SB3,1,4
1An Act to amend 66.0401 (1m) (intro.); to create 66.0401 (1r), 66.0401 (4) (h),
2196.49 (4m) and 196.491 (3) (d) 9. of the statutes; relating to: requiring local
3approval for certain wind and solar projects before Public Service Commission
4approval.
Analysis by the Legislative Reference Bureau
Current law prohibits a person from beginning construction of a large electric generating facility (LEGF) unless the Public Service Commission grants a certificate of public convenience and necessity (CPCN) for the proposed facility. An LEGF is defined as a facility with a nominal operating capacity of 100 megawatts or more. In addition, a public utility may not engage in certain construction, expansion, or other projects unless PSC grants a certificate of authority (CA) for the proposed project. The bill defines a solar project and wind project as an area of land on which, respectively, solar photovoltaic panels or devices used for collecting wind energy, along with any associated equipment and facilities, are installed in order to generate electricity and which altogether is designed for nominal operation at a capacity of 15 megawatts or more.
Under this bill, before PSC may approve a CA or a CPCN for the construction of a solar project or wind project, the person seeking the certificate must seek approval from each city, village, and town in which the solar project or wind project is to be located. The bill requires a city, village, or town to approve or disapprove a proposed solar project or wind project by adopting a resolution to that effect no later than 90 days after receiving a request for such approval. If the city, village, or town fails to act within that time period, the project is considered approved. The bill allows this deadline to be extended for certain reasons. Current law limits the authority of political subdivisions to regulate solar and wind energy systems, allowing political subdivisions to impose restrictions only if they meet certain conditions. The bill provides that those limitations do not apply to the approval or disapproval of a solar project or a wind project by a city, town, or village. Current law also imposes procedures for political subdivisions that receive applications for approval relating to wind energy systems. Those procedures do not apply to approval or disapproval of a wind project under the bill.
Under the bill, PSC may not issue a CPCN or CA for a solar project or wind project unless each city, village, and town in which the project is proposed to be located has adopted a resolution approving the project.
The people of the state of Wisconsin, represented in senate and assembly, do enact as follows:
SB3,1
1Section 1. 66.0401 (1m) (intro.) of the statutes is amended to read:
SB3,2,9266.0401 (1m) Authority to restrict systems limited. (intro.) No Except
3as provided in sub. (1r), no political subdivision may place any restriction, either
4directly or in effect, on the installation or use of a wind energy system that is more
5restrictive than the rules promulgated by the commission under s. 196.378 (4g) (b).
6No Except as provided in sub. (1r), no political subdivision may place any
7restriction, either directly or in effect, on the installation or use of a solar energy
8system, as defined in s. 13.48 (2) (h) 1. g., or a wind energy system, unless the
9restriction satisfies one of the following conditions:
SB3,210Section 2. 66.0401 (1r) of the statutes is created to read:
SB3,2,121166.0401 (1r) Authority to approve or reject certain wind or solar
12projects. (a) In this subsection:
SB3,2,13131. Municipality means a city, village, or town.
SB3,3,4
12. Solar project means an area of land on which solar photovoltaic panels or
2other devices used for collecting solar energy and any associated equipment and
3facilities are installed in order to generate electricity and which altogether is
4designed for nominal operation at a capacity of 15 megawatts or more.
SB3,3,853. Wind project means an area of land on which devices used for collecting
6wind energy and any associated equipment and facilities are installed in order to
7generate electricity and which altogether is designed for nominal operation at a
8capacity of 15 megawatts or more.
SB3,3,139(b) Before the commission may approve a certificate of authority under s.
10196.49 or a certificate of public convenience and necessity under s. 196.491 (3) to
11construct a solar project or wind project, the person seeking the certificate shall
12seek approval from each municipality in which the solar project or wind project is to
13be located.
SB3,3,1914(c) Notwithstanding sub. (4), a municipality shall, except as provided under
15par. (d), approve or disapprove a proposed solar project or wind project by adopting
16a resolution to that effect no later than 90 days after the person seeking approval
17submits the request for such approval. If a municipality fails to act within the 90
18days, or within any extended time period established under par. (d), the solar
19project or wind project is considered approved.
SB3,4,220(d) A municipality may extend the time period under par. (c) if, within that 90-
21day period, the municipality authorizes the extension in writing. A municipality
22may authorize any combination of the following extensions, except that the total

1amount of time for all extensions it authorizes under this paragraph may not exceed
290 days:
SB3,4,431. An extension of up to 45 days if the municipality needs additional
4information to determine whether to approve or deny the request for approval.
SB3,4,652. An extension of up to 90 days if the requester makes a material
6modification to the request for approval.
SB3,4,873. An extension of up to 90 days for other good cause specified in writing by
8the municipality.
SB3,4,119(e) The limitations of authority under s. 66.0401 (1m) do not apply to requests
10for approval of a solar project or wind project by a municipality under this
11subsection.
SB3,312Section 3. 66.0401 (4) (h) of the statutes is created to read:
SB3,4,141366.0401 (4) (h) This subsection does not apply to requests for approval of a
14wind project under sub. (1r).
SB3,415Section 4. 196.49 (4m) of the statutes is created to read:
SB3,4,2016196.49 (4m) The commission may not issue a certificate under sub. (1), (2), or
17(3) for the construction of a solar project, as defined in s. 66.0401 (1r) (a) 2., or a
18wind project, as defined in s. 66.0401 (1r) (a) 3., unless each city, village, and town
19in which the project is proposed to be located has adopted a resolution approving
20the project under s. 66.0401.
SB3,521Section 5. 196.491 (3) (d) 9. of the statutes is created to read:
SB3,5,222196.491 (3) (d) 9. For a facility that is a solar project, as defined in s. 66.0401
23(1r) (a) 2., or a wind project, as defined in s. 66.0401 (1r) (a) 3., each city, village, and

1town in which the project is proposed to be located has adopted a resolution
2approving the project under s. 66.0401.
SB3,5,33(end)