2. To submit with the application a drainage plan, including plans to repair or replace any subsurface drainage affected during the construction or decommissioning of a large wind energy system, large solar energy system, or battery energy storage system.
3. To provide visual screening of a large solar energy system or battery energy storage system for certain nearby properties that have a residence within 250 feet of the system.
4. To make attempts to enter good neighbor agreements with owners of certain nearby properties.
5. To provide written notice, no later than 45 days before submitting a CPCN application, indicating interest in entering into an economic development agreement to each political subdivision in which the proposed facility would be located and take all commercially reasonable efforts to negotiate an economic development agreement with each political subdivision.
6. To provide written notice at least 45 days before submitting a CPCN application to each property owner located within one mile of a proposed facility, each political subdivision in which the proposed facility is proposed, and the American Indian tribal governing body for any land under that bodys jurisdiction that is within the project boundary.
7. To post notice of the proposed project at least 45 days before submitting a CPCN application by class 1 notice in the official state newspaper.
The bill requires PSC to create a pamphlet of not more than two pages, available on its website, that explains in plain language all provisions of the bill relating specifically to large wind energy systems, large solar energy systems, and battery energy storage systems, and requires PSC, if it receives a CPCN application for such a system, to distribute this pamphlet by mail or electronically to certain impacted property owners and to the political subdivision in which the project is proposed to be located.
Purchase of agricultural conservation easements required for large wind, solar, and battery systems
The bill also requires owners of large wind energy systems, large solar energy systems, and battery energy storage systems that are located on land that has a National Commodity Crop Productivity Index (NCCPI) of 0.6 or greater as identified by the Natural Resources Conservation Service of the U.S. Department of Agriculture (USDA) and that was prime farmland at the time that a CPCN was applied for for the system to purchase certain agricultural conservation easements before placing the system in service. Under the bill, prime farmland means land in use for an agricultural use or in use for a use that has agricultural value, including land that is part of a crop rotation or land enrolled in the USDA Conservation Reserve Program if the land is prime farmland, unique farmland, or additional farmland of statewide importance under the specifications of the USDA. An agricultural conservation easement prohibits the land subject to the easement from being developed for a use that would make the land unavailable or unsuitable for agricultural use.
Under the bill, an owner of a large wind energy system, large solar energy system, or battery energy storage system must purchase agricultural conservation easements on four acres of prime farmland for each acre of land on which the system is located that was prime farmland having an NCCPI of 0.8 or greater, and must purchase such easements on two acres of prime farmland for each acre of land on which the system is located that was prime farmland having an NCCPI of not less than 0.6 and not more than 0.8 or that was unique farmland or additional farmland of statewide importance. The bill requires an owner to make commercially reasonable efforts to purchase agricultural conservation easements on acres of prime farmland in the following order of priority: 1) acres adjacent to the system and owned by an owner-operator; 2) acres located in the same county as the system and owned by an owner-operator; 3) acres located in an adjacent county and owned by an owner-operator; 4) acres adjacent to the system; 5) acres located in the same county as the system; 6) acres located in an adjacent county; and 7) acres located in this state. Under the bill, an owner-operator is a person who owns land and who materially participates in a trade or business that engages in an agricultural use on that land. The purchase cost of an agricultural conservation easement required under the bill is $2,500 for each acre, and is paid to the landowner in equal payments made over five years.
Under the bill, an application to PSC for a CPCN for a proposed large wind energy system, large solar energy system, or battery energy storage system must include proof that the applicant has entered into contracts for the purchase of agricultural conservation easements required by the bill. The bill also requires the agricultural conservation easements to include a provision that authorizes the Department of Agriculture, Trade and Consumer Protection, on behalf of the state, to bring actions to enforce or defend the easements. The bill prohibits large wind energy systems, large solar energy systems, and battery energy storage systems from being separated into multiple systems to decrease the nominal capacity of each system below 100 megawatts to construct the systems without purchasing the agricultural conservation easements required by the bill.
Nuclear energy as a state policy priority
The bill establishes as state policy that nuclear energy is a high-priority option, second only to energy efficiency and conservation, to be considered in meeting the states energy demands, over noncombustible renewable energy resources and combustible renewable energy resources. Under current law, it is the goal of the state that, to the extent it is cost effective and technically feasible, all new installed capacity for electric generation be based on renewable energy resources. The bill adds nuclear energy to this focus, along with renewable energy. Current law also provides that, in designing all new and replacement energy projects, a state agency or local governmental unit must rely to the greatest extent feasible on energy efficiency improvements and renewable energy resources if those are cost effective, are technically feasible, and do not have unacceptable environmental impacts. The bill adds nuclear energy resources to this list of prioritized resources.
Current law requires the Department of Administration to establish renewable energy percentage goals for certain state agencies to meet in 2007 and 2011 and then to submit a report to the governor and the legislature each March 1 concerning the degree of attainment of those goals during the preceding year. Under the bill, beginning in 2026, those reports must include nuclear energy in the definition of renewable resource for the purpose of that report.
The bill expands current laws that govern state renewable resource goals and renewable resource credits to include as an eligible resource one that derives electricity from nuclear power. The bill changes the terminology in these laws to use the term low-carbon-emission instead of renewable.
Light-Mitigating technology systems
The bill imposes lighting requirements on certain wind energy systems and high-voltage transmission line towers. Under the bill, such structures placed in service on or after the effective date of the bill must have a light-mitigating technology system (LMTS) installed; an LMTS is triggered by aircraft detection or otherwise reduces the impact of lighting necessary to make tall structures conspicuous to aircraft to avoid collisions. The bill applies to wind energy systems and high-voltage transmission line towers that meet the criteria for which construction or alteration would be subject to Federal Aviation Administration notice requirements, including a structure that is more than 200 feet above ground level (utility structures).
Current law prohibits the erection of any building, structure, tower, or other object that exceeds specified heights without a permit issued by the Department of Transportation (height permit). The bill extends this height permit requirement to any utility structure. However, DOT may not issue a height permit for a utility structure unless the applicant has received FAA approval to install an LMTS on the utility structure and the height permit includes as a condition that the applicant install the LMTS no later than 24 months after issuance of the permit. Current DOT rules implementing height permits govern enforcement of height permit requirements and conditions, including penalties and possible revocation.
The bill requires that a person be approved by FAA to install an LMTS on a utility structure. The bill specifies that a person who is selected to install an LMTS on a utility structure as required under the bill must provide notice to DOT and to the city, village, or town in which the utility structure is located of the progress of the installation. If the installation is delayed beyond the 24-month installation requirement, the bill requires the installer to provide an update on the reasons for the delay and the current status of the installation to DOT and the city, village, or town at least every three months. The bill allows DOT to establish policies and procedures to set a uniform schedule for submitting these notices and updates.
Also, the bill requires the owner of a utility structure that is placed in service before the bills effective date and for which DOT has issued a height permit to submit a report to PSC no later than July 1, 2026, on the commercial feasibility of installing an LMTS on the utility structure.
For further information see the state fiscal estimate, which will be printed as an appendix to this bill.
The people of the state of Wisconsin, represented in senate and assembly, do enact as follows:
AB174,1
1Section 1. 1.12 (3) (b) of the statutes is amended to read:
AB174,3,621.12 (3) (b) Renewable and nuclear energy resources. It is the goal of the state
3that, to the extent that it is cost-effective and technically feasible, all new installed
4capacity for electric generation in the state be based on renewable energy resources,
5including hydroelectric, wood, wind, solar, refuse, agricultural and biomass energy
6resources, or nuclear energy.
AB174,27Section 2. 1.12 (4) (cm) of the statutes is renumbered 1.12 (4) (am).
AB174,38Section 3. 1.12 (5) (a) of the statutes is amended to read:
AB174,3,1491.12 (5) (a) In designing all new and replacement energy projects, a state
10agency or local governmental unit shall rely to the greatest extent feasible on
11energy efficiency improvements and renewable or nuclear energy resources, if the
12energy efficiency improvements and renewable or nuclear energy resources are
13cost-effective and technically feasible and do not have unacceptable environmental
14impacts.
AB174,415Section 4. 13.94 (1) (q) of the statutes is created to read:
AB174,4,21613.94 (1) (q) Conduct audits under s. 196.485 (3r) (c) 1. of 15 percent of
17transmission facility contracts related to each certificate issued under s. 196.491 (3)
18that are required to be competitively bid under s. 196.485 (3r) (b), and as the joint

1legislative audit committee directs, conduct audits of other transmission facility
2contracts that are required to be competitively bid under s. 196.485 (3r) (b).
AB174,53Section 5. 16.75 (12) (a) 4. of the statutes is amended to read:
AB174,4,7416.75 (12) (a) 4. Renewable Except as provided under par. (e), renewable
5resource has the meaning given in s. 196.378 (1) (h) 1., 1m., or 2. and includes a
6resource, as defined in s. 196.378 (1) (j), that derives electricity from hydroelectric
7power.
AB174,68Section 6. 16.75 (12) (e) of the statutes is renumbered 16.75 (12) (e) 2.
AB174,79Section 7. 16.75 (12) (e) 1. of the statutes is created to read:
AB174,4,111016.75 (12) (e) 1. Beginning in 2026, and only for purposes of the report under
11this paragraph, renewable resources also includes nuclear energy resources.
AB174,812Section 8. 66.0401 (1e) (a) of the statutes is renumbered 66.0401 (4) (ag) and
13amended to read:
AB174,4,161466.0401 (4) (ag) Application In this subsection, application for approval
15means an application for approval of a wind energy system under rules
16promulgated by the commission under s. 196.378 (4g) (c) 1.
AB174,917Section 9. 66.0401 (1e) (am), (bk), (bL), (bm), (bn), (bo), (br), (cm) and (cs) of
18the statutes are created to read:
AB174,4,201966.0401 (1e) (am) Battery energy storage system has the meaning given in
20s. 196.491 (1) (ar).
AB174,4,2221(bk) Large solar energy system means a solar energy system designed for
22nominal operation at a capacity of 100 megawatts or more.
AB174,4,2423(bL) Large wind energy system means a wind energy system designed for
24nominal operation at a capacity of 100 megawatts or more.
AB174,5,2
1(bm) Nonparticipating property means real property that is not a
2participating property.
AB174,5,43(bn) Nonparticipating residence means a residence located on
4nonparticipating property.
AB174,5,65(bo) Occupied community building means a school, church or similar place
6of worship, a daycare facility, or a public library.
AB174,5,87(br) Participating property means real property that is the subject of an
8agreement that does all of the following:
AB174,5,1191. Provides for the payment of monetary compensation to the landowner from
10an owner regardless of whether any part of a wind energy system is constructed on
11the property.
AB174,5,14122. Specifies in writing any waiver of a requirement or right under this section
13or rules promulgated thereunder and that the landowners acceptance of payment
14establishes the landowners property as a participating property.
AB174,5,2115(cm) Residence means a primary or secondary personal residence that is
16occupied on the date that an application for approval of a wind energy system or
17solar energy system is filed under this section or s. 196.491 (3), including a
18manufactured home as defined in s. 101.91 (2), a hospital, community-based
19residential facility, residential care apartment complex, or similar facility, or a
20nursing home. Residence includes a temporarily unoccupied primary or
21secondary personal residence. Residence does not include any of the following:
AB174,5,23221. A recreational vehicle, as defined in s. 340.01 (48r), notwithstanding the
23length of the vehicle.
AB174,5,24242. A camping trailer, as defined in s. 340.01 (6m).
AB174,6,1
13. A permanently abandoned personal residence.
AB174,6,32(cs) Solar energy system means a solar energy system as defined under s.
313.48 (2) (h) 1. g.
AB174,104Section 10. 66.0401 (1m) (intro.) of the statutes is amended to read:
AB174,6,11566.0401 (1m) Authority to restrict systems limited. (intro.) No political
6subdivision may place any restriction, either directly or in effect, on the installation
7or use of a wind energy system that is more restrictive than the rules promulgated
8by the commission under s. 196.378 (4g) (b). No political subdivision may place any
9restriction, either directly or in effect, on the installation or use of a solar energy
10system, as defined in s. 13.48 (2) (h) 1. g., or a wind energy system, unless the
11restriction satisfies one of the following conditions:
AB174,1112Section 11. 66.0401 (4) (a) of the statutes is renumbered 66.0401 (4) (am).
AB174,1213Section 12. 66.0401 (5) (a) and (e) of the statutes are amended to read:
AB174,6,181466.0401 (5) (a) A decision of a political subdivision to determine that an
15application is incomplete under sub. (4) (a) (am) 1., or to approve, disapprove, or
16impose a restriction upon a wind energy system, or an action of a political
17subdivision to enforce a restriction on a wind energy system, may be appealed only
18as provided in this subsection.
AB174,6,2319(e) In conducting a review under par. (d), the commission may treat a political
20subdivisions determination that an application under sub. (4) (a) (am) 1. is
21incomplete as a decision to disapprove the application if the commission determines
22that a political subdivision has unreasonably withheld its determination that an
23application is complete.
AB174,1324Section 13. 66.0401 (7) to (12) of the statutes are created to read:
AB174,7,5
166.0401 (7) Decommissioning of large wind, large solar, and battery
2energy systems. A person who submits an application for approval of a large wind
3energy system, large solar energy system, or battery energy storage system under
4this section or s. 196.491 (3) shall submit with the application a decommissioning
5and site restoration plan that includes all of the following:
AB174,7,196(a) A plan to clear, clean, and remove the foundations of the large wind energy
7system, solar energy system, or battery energy storage system from the ground to a
8depth of at least 3 feet below the surface grade of the land in which the foundations
9are installed on the site within 18 months from the date the large wind energy
10system, large solar energy system, or battery energy storage system ceases
11operations, unless otherwise agreed to by the property owner. The date the large
12wind energy system, large solar energy system, or battery energy storage system
13ceases operation is the date on which the system is no longer capable of generating
14or storing electricity in commercial quantities, except when such inability to
15generate or store electricity is the result of an event of force majeure or when the
16grantee is in the process of repairing the wind energy system, solar energy system,
17or battery energy storage system, provided that, in either case, the large wind
18energy system, large solar energy system, or battery energy storage system
19resumes generating or storing electricity in commercial quantities within 180 days.
AB174,7,2120(b) A plan to restore the land to a reasonably similar condition as prior to the
21commencement of construction.
AB174,8,522(c) A financial assurance obligation in an amount equal to the estimated cost
23of decommissioning the large wind energy system, large solar energy system, or
24battery energy storage system less the salvage value of the components, as

1calculated by a 3rd-party licensed engineer. This amount shall be provided in a
2surety bond, irrevocable line of credit, parent company guarantee, or similar
3instrument and shall be posted by the 15th anniversary of the start of operations of
4the large wind energy system, large solar energy system, or battery energy storage
5system.
AB174,8,156(8) Visual screening. At the request of the owner of nonparticipating
7property and prior to the start of operations, a person who has received a certificate
8of public convenience and necessity under s. 196.491 (3) for a large solar energy
9system or battery energy storage system and the participating property owner
10shall, at their joint expense, provide visual screening for nonparticipating
11residences within 250 feet of the above-ground components of the large solar energy
12system or battery energy storage system, with a maximum cost of $1,500 per
13property line. The visual screening may be erected by the large solar energy system
14owner or battery energy storage system owner, as applicable, or provided as a one-
15time payment-in-lieu directly to the nonparticipating property owner.
AB174,8,2316(9) Good neighbor agreements. (a) Within 120 days of submitting an
17application for any approval of a large wind energy system, large solar energy
18system, or battery energy storage system under this section or s. 196.491 (3), the
19person proposing the large wind energy system, large solar energy system, or
20battery energy storage system or that persons representative shall make no less
21than three attempts to meet with nonparticipating property owners to disclose and
22discuss the project and enter into any contractual agreements, unless advised by
23the contacted property owner to cease contact attempts.
AB174,9,2
1(b) An attempt under par. (a) may be made in-person, electronically, or via
2certified mail.
AB174,9,73(c) A person proposing a large wind energy system, large solar energy system,
4or battery energy storage system shall make commercially reasonable attempts to
5reach agreements with nonparticipating property owners, and nonparticipating
6property owners shall accept or deny any such contractual agreements no later than
745 days after receiving an offer.
AB174,9,118(d) Payments made pursuant to a contractual agreement under par. (c) shall
9be contingent upon the person proposing the project receiving all required
10approvals for construction of the large wind energy system, large solar energy
11system, or battery energy storage system.
AB174,9,1912(10) Economic development agreements. (a) No later than 45 days before
13a person submits an application for approval of a large wind energy system, large
14solar energy system, or battery energy storage system under s. 196.491 (3), if
15required, the person shall submit a written notice indicating the person's interest
16in entering into an economic development agreement to each political subdivision
17in which the proposed facility would be located and shall take all commercially
18reasonable efforts to negotiate an economic development agreement with each
19political subdivision.
AB174,9,2120(b) An economic development agreement under this subsection may include
21any of the following:
AB174,9,22221. Setbacks and screening from occupied community buildings.
AB174,9,23232. Road use agreements.
AB174,9,24243. Decommissioning.
AB174,10,1
14. Drainage infrastructure.
AB174,10,225. First responder services and communication.
AB174,10,336. Planning and coordination of construction activities.
AB174,10,54(c) Failure to reach an agreement may not be used as justification for denial of
5any approval under this section or s.196.491 (3).
AB174,10,106(11) Drainage plan. A person who seeks approval of a large wind energy
7system, large solar energy system, or battery energy storage system under this
8section or s. 196.491 (3) shall submit with its application a drainage plan, which
9shall include plans to repair or replace any subsurface drainage affected during the
10construction or decommissioning of the system.
AB174,10,1511(12) Information for property owners and political subdivisions. (a)
12The public service commission shall create a pamphlet of not more than 2 pages,
13available on its website, that explains in plain language all provisions under this
14section and s. 196.491 (3) that relate specifically to large wind energy systems, large
15solar energy systems, and battery energy storage systems.
AB174,10,2116(b) If the commission receives an application for a certificate of public
17convenience and necessity under s. 196.491 (3) for a large wind energy system, large
18solar energy system, or battery energy storage system, the commission shall
19distribute the pamphlet under par. (a) by mail or electronically to any owner of
20property on which or adjacent to which the project is proposed to be located and any
21political subdivision in which the project is proposed to be located.
AB174,1422Section 14. 66.0627 (1) (bk) 2. of the statutes is amended to read:
AB174,11,22366.0627 (1) (bk) 2. An improvement to a premises that allows for the small

1scale derivation of electricity from a renewable low-carbon-emission resource listed
2under s. 196.378 (1) (h).
AB174,153Section 15. 93.74 of the statutes is created to read:
AB174,11,5493.74 Purchase of agricultural conservation easements required for
5large wind, large solar, and battery systems. (1) Definitions. In this section:
AB174,11,86(a) Agricultural conservation easement means a conservation easement, as
7defined in s. 700.40 (1) (a), the purpose of which is to assure the availability of land
8for agricultural use.
AB174,11,119(b) Agricultural use has the meaning given in s. 93.73 (1m) (b), except that
10agricultural use does not include use of land on which any of the following is
11located:
AB174,11,12121. A wind energy system, as defined in s. 66.0403 (1) (m).
AB174,11,13132. A solar energy system, as defined in s. 13.48 (2) (h) 1. g.