February 12, 2025 - Introduced by Senator LeMahieu, cosponsored by Representative Petersen. Referred to Committee on Utilities and Tourism.
SB28,1,6
1An Act to repeal 196.485 (1) (cr), 196.485 (1) (ef) and 196.485 (3g); to create
2196.485 (1) (cr), 196.485 (1) (ef) and 196.485 (3g) of the statutes; relating to:
3an incumbent transmission facility owners right to construct, own, and
4maintain certain transmission facilities and Public Service Commission
5procedures if the transmission facility is a regionally cost-shared transmission
6line.
Analysis by the Legislative Reference Bureau
This bill grants to an incumbent transmission facility owner the right to construct, own, and maintain a transmission facility that has been approved for construction in the Midcontinent Independent System Operators (MISO) transmission plan and that connects to transmission facilities owned by that incumbent transmission facility owner. Under the bill, an incumbent transmission facility owner includes a transmission company or transmission utility (a cooperative or public utility that owns a transmission facility and provides transmission service in this state), regardless of whether this state is its principal place of business or where it is organized or headquartered. Under current law, MISO is an organization that is subject to the jurisdiction of the Federal Energy Regulatory Commission and that coordinates and controls electric transmission in a region of the country that includes this state. The bill provides that the right to construct, own, and maintain a transmission facility that connects to transmission facilities owned by two or more incumbent transmission facility owners belongs individually and proportionally to each incumbent transmission facility owner, unless otherwise agreed upon in writing.
Under the bill, if under MISOs transmission plan a regionally cost-shared transmission line has been approved for construction and connection to facilities owned by an incumbent transmission facility owner, the incumbent transmission facility owner must give the Public Service Commission written notice regarding the owners intent to construct, own, and maintain the line no later than 90 days after approval of the transmission plan or 90 days after the date on which this bill becomes law, whichever is later. If the owner indicates that it does not intent to construct the line, the bill requires it to fully explain that decision in the notice to PSC. In that case, the bill allows PSC to determine whether the incumbent transmission facility owner or another entity must construct the line, taking into consideration issues such as cost, efficiency, and reliability. The bill defines regionally cost-shared transmission line to mean a high-voltage transmission line that is eligible for regional cost sharing and is not subject to a right of first refusal in accordance with the MISO tariff.
The bill requires an incumbent transmission facility owner with the right to construct a MISO-approved regionally cost-shared transmission line to include in any application for a certificate of public convenience and necessity an estimate of the cost of construction, along with documentation that the estimate is the result of competitively bid engineering, procurement, and construction contracts. The bill also requires such an incumbent transmission facility owner to provide to PSC until construction is complete quarterly reports that include updated estimates of the construction cost and an explanation of any changes from prior cost estimates.
The bill requires an incumbent transmission facility owner with the right to construct a MISO-approved regionally cost-shared transmission line to, as soon as practicable after the information is available, submit a report to PSC, the assembly speaker, the assembly minority leader, the senate majority leader, the senate minority leader, and the governor detailing the amount of the costs of the transmission line project that are being charged to energy consumers outside this state.
The bill sunsets the rights and responsibilities created under the bill after 10 years.
The people of the state of Wisconsin, represented in senate and assembly, do enact as follows:
SB28,1
1Section 1. 196.485 (1) (cr) of the statutes is created to read:
SB28,3,3
1196.485 (1) (cr) Incumbent transmission facility owner includes a
2transmission company or transmission utility, regardless of whether this state is its
3principal place of business or where it is organized or headquartered.
SB28,24Section 2. 196.485 (1) (cr) of the statutes, as created by 2025 Wisconsin Act
5.... (this act), is repealed.
SB28,36Section 3. 196.485 (1) (ef) of the statutes is created to read:
SB28,3,107196.485 (1) (ef) Regionally cost-shared transmission line means a high-
8voltage transmission line that is eligible, in whole or in part, for regional cost
9sharing and is not subject to a right of first refusal in accordance with the tariff of
10the Midwest independent system operator.
SB28,411Section 4. 196.485 (1) (ef) of the statutes, as created by 2025 Wisconsin Act
12.... (this act), is repealed.
SB28,513Section 5. 196.485 (3g) of the statutes is created to read:
SB28,3,2314196.485 (3g) Incumbent transmission facility owner rights. (a) Rights.
15Subject to the approval of the commission under s. 196.491 (3), an incumbent
16transmission facility owner has the right to construct, own, and maintain a
17transmission facility that has been approved for construction in the Midwest
18independent system operators transmission plan and that connects to
19transmission facilities owned by that incumbent transmission facility owner. The
20right to construct, own, and maintain a transmission facility that connects to
21transmission facilities owned by 2 or more incumbent transmission facility owners
22belongs individually and proportionally to each incumbent transmission facility
23owner, unless otherwise agreed upon in writing.
SB28,4,8
1(b) Commission procedure. 1. If, in the Midwest independent system
2operators transmission plan, a regionally cost-shared transmission line has been
3approved for construction and connection to facilities owned by an incumbent
4transmission facility owner, the incumbent transmission facility owner shall give
5written notice to the commission regarding the owners intent to construct, own,
6and maintain the regionally cost-shared transmission line no later than 90 days
7after approval of the transmission plan or 90 days after the effective date of this
8subdivision .... [LRB inserts date], whichever is later.
SB28,4,1592. If an incumbent transmission facility owner indicates in its notice to the
10commission under subd. 1. that it does not intend to construct the regionally cost-
11shared transmission line, it shall in the notice fully explain the basis for that
12decision. In that case, the commission may determine whether the incumbent
13transmission facility owner or another entity is required to construct the regionally
14cost-shared transmission line, taking into consideration issues such as cost,
15efficiency, reliability, and other factors identified in this chapter.
SB28,4,1916(c) Cost control, requirement of competition, and cost allocation. With respect
17to a regionally cost-shared transmission line approved by the Midwest independent
18system operator, an incumbent transmission facility owner with the right to
19construct the transmission line shall do all of the following:
SB28,4,23201. In any application filed pursuant to s. 196.491 (3), provide to the
21commission an estimate of the cost to construct the regionally cost-shared
22transmission line and documentation showing that this cost is the result of
23competitively bid engineering, procurement, and construction contracts.
SB28,5,5
12. Until construction of the regionally cost-shared transmission line is
2complete, provide to the commission a quarterly report that includes an updated
3estimate of the cost to construct the regionally cost-shared transmission line and an
4explanation of changes from prior cost estimates provided under this subdivision or
5subd. 1.
SB28,5,1063. As soon as practicable after the information is available, submit a report to
7the commission, the assembly speaker, the assembly minority leader, the senate
8majority leader, the senate minority leader, and the governor detailing the amount
9of the costs of the regionally cost-shared transmission line project that are being
10charged to energy consumers outside this state.
SB28,611Section 6. 196.485 (3g) of the statutes, as created by 2025 Wisconsin Act ....
12(this act), is repealed.
SB28,713Section 7. Effective dates. This act takes effect on the day after
14publication, except as follows:
SB28,5,1615(1) The repeal of ss. 196.485 (1) (cr) and (ef) and (3g) takes effect on the first
16day of the 10th year beginning after publication.
SB28,5,1717(end)