AB174,6,181466.0401 (5) (a) A decision of a political subdivision to determine that an 15application is incomplete under sub. (4) (a) (am) 1., or to approve, disapprove, or 16impose a restriction upon a wind energy system, or an action of a political 17subdivision to enforce a restriction on a wind energy system, may be appealed only 18as provided in this subsection. AB174,6,2319(e) In conducting a review under par. (d), the commission may treat a political 20subdivision’s determination that an application under sub. (4) (a) (am) 1. is 21incomplete as a decision to disapprove the application if the commission determines 22that a political subdivision has unreasonably withheld its determination that an 23application is complete. AB174,1324Section 13. 66.0401 (7) to (12) of the statutes are created to read: AB174,7,5
166.0401 (7) Decommissioning of large wind, large solar, and battery 2energy systems. A person who submits an application for approval of a large wind 3energy system, large solar energy system, or battery energy storage system under 4this section or s. 196.491 (3) shall submit with the application a decommissioning 5and site restoration plan that includes all of the following: AB174,7,196(a) A plan to clear, clean, and remove the foundations of the large wind energy 7system, solar energy system, or battery energy storage system from the ground to a 8depth of at least 3 feet below the surface grade of the land in which the foundations 9are installed on the site within 18 months from the date the large wind energy 10system, large solar energy system, or battery energy storage system ceases 11operations, unless otherwise agreed to by the property owner. The date the large 12wind energy system, large solar energy system, or battery energy storage system 13ceases operation is the date on which the system is no longer capable of generating 14or storing electricity in commercial quantities, except when such inability to 15generate or store electricity is the result of an event of force majeure or when the 16grantee is in the process of repairing the wind energy system, solar energy system, 17or battery energy storage system, provided that, in either case, the large wind 18energy system, large solar energy system, or battery energy storage system 19resumes generating or storing electricity in commercial quantities within 180 days. AB174,7,2120(b) A plan to restore the land to a reasonably similar condition as prior to the 21commencement of construction. AB174,8,522(c) A financial assurance obligation in an amount equal to the estimated cost 23of decommissioning the large wind energy system, large solar energy system, or 24battery energy storage system less the salvage value of the components, as
1calculated by a 3rd-party licensed engineer. This amount shall be provided in a 2surety bond, irrevocable line of credit, parent company guarantee, or similar 3instrument and shall be posted by the 15th anniversary of the start of operations of 4the large wind energy system, large solar energy system, or battery energy storage 5system. AB174,8,156(8) Visual screening. At the request of the owner of nonparticipating 7property and prior to the start of operations, a person who has received a certificate 8of public convenience and necessity under s. 196.491 (3) for a large solar energy 9system or battery energy storage system and the participating property owner 10shall, at their joint expense, provide visual screening for nonparticipating 11residences within 250 feet of the above-ground components of the large solar energy 12system or battery energy storage system, with a maximum cost of $1,500 per 13property line. The visual screening may be erected by the large solar energy system 14owner or battery energy storage system owner, as applicable, or provided as a one-15time payment-in-lieu directly to the nonparticipating property owner. AB174,8,2316(9) Good neighbor agreements. (a) Within 120 days of submitting an 17application for any approval of a large wind energy system, large solar energy 18system, or battery energy storage system under this section or s. 196.491 (3), the 19person proposing the large wind energy system, large solar energy system, or 20battery energy storage system or that person’s representative shall make no less 21than three attempts to meet with nonparticipating property owners to disclose and 22discuss the project and enter into any contractual agreements, unless advised by 23the contacted property owner to cease contact attempts. AB174,9,2
1(b) An attempt under par. (a) may be made in-person, electronically, or via 2certified mail. AB174,9,73(c) A person proposing a large wind energy system, large solar energy system, 4or battery energy storage system shall make commercially reasonable attempts to 5reach agreements with nonparticipating property owners, and nonparticipating 6property owners shall accept or deny any such contractual agreements no later than 745 days after receiving an offer. AB174,9,118(d) Payments made pursuant to a contractual agreement under par. (c) shall 9be contingent upon the person proposing the project receiving all required 10approvals for construction of the large wind energy system, large solar energy 11system, or battery energy storage system. AB174,9,1912(10) Economic development agreements. (a) No later than 45 days before 13a person submits an application for approval of a large wind energy system, large 14solar energy system, or battery energy storage system under s. 196.491 (3), if 15required, the person shall submit a written notice indicating the person's interest 16in entering into an economic development agreement to each political subdivision 17in which the proposed facility would be located and shall take all commercially 18reasonable efforts to negotiate an economic development agreement with each 19political subdivision. AB174,9,2120(b) An economic development agreement under this subsection may include 21any of the following: AB174,9,22221. Setbacks and screening from occupied community buildings. AB174,9,23232. Road use agreements. AB174,9,24243. Decommissioning. AB174,10,1
14. Drainage infrastructure. AB174,10,225. First responder services and communication. AB174,10,336. Planning and coordination of construction activities. AB174,10,54(c) Failure to reach an agreement may not be used as justification for denial of 5any approval under this section or s.196.491 (3). AB174,10,106(11) Drainage plan. A person who seeks approval of a large wind energy 7system, large solar energy system, or battery energy storage system under this 8section or s. 196.491 (3) shall submit with its application a drainage plan, which 9shall include plans to repair or replace any subsurface drainage affected during the 10construction or decommissioning of the system. AB174,10,1511(12) Information for property owners and political subdivisions. (a) 12The public service commission shall create a pamphlet of not more than 2 pages, 13available on its website, that explains in plain language all provisions under this 14section and s. 196.491 (3) that relate specifically to large wind energy systems, large 15solar energy systems, and battery energy storage systems. AB174,10,2116(b) If the commission receives an application for a certificate of public 17convenience and necessity under s. 196.491 (3) for a large wind energy system, large 18solar energy system, or battery energy storage system, the commission shall 19distribute the pamphlet under par. (a) by mail or electronically to any owner of 20property on which or adjacent to which the project is proposed to be located and any 21political subdivision in which the project is proposed to be located. AB174,1422Section 14. 66.0627 (1) (bk) 2. of the statutes is amended to read: AB174,11,22366.0627 (1) (bk) 2. An improvement to a premises that allows for the small
1scale derivation of electricity from a renewable low-carbon-emission resource listed 2under s. 196.378 (1) (h). AB174,153Section 15. 93.74 of the statutes is created to read: AB174,11,5493.74 Purchase of agricultural conservation easements required for 5large wind, large solar, and battery systems. (1) Definitions. In this section: AB174,11,86(a) “Agricultural conservation easement” means a conservation easement, as 7defined in s. 700.40 (1) (a), the purpose of which is to assure the availability of land 8for agricultural use. AB174,11,119(b) “Agricultural use” has the meaning given in s. 93.73 (1m) (b), except that 10“agricultural use” does not include use of land on which any of the following is 11located: AB174,11,12121. A wind energy system, as defined in s. 66.0403 (1) (m). AB174,11,13132. A solar energy system, as defined in s. 13.48 (2) (h) 1. g. AB174,11,14143. A battery energy storage system, as defined in s. 196.491 (1) (ar). AB174,11,1715(c) “Owner-operator” means a person who has an ownership interest in land 16and who materially participates in a nonpassive trade or business that engages in 17an agricultural use on that land. AB174,11,2118(d) “Prime farmland” means land in use for an agricultural use or in use for a 19use that has agricultural value including land that is part of a crop rotation or land 20enrolled in the federal conservation reserve program under 16 USC 3831 et seq. if 21the land is any of the following: AB174,11,22221. Prime farmland under the specifications in 7 CFR 657.5 (a). AB174,11,23232. Unique farmland under the specifications in 7 CFR 657.5 (b). AB174,12,2
13. Additional farmland of statewide importance under the specification in 7 2CFR 657.5 (c). AB174,12,53(e) “Productivity index” means the national commodity crop productivity 4index as identified by the natural resources conservation service of the federal 5department of agriculture. AB174,12,76(f) “Purchase cost” means the amount paid to a landowner to acquire an 7agricultural conservation easement from the landowner. AB174,12,108(g) “Specified facility” means a large wind energy system, as defined in s. 966.0401 (1e) (bL), a large solar energy system, as defined in s. 66.0401 (1e) (bk), or 10a battery energy storage system, as defined in s. 196.491 (1) (ar). AB174,12,1711(2) Purchase of easement required. (a) 1. An owner of a specified facility 12that is located on land that has a productivity index of 0.6 or greater and that was 13prime farmland at the time that the application pursuant to s. 196.491 (3) was filed 14for the specified facility shall before placing the specified facility in service and, if 15the land is leased, before renewing a lease or entering into a new lease for land on 16which the specified facility is located purchase agricultural conservation easements 17as follows: AB174,12,2218a. For each acre of land on which the specified facility is located that was 19prime farmland having a productivity index of 0.8 or greater at the time that the 20application for the specified facility was filed, the owner shall purchase agricultural 21conservation easements for 4 acres of prime farmland having a productivity index 22of 0.8 or greater as provided in par. (b). AB174,13,323b. For each acre of land on which the specified facility is located that was 24prime farmland having a productivity index of not less than 0.6 and not more than
10.8 at the time that the application for the specified facility was filed, the owner 2shall purchase agricultural conservation easements for 2 acres of prime farmland 3having a productivity index of 0.6 of greater as provided in par. (b). AB174,13,1042. a. An owner of a specified facility that is located on land that was unique 5farmland under the specifications in 7 CFR 657.5 (b) or additional farmland of 6statewide importance under the specification in 7 CFR 657.5 (c) at the time that the 7application pursuant to s. 196.491 (3) was filed for the specified facility shall before 8placing the specified facility in service and, if the land is leased, before renewing a 9lease or entering into a new lease for land on which the specified facility is located 10purchase agricultural conservation easements as provided in par. (b). AB174,13,1811b. For each acre of land on which a specified facility described in subd. 2. a. is 12located that was unique farmland under the specifications in 7 CFR 657.5 (b) or 13additional farmland of statewide importance under the specification in 7 CFR 657.5 14(c) at the time that the application for the specified facility was filed, the owner 15shall purchase as provided in par. (b) agricultural conservation easements for 2 16acres of prime farmland that is unique farmland under the specifications in 7 CFR 17657.5 (b) or additional farmland of statewide importance under the specification in 187 CFR 657.5 (c) or that has a productivity index of 0.6 or greater. AB174,13,2319(b) 1. An owner required to purchase agricultural conservation easements 20under par. (a) shall make commercially reasonable efforts to purchase all of those 21required agricultural conservation easements on acres of prime farmland that are 22adjacent to the parcel on which the owner’s specified facility is located and that are 23owned by an owner-operator. AB174,14,6242. If an owner required to purchase agricultural conservation easements
1under par. (a) is unable to purchase all of those required agricultural conservation 2easements on acres of prime farmland described in subd. 1., the owner shall make 3commercially reasonable efforts to purchase the remaining agricultural 4conservation easements required under par. (a) on acres of prime farmland that are 5located in the same county as the owner’s specified facility and that are owned by an 6owner-operator. AB174,14,1373. If an owner required to purchase agricultural conservation easements 8under par. (a) is unable to purchase all of those required agricultural conservation 9easements on acres of prime farmland described in subd. 1. or 2., the owner shall 10make commercially reasonable efforts to purchase the remaining agricultural 11conservation easements required under par. (a) on acres of prime farmland that are 12located in a county that is adjacent to the county in which the owner’s specified 13facility located and that are owned by an owner-operator. AB174,14,19144. If an owner required to purchase agricultural conservation easements 15under par. (a) is unable to purchase all of those required agricultural conservation 16easements on acres of prime farmland described in subd. 1., 2., or 3., the owner 17shall make commercially reasonable efforts to purchase the remaining agricultural 18conservation easements required under par. (a) on acres of prime farmland that are 19adjacent to the parcel on which the owner’s specified facility is located. AB174,15,2205. If an owner required to purchase agricultural conservation easements 21under par. (a) is unable to purchase all of those required agricultural conservation 22easements on acres of prime farmland described in subd. 1., 2., 3., or 4., the owner 23shall make commercially reasonable efforts to purchase the remaining agricultural
1conservation easements required under par. (a) on acres of prime farmland that are 2located in the same county as the owner’s specified facility. AB174,15,936. If an owner required to purchase agricultural conservation easements 4under par. (a) is unable to purchase all of those required agricultural conservation 5easements on acres of prime farmland described in subd. 1., 2., 3., 4., or 5., the 6owner shall make commercially reasonable efforts to purchase the remaining 7agricultural conservation easements required under par. (a) on acres of prime 8farmland that are located in a county that is adjacent to the county in which the 9owner’s specified facility is located. AB174,15,15107. If an owner required to purchase agricultural conservation easements 11under par. (a) is unable to purchase all of those required agricultural conservation 12easements on acres of prime farmland described in subd. 1., 2., 3., 4., 5., or 6., the 13owner shall make commercially reasonable efforts to purchase the remaining 14agricultural conservation easements required under par. (a) on acres of prime 15farmland that are located in this state. AB174,15,1716(c) 1. The purchase cost of an agricultural conservation easement purchased 17pursuant to par. (a) shall be $2,500 for each acre. AB174,15,21182. The purchase cost of an agricultural conservation easement purchased 19pursuant to par. (a) shall be paid to the landowner in equal payments made over 5 20years, beginning with the year in which the specified facility for which that 21easement is purchased pursuant to par. (a) is placed in service. AB174,15,2322(d) 1. An agricultural conservation easement purchased pursuant to par. (a) 23shall satisfy all of the following: AB174,16,224a. The easement shall prohibit the land subject to the easement from being
1developed for a use that would make the land unavailable or unsuitable for 2agricultural use. AB174,16,43b. The easement shall include a provision that authorizes the department, on 4behalf of this state, to bring an action to enforce or defend the easement. AB174,16,652. An agricultural conservation easement purchased pursuant to par. (a) shall 6terminate at the one of the following, whichever is earliest: AB174,16,87a. The end of the lease term for the land on which is located the specified 8facility for which the easement is purchased pursuant to par. (a). AB174,16,109b. The termination of the lease for the land on which is located the specified 10facility for which the easement is purchased pursuant to par. (a). AB174,16,1211c. The decommissioning of the specified facility for which the easement is 12purchased pursuant to par. (a). AB174,16,1713(3) Splitting of facilities prohibited. An owner of a proposed specified 14facility may not separate the proposed specified facility into multiple specified 15facilities to decrease the nominal capacity of each of the specified facilities below 16100 megawatts to construct the specified facilities without complying with the 17requirements under this section. AB174,16,2118(4) Recording; enforcement; transfers. (a) Upon purchase of an 19agricultural conservation easement pursuant to sub. (2) (a), the holder shall 20promptly record the easement with the register of deeds of the county in which the 21land subject to the easement is located. AB174,16,2422(b) The department may enforce and defend an agricultural conservation 23easement purchased pursuant to sub. (2) (a) and may, on behalf of this state, bring 24an action to enforce or defend such an easement. AB174,17,3
1(c) The transfer of a holder’s interest in an agricultural conservation 2easement purchased pursuant to sub. (2) (a) does not affect the department’s 3authority to bring an action to enforce the agricultural conservation easement. AB174,17,54(d) A holder of an agricultural conservation easement purchased pursuant to 5sub. (2) (a) may not terminate the easement except as provided under sub. (2) (d) 2. AB174,17,106(e) If an owner of a specified facility that is required to purchase an 7agricultural conservation easement under sub. (2) (a) transfers ownership of the 8specified facility, the owner shall also transfer all agricultural conservation 9easements purchased for the specified facility that are held by the owner to the 10person to which the specified facility is transferred. AB174,1611Section 16. 114.135 (7) of the statutes is renumbered 114.135 (7) (b) (intro.) 12and amended to read: AB174,17,1513114.135 (7) (b) (intro.) For the purposes of sub. (6), the power and authority to 14control the erection of buildings, structures, towers, and other objects by the 15secretary of transportation shall be limited to those objects all of the following: AB174,17,17161. An object that would either extend to a height of more than 500 feet above 17the ground or surface of the water within one mile of the location of the object, or. AB174,17,20182. An object that would extend above a height determined by the ratio of one 19foot vertical to 40 feet horizontal measured from the nearest boundary of the 20nearest public airport or spaceport within the state; however, this. AB174,18,221(c) The power and authority under par. (b) shall not extend to objects of less 22than 150 feet in height above the ground or water level at the location of the object 23or to objects located within areas zoned under s. 114.136 or to objects located within
1areas zoned under s. 62.23 (7) where the zoning ordinance enacted under said 2subsection controls the height of structures. AB174,173Section 17. 114.135 (7) (a) of the statutes is created to read: AB174,18,44114.135 (7) (a) In this subsection: AB174,18,651. “High-voltage transmission line tower” means a tower used to support a 6high-voltage transmission line, as defined in s. 196.491 (1) (f). AB174,18,1072. “Light-mitigating technology system” means aircraft detection lighting or 8any other comparable system capable of reducing the impact of obstruction lighting 9while maintaining conspicuity sufficient to assist aircraft in identifying and 10avoiding collision with a structure. AB174,18,13113. “Utility structure” means a high-voltage transmission line tower or a wind 12energy system that meets the criteria that would require submittal of a notice to the 13federal aviation administration under 14 CFR 77.9. AB174,18,14144. “Wind energy system” has the meaning given in s. 66.0403 (1) (m). AB174,1815Section 18. 114.135 (7) (b) 3. of the statutes is created to read: AB174,18,1616114.135 (7) (b) 3. A utility structure. AB174,1917Section 19. 114.135 (7) (d) of the statutes is created to read: AB174,19,218114.135 (7) (d) 1. The secretary may not issue a permit under sub. (6) for a 19utility structure placed in service on or after the effective date of this subdivision .... 20[LRB inserts date], under par. (b) 3. unless the applicant has received federal 21aviation administration approval to install a light-mitigating technology system on 22the utility structure and the permit under sub. (6) includes as a condition that the
1applicant install the light-mitigating technology system no later than 24 months 2after issuance of the permit. AB174,19,1432. No person may install a light-mitigating technology system on a utility 4structure unless the person is approved by the federal aviation administration to 5perform that installation. A person who is selected to install a light-mitigating 6technology system on a utility structure required under subd. 1. shall provide notice 7to the department and to the city, village, or town in which the utility structure is 8located, in the form and manner prescribed by the department, of the progress of 9the installation. If the installation is delayed beyond the 24-month installation 10requirement under subd. 1., the installer shall provide an update to the department 11and to the city, village, or town in which the utility structure is located on the 12reasons for the delay and the current status of the installation not less than once 13every 3 months. The department may establish policies and procedures to set a 14uniform schedule for submitting notice and updates pursuant to this subdivision. AB174,19,19153. No later than July 1, 2026, the owner of a utility structure placed in service 16before the effective date of this subdivision .... [LRB inserts date], for which a 17permit is issued under sub. (6) shall submit a report to the public service 18commission on the commercial feasibility of installing a light-mitigating technology 19system on the utility structure. AB174,2020Section 20. 196.374 (3) (a) of the statutes is amended to read: AB174,20,621196.374 (3) (a) In general. The commission shall have oversight of programs 22under sub. (2). The commission shall maximize coordination of program delivery, 23including coordination between programs under subs. (2) (a) 1., (b) 1. and 2., and (c) 24and (7), ordered programs, low-income weatherization programs under s. 16.957,
1renewable resource low-carbon-emission energy source programs under s. 196.378, 2and other energy efficiency or renewable resource programs. The commission shall 3cooperate with the department of natural resources to ensure coordination of 4energy efficiency and renewable resource programs with air quality programs and 5to maximize and document the air quality improvement benefits that can be 6realized from energy efficiency and renewable resource programs. AB174,217Section 21. 196.378 (title) of the statutes is repealed and recreated to read: AB174,20,88196.378 (title) Low-carbon-emission energy sources.