AB174,38,19163. An owner of a transmission facility for which a certificate is issued under s. 17196.491 (3) may not seek to recover in rates approved by the federal energy 18regulatory commission an amount of equity in the transmission facility that 19exceeds 50 percent of the project costs. AB174,6520Section 65. 196.491 (1) (ar) of the statutes is created to read: AB174,38,2321196.491 (1) (ar) “Battery energy storage system” means a device that 22occupies one acre or more and that captures energy produced at one time, stores 23that energy for future use, and later delivers that energy as electricity. AB174,6624Section 66. 196.491 (1) (e) of the statutes is amended to read: AB174,39,2
1196.491 (1) (e) “Facility” means a large electric generating facility or, a high-2voltage transmission line, or a battery energy storage system. AB174,673Section 67. 196.491 (1) (h) of the statutes is created to read: AB174,39,54196.491 (1) (h) “Large solar energy system” has the meaning given in s. 566.0401 (1e) (bk). AB174,686Section 68. 196.491 (1) (i) of the statutes is created to read: AB174,39,87196.491 (1) (i) “Large wind energy system” has the meaning given in s. 866.0401 (1e) (bL). AB174,699Section 69. 196.491 (3) (a) 1m. of the statutes is created to read: AB174,39,1510196.491 (3) (a) 1m. A person who files an application under subd. 1. for a large 11wind energy system, large solar energy system, or battery energy storage system 12proposed to be located on prime farmland, as defined in s. 93.74 (1) (d), having a 13productivity index, as defined in s. 93.74 (1) (e), of 0.6 or greater shall include with 14the application proof that the applicant has entered into contracts for the purchase 15of agricultural conservation easements required under s. 93.74 (2) (a). AB174,7016Section 70. 196.491 (3) (a) 4. of the statutes is created to read: AB174,39,2017196.491 (3) (a) 4. At least 45 days before a person files an application under 18subd. 1. for a large wind energy system, large solar energy system, or battery 19energy storage system, the person shall provide written notice of the proposed 20project to all of the following: AB174,39,2121a. Each property owner located within one mile of a proposed project AB174,39,2222b. Each city, village, town, or county in which project facilities are proposed. AB174,39,2423c. The American Indian tribal governing body for any land under that body’s 24jurisdiction that is within the project boundary. AB174,71
1Section 71. 196.491 (3) (a) 5. of the statutes is created to read: AB174,40,52196.491 (3) (a) 5. At least 45 days before a person files an application under 3subd. 1. for a large wind energy system, large solar energy system, or battery 4energy storage system, the person shall post notice of the proposed project by class 51 notice under ch. 985 in the official state newspaper. AB174,726Section 72. 196.491 (3) (a) 6. of the statutes is created to read: AB174,40,127196.491 (3) (a) 6. At least 45 days before a person files an application under 8subd. 1. for a large wind energy system, large solar energy system, or battery 9energy storage system, the person shall satisfy the requirement under s. 66.0401 10(10). This subdivision does not require a person to enter into a economic 11development agreement with a political subdivision under s. 66.0401 (10) to file an 12application under subd. 1. AB174,7313Section 73. 196.491 (3) (d) 9. of the statutes is created to read: AB174,40,1814196.491 (3) (d) 9. For a large wind energy system, large solar energy system, 15or battery energy storage system, the applicant has provided the commission with 16documentation that the applicant consulted about the project with the American 17Indian tribal governing body for any land under that body’s jurisdiction that is 18within the project boundary. AB174,7419Section 74. 196.491 (3) (d) 10. of the statutes is created to read: AB174,40,2320196.491 (3) (d) 10. For a large wind energy system, large solar energy system, 21or battery energy storage system, the applicant has provided the commission with 22a decommissioning and site restoration plan under s. 66.0401 (7) and a drainage 23plan under s. 66.0401 (11). AB174,7524Section 75. 196.491 (3) (d) 11. of the statutes is created to read: AB174,41,2
1196.491 (3) (d) 11. For a large wind energy system, large solar energy system, 2or battery energy storage system, all of the following apply: AB174,41,63a. Including the acres occupied by the facility proposed by the applicant, the 4total amount of acres of land in the town in which the facility is located that are 5occupied by a large wind energy system, a large solar energy system, or a battery 6energy storage system is not more than 2,000 acres. AB174,41,107b. Including the acres occupied by the facility proposed by the applicant, the 8total amount of acres of land in the county in which the facility is located that are 9occupied by a large wind energy system, a large solar energy system, or a battery 10energy storage system is not more than 5,000 acres. AB174,7611Section 76. 238.15 (1) (g) of the statutes is amended to read: AB174,41,1712238.15 (1) (g) It is not primarily engaged in real estate development, 13insurance, banking, lending, lobbying, political consulting, professional services 14provided by attorneys, accountants, business consultants, physicians, or health 15care consultants, wholesale or retail trade, leisure, hospitality, transportation, or 16construction, except construction of power production plants that derive energy 17from a renewable low-carbon-emission resource, as defined in s. 196.378 (1) (h). AB174,7718Section 77. Initial applicability. AB174,41,2119(1) Letting of transmission facility contracts by bidding. The 20treatment of s. 196.485 (3r) first applies to a contract entered into, modified, or 21renewed on the effective date of this subsection. AB174,42,422(2) Applications for large wind, large solar, and battery energy 23systems. The treatment of ss. 66.0401 (1e) (a), (am), (bk), (bL), (bm), (bn), (bo), (br), 24(cm), and (cs), (4) (a), (5) (a) and (e), (7), (8), (9), (10), (11), and (12) and 196.491 (1)
1(ar), (e), (h), and (i) and (3) (a) 1m., 4., 5., and 6. and (d) 9., 10., and 11. first applies 2to an application for approval of a large wind energy system, large solar energy 3system, or battery energy storage system under s. 66.0401 or 196.491 (3) submitted 4on the effective date of this subsection. AB174,42,85(3) Purchase of easements for large wind, large solar, and battery 6energy systems. The treatment of s. 93.74 first applies to a specified facility, as 7defined in s. 93.74 (1) (g), for which an application under s. 196.491 (3) is submitted 8on the effective date of this subsection.