion protection systems for tanks and piping.
ATCP 93.100(2)(L)2. 2. For impressed current systems, the location and materials of gas mains and gas service lines serving the facility.
ATCP 93.100(2)(m) (m) Information regarding the type of secondary containment system.
ATCP 93.100(2)(n) (n) Specifications describing the spill and overfill protection devices.
ATCP 93.100(2)(o) (o) Information regarding the compatibility of the tank and piping system with the regulated substance.
ATCP 93.100(2)(p) (p) A copy of any easement that reflects any property not owned by the system operator on which any portion of the system is located or any vehicle is parked while transferring product.
ATCP 93.100(2)(q) (q) Any material-approval numbers issued under s. ATCP 93.130.
ATCP 93.100(2)(r) (r) Information and specifications, including manufacturer's model numbers on materials, equipment and devices to be used in the project which do not have material-approval numbers issued under s. ATCP 93.130 and which have a direct impact on the regulated system.
ATCP 93.100 Note Note: Examples of this equipment include valves, nozzles and hoses.
ATCP 93.100(2)(s) (s) Additional data and information regarding storage of regulated substances within buildings or enclosures to demonstrate compliance with the requirements of this chapter.
ATCP 93.100(2)(t) (t) Any other information necessary for the reviewer to determine code compliance.
ATCP 93.100(3) (3)Application and approval process.
ATCP 93.100(3)(a) (a) Submission of forms.
ATCP 93.100(3)(a)1.1. `General.' The department's installation application form, TR-WM-126, shall be completed and included with each application for approval, except as provided in subd. 5.
ATCP 93.100(3)(a)2. 2. `POS fueling.' For facilities that include dispenser point-of-sale fueling, the first page of the department's POS fueling installation form, TR-WM-130, shall also be completed and submitted.
ATCP 93.100(3)(a)3. 3. `Leak detection.' For facilities that include leak detection installation during the overall installation process, the first page of the department's leak detection installation form, TR-WM-133, shall also be completed and submitted.
ATCP 93.100(3)(a)4. 4. `Alternative fuel.'
ATCP 93.100(3)(a)4.a.a. For facilities that include fuel consisting of more than either 10 percent ethanol or 5 percent biodiesel by volume, as regulated under s. ATCP 93.680, Part I of the department's alternative fuel installation/conversion application form, TR-WM-132, shall be completed and submitted for approval. Part II shall serve as an addendum to the inspection checklist.
ATCP 93.100(3)(a)4.b. b. If the component or equipment manufacturer verifies the compatibility of the equipment, the verification shall be in writing, indicate an affirmative statement of compatibility, and specify the range of biofuel blends with which the component is compatible.
ATCP 93.100(3)(a)5. 5. `Exceptions.'
ATCP 93.100(3)(a)5.a.a. For aboveground storage tanks that have a capacity of less than 1,100 gallons, at a farm premises or construction project, the department's farm and construction AST installation notification form, TR-WM-124, shall be completed and submitted as notification to the authorized agent or the department at the time of installation inspection. This form shall also serve as the plan submittal application and the installation checklist.
ATCP 93.100(3)(a)5.b. b. Where conversion to point-of-sale fueling is the only change at a facility, the department's POS fueling installation form, TR-WM-130, shall be completed and submitted to the authorized agent or the department at least 10 days prior to conversion. This form shall also serve as the plan submittal application and the installation checklist.
ATCP 93.100(3)(a)5.c. c. Where an upgrade, exchange or conversion of installed leak detection methodology to another approved methodology or manufacturer is the only change at a facility, the department's leak detection installation form, TR-WM-133, shall be completed and submitted to the department within 5 days of installation. This form shall also serve as the plan submittal application and the installation checklist.
ATCP 93.100(3)(a)5.d. d. Where conversion to storage and dispensing of alternative motor fuels is the only change at a facility, Part I of the department's alternative fuel installation/conversion application form, TR-WM-132, shall be completed and submitted to the department prior to conversion. Part I shall serve as the plan submittal application and Part II as the installation checklist.
ATCP 93.100 Note Note: Forms TR-WM-124 — Farm and Construction Aboveground Storage Tank Installation Notification, TR-WM-126 —Flammable/Combustible/Hazardous Liquid Tanks Installation Application, TR-WM-130 — Point-of-Sale Fueling Installation Notification, TR-WM-132 — Storage Tank Alternative Fuel Installation/Conversion Application, and TR-WM-133 — Storage Tank Leak Detection Installation or Upgrade Application are available from the Bureau of Weights and Measures, PO Box 8911, Madison, WI 53708-8911, or at telephone (608) 224-4942, or from the Bureau's Web site at https://datcp.wi.gov/Pages/Programs_Services/PetroleumHazStorageTanks.aspx.
ATCP 93.100 Note Note: Within a 1st class city, the provisions in subdivision paragraphs c. and d. may be administered by that city instead of the department, as authorized in ss. ATCP 93.020 (8) (b) and 93.110 (3) and (4). As of November 1, 2019, only the City of Milwaukee is a 1st class city.
ATCP 93.100(3)(b) (b) Review time. The authorized agent or the department shall review and make a determination on an application for installation approval and plan review within 20 business days of receiving all of the required information and fees. If an applicant does not respond to a request by the department for additional information within 6 months after the date of the request, the department shall make a determination on the application based upon the information on hand.
ATCP 93.100 Note Note: Section ATCP 93.1605 addresses fees associated with ch. ATCP 93 plan submittal, review, and inspection.
ATCP 93.100 Note Note: Section ATCP 93.1605 authorizes double fees when construction is initiated without the required plan approval.
ATCP 93.100(3)(c) (c) Conditional approval.
ATCP 93.100(3)(c)1.1. If the authorized agent or the department determines that the plans and the application substantially conform to the provisions of this chapter, a conditional approval shall be granted in writing.
ATCP 93.100(3)(c)2. 2. All conditions stated in the conditional approval shall be met before or during construction or installation.
ATCP 93.100(3)(c)3. 3. A conditional approval issued by the authorized agent or the department is not an assumption of any responsibility for the design, construction or maintenance of the facility.
ATCP 93.100 Note Note: Various sections of this chapter address the responsibilities that contractors have, under s. 168.22 (1), Stats., in achieving compliance with the technical requirements of this chapter, after plans and specifications are approved. For example, s. ATCP 93.115 (2) (b) 2. a. has requirements about completing a pre-construction installation form, and meeting then with an inspector; s. ATCP 93.115 (2) (b) 3. has requirements about notifying an inspector before starting an installation; ss. ATCP 93.400 (5) (b) and 93.500 (6) (a) have requirements about installing aboveground and underground tank systems according to the manufacturer's instructions, the applicable national standards in s. ATCP 93.200, plans and specifications approved under s. ATCP 93.100 and this chapter; ss. ATCP 93.400 (5) (f) and 93.500 (6) (d) have requirements about completing a checklist during installation of aboveground and underground tanks or piping; and s. ATCP 93.500 (9) (a) 2. has requirements about documenting the performance of newly installed leak detection equipment. Contractors also have compliance responsibilities under various other sections, such as notifying an inspector about installing small tanks at farms and construction sites, in s. ATCP 93.630 (3) (c); notifying an inspector about converting a dispensing facility to a point-of-use dispenser, in s. ATCP 93.100 (1) (a) 7.; performing tank linings for underground tanks, in s. ATCP 93.530; applying for approval to convert an installed tank system to store alternative fuel, in s. ATCP 93.680; not allowing releases to occur, in s. ATCP 93.230 (a); stopping leaks and preventing migration of free product into the environment, in s. ATCP 93.585 (1); reporting releases to the department of natural resources, in s. ATCP 93.585 (2); and cleaning or removing tanks during closure, in ss. ATCP 93.315 (2) and 93.560 (2).
ATCP 93.100 Note Note: Section ATCP 93.115 (2) (b) 4. addresses the responsibility of the authorized agent or the department to inspect installation of shop-built tanks and to record the results on the installation checklist.
ATCP 93.100(3)(d) (d) Plan sets.
ATCP 93.100(3)(d)1.1. A letter shall be sent to the designer and the owner of record with a statement relating to the examination of the plans and specifications and citing the conditions of approval or denial.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.