AB174,38,19163. An owner of a transmission facility for which a certificate is issued under s.
17196.491 (3) may not seek to recover in rates approved by the federal energy
18regulatory commission an amount of equity in the transmission facility that
19exceeds 50 percent of the project costs.
AB174,6520Section 65. 196.491 (1) (ar) of the statutes is created to read:
AB174,38,2321196.491 (1) (ar) Battery energy storage system means a device that
22occupies one acre or more and that captures energy produced at one time, stores
23that energy for future use, and later delivers that energy as electricity.
AB174,6624Section 66. 196.491 (1) (e) of the statutes is amended to read:
AB174,39,2
1196.491 (1) (e) Facility means a large electric generating facility or, a high-
2voltage transmission line, or a battery energy storage system.
AB174,673Section 67. 196.491 (1) (h) of the statutes is created to read:
AB174,39,54196.491 (1) (h) Large solar energy system has the meaning given in s.
566.0401 (1e) (bk).
AB174,686Section 68. 196.491 (1) (i) of the statutes is created to read:
AB174,39,87196.491 (1) (i) Large wind energy system has the meaning given in s.
866.0401 (1e) (bL).
AB174,699Section 69. 196.491 (3) (a) 1m. of the statutes is created to read:
AB174,39,1510196.491 (3) (a) 1m. A person who files an application under subd. 1. for a large
11wind energy system, large solar energy system, or battery energy storage system
12proposed to be located on prime farmland, as defined in s. 93.74 (1) (d), having a
13productivity index, as defined in s. 93.74 (1) (e), of 0.6 or greater shall include with
14the application proof that the applicant has entered into contracts for the purchase
15of agricultural conservation easements required under s. 93.74 (2) (a).
AB174,7016Section 70. 196.491 (3) (a) 4. of the statutes is created to read:
AB174,39,2017196.491 (3) (a) 4. At least 45 days before a person files an application under
18subd. 1. for a large wind energy system, large solar energy system, or battery
19energy storage system, the person shall provide written notice of the proposed
20project to all of the following:
AB174,39,2121a. Each property owner located within one mile of a proposed project
AB174,39,2222b. Each city, village, town, or county in which project facilities are proposed.
AB174,39,2423c. The American Indian tribal governing body for any land under that bodys
24jurisdiction that is within the project boundary.
AB174,71
1Section 71. 196.491 (3) (a) 5. of the statutes is created to read:
AB174,40,52196.491 (3) (a) 5. At least 45 days before a person files an application under
3subd. 1. for a large wind energy system, large solar energy system, or battery
4energy storage system, the person shall post notice of the proposed project by class
51 notice under ch. 985 in the official state newspaper.
AB174,726Section 72. 196.491 (3) (a) 6. of the statutes is created to read:
AB174,40,127196.491 (3) (a) 6. At least 45 days before a person files an application under
8subd. 1. for a large wind energy system, large solar energy system, or battery
9energy storage system, the person shall satisfy the requirement under s. 66.0401
10(10). This subdivision does not require a person to enter into a economic
11development agreement with a political subdivision under s. 66.0401 (10) to file an
12application under subd. 1.
AB174,7313Section 73. 196.491 (3) (d) 9. of the statutes is created to read:
AB174,40,1814196.491 (3) (d) 9. For a large wind energy system, large solar energy system,
15or battery energy storage system, the applicant has provided the commission with
16documentation that the applicant consulted about the project with the American
17Indian tribal governing body for any land under that bodys jurisdiction that is
18within the project boundary.
AB174,7419Section 74. 196.491 (3) (d) 10. of the statutes is created to read:
AB174,40,2320196.491 (3) (d) 10. For a large wind energy system, large solar energy system,
21or battery energy storage system, the applicant has provided the commission with
22a decommissioning and site restoration plan under s. 66.0401 (7) and a drainage
23plan under s. 66.0401 (11).
AB174,7524Section 75. 196.491 (3) (d) 11. of the statutes is created to read:
AB174,41,2
1196.491 (3) (d) 11. For a large wind energy system, large solar energy system,
2or battery energy storage system, all of the following apply:
AB174,41,63a. Including the acres occupied by the facility proposed by the applicant, the
4total amount of acres of land in the town in which the facility is located that are
5occupied by a large wind energy system, a large solar energy system, or a battery
6energy storage system is not more than 2,000 acres.
AB174,41,107b. Including the acres occupied by the facility proposed by the applicant, the
8total amount of acres of land in the county in which the facility is located that are
9occupied by a large wind energy system, a large solar energy system, or a battery
10energy storage system is not more than 5,000 acres.
AB174,7611Section 76. 238.15 (1) (g) of the statutes is amended to read:
AB174,41,1712238.15 (1) (g) It is not primarily engaged in real estate development,
13insurance, banking, lending, lobbying, political consulting, professional services
14provided by attorneys, accountants, business consultants, physicians, or health
15care consultants, wholesale or retail trade, leisure, hospitality, transportation, or
16construction, except construction of power production plants that derive energy
17from a renewable low-carbon-emission resource, as defined in s. 196.378 (1) (h).
AB174,7718Section 77. Initial applicability.
AB174,41,2119(1) Letting of transmission facility contracts by bidding. The
20treatment of s. 196.485 (3r) first applies to a contract entered into, modified, or
21renewed on the effective date of this subsection.
AB174,42,422(2) Applications for large wind, large solar, and battery energy
23systems. The treatment of ss. 66.0401 (1e) (a), (am), (bk), (bL), (bm), (bn), (bo), (br),
24(cm), and (cs), (4) (a), (5) (a) and (e), (7), (8), (9), (10), (11), and (12) and 196.491 (1)

1(ar), (e), (h), and (i) and (3) (a) 1m., 4., 5., and 6. and (d) 9., 10., and 11. first applies
2to an application for approval of a large wind energy system, large solar energy
3system, or battery energy storage system under s. 66.0401 or 196.491 (3) submitted
4on the effective date of this subsection.
AB174,42,85(3) Purchase of easements for large wind, large solar, and battery
6energy systems. The treatment of s. 93.74 first applies to a specified facility, as
7defined in s. 93.74 (1) (g), for which an application under s. 196.491 (3) is submitted
8on the effective date of this subsection.