AB174,573Section 57. 196.378 (4r) of the statutes is amended to read:
AB174,32,114196.378 (4r) Reports. No later than July 1 of each even-numbered year, the
5commission shall submit a report to the governor and chief clerk of each house of
6the legislature for distribution to the legislature under s. 13.172 (2) that evaluates
7the impact of the requirements of this section on the rates and revenue
8requirements of electric providers and compares that impact with the impact that
9would have occurred if renewable low-carbon-emission energy practices of electric
10providers were subject to market forces in the absence of the requirements of this
11section.
AB174,5812Section 58. 196.378 (5) (intro.) of the statutes is amended to read:
AB174,32,2013196.378 (5) Penalty. (intro.) Any person who violates sub. (2) or any
14renewable low-carbon-emission energy supplier who provides an electric provider
15with a false or misleading certification regarding the sources or amounts of
16renewable low-carbon-emission energy supplied at wholesale to the electric
17provider shall forfeit not less than $5,000 nor more than $500,000. Forfeitures
18under this subsection shall be enforced by action on behalf of the state by the
19attorney general. A court imposing a forfeiture under this subsection shall consider
20all of the following in determining the amount of the forfeiture:
AB174,5921Section 59. 196.485 (1) (cr) of the statutes is created to read:
AB174,32,2422196.485 (1) (cr) Incumbent transmission facility owner includes a
23transmission company or transmission utility, regardless of whether this state is its
24principal place of business or where it is organized or headquartered.
AB174,60
1Section 60. 196.485 (1) (ef) of the statutes is created to read:
AB174,33,52196.485 (1) (ef) Regionally cost-shared transmission line means a high-
3voltage transmission line that is eligible, in whole or in part, for regional cost
4sharing and is not subject to a right of first refusal in accordance with the tariff of
5the Midwest independent system operator.
AB174,616Section 61. 196.485 (1) (hm) of the statutes is created to read:
AB174,33,87196.485 (1) (hm) Transmission facility contract means a contract for the
8design of, construction of, or furnishing of materials for a transmission facility.
AB174,629Section 62. 196.485 (3g) of the statutes is created to read:
AB174,33,1910196.485 (3g) Incumbent transmission facility owner rights. (a) Rights.
11Subject to the approval of the commission under s. 196.491 (3), an incumbent
12transmission facility owner has the right to construct, own, and maintain a
13transmission facility that has been approved for construction in the Midwest
14independent system operators transmission plan and that connects to
15transmission facilities owned by that incumbent transmission facility owner. The
16right to construct, own, and maintain a transmission facility that connects to
17transmission facilities owned by 2 or more incumbent transmission facility owners
18belongs individually and proportionally to each incumbent transmission facility
19owner, unless otherwise agreed upon in writing.
AB174,34,420(b) Commission procedure. 1. If, in the Midwest independent system
21operators transmission plan, a regionally cost-shared transmission line has been
22approved for construction and connection to facilities owned by an incumbent
23transmission facility owner, the incumbent transmission facility owner shall give

1written notice to the commission regarding the owners intent to construct, own,
2and maintain the regionally cost-shared transmission line no later than 90 days
3after approval of the transmission plan or 90 days after the effective date of this
4subdivision .... [LRB inserts date], whichever is later.
AB174,34,1152. If an incumbent transmission facility owner indicates in its notice to the
6commission under subd. 1. that it does not intend to construct the regionally cost-
7shared transmission line, it shall in the notice fully explain the basis for that
8decision. In that case, the commission may determine whether the incumbent
9transmission facility owner or another entity is required to construct the regionally
10cost-shared transmission line, taking into consideration issues such as cost,
11efficiency, reliability, and other factors identified in this chapter.
AB174,6312Section 63. 196.485 (3j) of the statutes is created to read:
AB174,34,2013196.485 (3j) Effect of certain actions. If the president of the United
14States issues a lawful executive order, the federal energy regulatory commission
15issues a lawful order or rule, or Congress enacts a valid statute and that executive
16order, order, rule, or statute has the effect of repealing or nullifying provisions of the
17Midwest independent system operators tariff that allow the owner of a
18transmission facility to allocate costs of the transmission facility over a region
19encompassing more than one state, then subs. (1) (cr) and (ef), (3g), and (3r) (a) 4.
20are void effective on the date of that executive order, order, rule, or statute.
AB174,6421Section 64. 196.485 (3r) of the statutes is created to read:
AB174,34,2322196.485 (3r) Cost control, competitive bidding requirements and
23oversight.
AB174,35,224(a) Cost control, requirement of competition, and cost allocation. With respect

1to a transmission facility for which an application is filed pursuant to s. 196.491 (3),
2the owner of the proposed transmission facility shall do all of the following:
AB174,35,631. In any application filed pursuant to s. 196.491 (3), provide to the
4commission an estimate of the cost to construct the transmission facility and
5documentation showing that this cost is the result of competitively bid transmission
6facility contracts pursuant to par. (b).
AB174,35,1072. Until construction of the transmission facility is complete, provide to the
8commission an annual report that includes an updated estimate of the cost to
9construct the transmission facility and an explanation of changes from prior cost
10estimates provided under this subdivision or subd. 1.
AB174,35,13113. No later than 30 days after the transmission facility is placed in service,
12provide evidence to the commission that transmission facility contracts performed
13in completing the transmission facility were awarded in compliance with par. (b).
AB174,35,20144. With respect to a regionally cost-shared transmission line under sub. (3g)
15constructed by an incumbent transmission facility owner, as soon as practicable
16after the information is available, submit a report to the commission, the assembly
17speaker, the assembly minority leader, the senate majority leader, the senate
18minority leader, and the governor detailing the amount of the costs of the regionally
19cost-shared transmission line project that are being charged to energy consumers
20outside this state.
AB174,36,221(b) Competitive bidding process requirement. 1. An owner of a proposed
22transmission facility for which a certificate of public convenience and necessity is
23required under s. 196.491 (3) shall let by contract a transmission facility contract if

1the estimated cost of performing the contract exceeds $1,000,000, and shall comply
2with all of the following:
AB174,36,33a. The bidding shall be on the basis of sealed competitive bids.
AB174,36,74b. If fewer than 3 bids from responsible bidders are initially received for the
5contract, the owner shall solicit additional bids for at least 30 additional days. If
6fewer than 3 bids from responsible bidders are received after the additional bidding
7period, the owner shall document that circumstance.
AB174,36,88c. The contract shall be awarded to the lowest responsible bidder.
AB174,36,1592. a. An owner of a proposed transmission facility entering into a
10transmission facility contract that is required to be competitively bid under subd. 1.
11may require a person, before the person submits a bid for a transmission facility
12contract, to submit a statement containing information relating to financial ability,
13equipment, experience in the work prescribed by the transmission facility contract,
14and ability to safely perform the work prescribed by the transmission facility
15contract.
AB174,36,1716b. A person shall submit a statement described in subd. 2. a. in the manner
17and form designated by the owner of the proposed transmission facility.
AB174,36,2318c. The contents of a statement described in subd. 2. a. shall be confidential
19and may not be disclosed except upon the written order of the person submitting the
20statement, for necessary use by the owner of the proposed transmission facility in
21qualifying the person, for necessary use by the legislative audit bureau in
22conducting an audit described in par. (c) 1., or in cases of actions against, or by, the
23person or owner of the proposed transmission facility.
AB174,37,224d. The owner of the proposed transmission facility shall evaluate a statement

1described in subd. 2. a. and shall find the maker of the statement either responsible
2or not responsible.
AB174,37,733. An owner of a proposed transmission facility may not separate a
4transmission facility contract into multiple transmission facility contracts to
5decrease the estimated costs of performing each of the transmission facility
6contracts below the threshold specified in subd. 1. to enter into the transmission
7facility contracts without complying with the requirements under subd. 1.
AB174,37,168(c) Audits. 1. The legislative audit bureau shall conduct an audit of 15
9percent of transmission facility contracts that are subject to the requirements
10under par. (b) and that are performed related to constructing each transmission
11facility for which a certificate is issued under s. 196.491 (3). In addition, the
12legislative audit bureau shall conduct an audit of a transmission facility contract
13that is subject to the requirements under par. (b) and for which the joint legislative
14audit committee requests an audit. Within 30 days after completion of an audit
15under this subdivision, the legislative audit bureau shall file with the commission a
16detailed report thereof, including specific instances of any violations of par. (b).
AB174,37,20172. Upon receipt of a report from the legislative audit bureau under subd. 1.,
18the commission shall open a docket to review the audit report, in which proceeding
19the commission shall hold a public hearing. The commission shall determine if the
20transmission facility owner violated any requirement under par. (b).
AB174,38,321(d) Rate of return on equity; recovery of debt. 1. If the commission determines
22under par. (c) 2. that an owner of a transmission facility for which the transmission
23rates are determined by the federal energy regulatory commission violated par. (b),
24the owner shall seek approval of a tariff that provides a rate of return on equity that

1is either half of the base return on equity guaranteed with respect to the
2transmission facility or equal to the transmission facility owners average cost of
3debt, whichever is higher.
AB174,38,1242. a. Except as provided in subd. 2. b., if the cost to construct a transmission
5facility for which the transmission rates are determined by the federal energy
6regulatory commission exceeds the estimated cost provided to the commission
7under par. (a) 1. or 2. for the transmission facility, the owner of the transmission
8facility shall seek approval of a tariff with respect to the transmission facility that
9provides a rate of return on equity, for the portion of the cost to construct the
10transmission facility that exceeds the estimated cost provided under par. (a) 1. or 2.,
11that is either half of the base return on equity or equal to the transmission facility
12owners average cost of debt, whichever is higher.
AB174,38,1513b. Costs that exceed the estimated cost for the facility provided to the
14commission under par. (a) 1. or 2. but that are prudently incurred or that are a
15result of force majeure may not be considered excess costs under subd. 2. a.
AB174,38,19163. An owner of a transmission facility for which a certificate is issued under s.
17196.491 (3) may not seek to recover in rates approved by the federal energy
18regulatory commission an amount of equity in the transmission facility that
19exceeds 50 percent of the project costs.
AB174,6520Section 65. 196.491 (1) (ar) of the statutes is created to read:
AB174,38,2321196.491 (1) (ar) Battery energy storage system means a device that
22occupies one acre or more and that captures energy produced at one time, stores
23that energy for future use, and later delivers that energy as electricity.
AB174,6624Section 66. 196.491 (1) (e) of the statutes is amended to read:
AB174,39,2
1196.491 (1) (e) Facility means a large electric generating facility or, a high-
2voltage transmission line, or a battery energy storage system.
AB174,673Section 67. 196.491 (1) (h) of the statutes is created to read:
AB174,39,54196.491 (1) (h) Large solar energy system has the meaning given in s.
566.0401 (1e) (bk).
AB174,686Section 68. 196.491 (1) (i) of the statutes is created to read:
AB174,39,87196.491 (1) (i) Large wind energy system has the meaning given in s.
866.0401 (1e) (bL).
AB174,699Section 69. 196.491 (3) (a) 1m. of the statutes is created to read:
AB174,39,1510196.491 (3) (a) 1m. A person who files an application under subd. 1. for a large
11wind energy system, large solar energy system, or battery energy storage system
12proposed to be located on prime farmland, as defined in s. 93.74 (1) (d), having a
13productivity index, as defined in s. 93.74 (1) (e), of 0.6 or greater shall include with
14the application proof that the applicant has entered into contracts for the purchase
15of agricultural conservation easements required under s. 93.74 (2) (a).
AB174,7016Section 70. 196.491 (3) (a) 4. of the statutes is created to read:
AB174,39,2017196.491 (3) (a) 4. At least 45 days before a person files an application under
18subd. 1. for a large wind energy system, large solar energy system, or battery
19energy storage system, the person shall provide written notice of the proposed
20project to all of the following:
AB174,39,2121a. Each property owner located within one mile of a proposed project
AB174,39,2222b. Each city, village, town, or county in which project facilities are proposed.
AB174,39,2423c. The American Indian tribal governing body for any land under that bodys
24jurisdiction that is within the project boundary.
AB174,71
1Section 71. 196.491 (3) (a) 5. of the statutes is created to read:
AB174,40,52196.491 (3) (a) 5. At least 45 days before a person files an application under
3subd. 1. for a large wind energy system, large solar energy system, or battery
4energy storage system, the person shall post notice of the proposed project by class
51 notice under ch. 985 in the official state newspaper.
AB174,726Section 72. 196.491 (3) (a) 6. of the statutes is created to read:
AB174,40,127196.491 (3) (a) 6. At least 45 days before a person files an application under
8subd. 1. for a large wind energy system, large solar energy system, or battery
9energy storage system, the person shall satisfy the requirement under s. 66.0401
10(10). This subdivision does not require a person to enter into a economic
11development agreement with a political subdivision under s. 66.0401 (10) to file an
12application under subd. 1.
AB174,7313Section 73. 196.491 (3) (d) 9. of the statutes is created to read:
AB174,40,1814196.491 (3) (d) 9. For a large wind energy system, large solar energy system,
15or battery energy storage system, the applicant has provided the commission with
16documentation that the applicant consulted about the project with the American
17Indian tribal governing body for any land under that bodys jurisdiction that is
18within the project boundary.
AB174,7419Section 74. 196.491 (3) (d) 10. of the statutes is created to read:
AB174,40,2320196.491 (3) (d) 10. For a large wind energy system, large solar energy system,
21or battery energy storage system, the applicant has provided the commission with
22a decommissioning and site restoration plan under s. 66.0401 (7) and a drainage
23plan under s. 66.0401 (11).
AB174,7524Section 75. 196.491 (3) (d) 11. of the statutes is created to read:
AB174,41,2
1196.491 (3) (d) 11. For a large wind energy system, large solar energy system,
2or battery energy storage system, all of the following apply:
AB174,41,63a. Including the acres occupied by the facility proposed by the applicant, the
4total amount of acres of land in the town in which the facility is located that are
5occupied by a large wind energy system, a large solar energy system, or a battery
6energy storage system is not more than 2,000 acres.
AB174,41,107b. Including the acres occupied by the facility proposed by the applicant, the
8total amount of acres of land in the county in which the facility is located that are
9occupied by a large wind energy system, a large solar energy system, or a battery
10energy storage system is not more than 5,000 acres.
AB174,7611Section 76. 238.15 (1) (g) of the statutes is amended to read:
AB174,41,1712238.15 (1) (g) It is not primarily engaged in real estate development,
13insurance, banking, lending, lobbying, political consulting, professional services
14provided by attorneys, accountants, business consultants, physicians, or health
15care consultants, wholesale or retail trade, leisure, hospitality, transportation, or
16construction, except construction of power production plants that derive energy
17from a renewable low-carbon-emission resource, as defined in s. 196.378 (1) (h).
AB174,7718Section 77. Initial applicability.
AB174,41,2119(1) Letting of transmission facility contracts by bidding. The
20treatment of s. 196.485 (3r) first applies to a contract entered into, modified, or
21renewed on the effective date of this subsection.
AB174,42,422(2) Applications for large wind, large solar, and battery energy
23systems. The treatment of ss. 66.0401 (1e) (a), (am), (bk), (bL), (bm), (bn), (bo), (br),
24(cm), and (cs), (4) (a), (5) (a) and (e), (7), (8), (9), (10), (11), and (12) and 196.491 (1)

1(ar), (e), (h), and (i) and (3) (a) 1m., 4., 5., and 6. and (d) 9., 10., and 11. first applies
2to an application for approval of a large wind energy system, large solar energy
3system, or battery energy storage system under s. 66.0401 or 196.491 (3) submitted
4on the effective date of this subsection.
AB174,42,85(3) Purchase of easements for large wind, large solar, and battery
6energy systems. The treatment of s. 93.74 first applies to a specified facility, as
7defined in s. 93.74 (1) (g), for which an application under s. 196.491 (3) is submitted
8on the effective date of this subsection.