May 15, 2025 - Offered by Senators Larson, Carpenter, Roys, Drake, Dassler-Alfheim, Habush Sinykin, Smith and Spreitzer.
SB125-SSA1,1,3
1An Act to amend 196.491 (2) (title); to create 196.491 (2) (a) 3s. and 196.491 2(2) (h) of the statutes; relating to: strategic energy assessments and
3integrated resource plans. Analysis by the Legislative Reference Bureau
This bill requires investor-owned and municipal electric utilities to file integrated resource plans with the Public Service Commission. An integrated resource plan must describe the resources an electric utility could use to meet the service needs of its customers over the next 5-year, 10-year, and 15-year periods, and must contain certain other information, including forecasts of electricity demand under various reasonable scenarios and plans and projected costs for meeting that electricity demand. PSC must establish requirements for the contents and filing of the plans, and PSC must approve, reject, or modify an electric utility’s integrated resource plan consistent with the public interest. The bill also requires PSC to review the integrated resource plans filed by electric utilities to inform its biennial strategic energy assessment. Under current law, the strategic energy assessment evaluates the adequacy and reliability of the state’s current and future energy supply.
The people of the state of Wisconsin, represented in senate and assembly, do enact as follows:
SB125-SSA1,1
1Section 1. 196.491 (2) (title) of the statutes is amended to read: SB125-SSA1,2,32196.491 (2) (title) Strategic energy assessment and integrated 3resource plans. SB125-SSA1,24Section 2. 196.491 (2) (a) 3s. of the statutes is created to read: SB125-SSA1,2,65196.491 (2) (a) 3s. Review the integrated resource plans submitted by electric 6utilities under par. (h) to help inform the strategic energy assessment. SB125-SSA1,37Section 3. 196.491 (2) (h) of the statutes is created to read: SB125-SSA1,3,28196.491 (2) (h) 1. Each electric utility shall prepare and file an integrated 9resource plan with the commission. The commission shall by order establish 10integrated resource plan content and filing requirements, including filing 11deadlines. An integrated resource plan shall include a set of resource options that 12an electric utility could use to meet the service needs of its customers over the next 135-year, 10-year, and 15-year periods, including an explanation of the supply-and-14demand circumstances under which, and the extent to which, each resource option 15would be used to meet those service needs. Resource options that could be used to 16meet service needs include using, refurbishing, and constructing electric generating 17plants and equipment; buying electricity generated by other entities; controlling 18customer loads; and implementing customer energy conservation. The commission 19shall approve, reject, or modify an electric utility’s integrated resource plan 20consistent with the public interest. The commission’s acceptance of an integrated 21resource plan under this paragraph does not constitute issuance of a certificate
1under s. 196.49 or issuance of a certificate of public convenience and necessity 2under sub. (3). SB125-SSA1,3,432. An integrated resource plan under this paragraph shall include all of the 4following: SB125-SSA1,3,65a. A long-term forecast of the electric utility’s sales and peak demand under 6various reasonable scenarios. SB125-SSA1,3,97b. Details regarding the amount of peak demand reduction the electric utility 8expects to achieve and the electric utility’s proposals for achieving the reduction in 9peak demand, including through load management and demand response. SB125-SSA1,3,1310c. If the plan identifies constructing a generation facility as a resource option, 11the type of generation technology proposed for the generation facility, the proposed 12capacity of the generation facility, and the projected fuel costs for the proposed 13generation facility under various reasonable scenarios. SB125-SSA1,3,1814d. Projected electricity purchased or produced by the electric utility that is 15generated from a renewable energy resource. If the electric utility projects the total 16level of electricity purchased or produced from a renewable energy resource to 17decrease over the periods described in subd. 1. a., the electric utility shall explain 18why the decrease is in the best interests of ratepayers. SB125-SSA1,3,2219e. Details regarding the impacts of energy efficiency programs on the electric 20utility’s electricity sales and peak demand under various reasonable scenarios, 21including the total amount of customer energy savings and the associated costs of 22the energy efficiency programs. SB125-SSA1,4,2
1f. Projected energy and capacity purchased or produced by the electric utility 2from a cogeneration resource. SB125-SSA1,4,43g. An analysis of potential new or upgraded electricity transmission options 4for the electric utility. SB125-SSA1,4,75h. Data regarding the electric utility’s current generation portfolio, including 6the age, capacity factor, licensing status, and estimated remaining operating time 7for each electric generating facility in the portfolio. SB125-SSA1,4,118i. Plans for meeting current and future capacity needs, including cost 9estimates for any power purchase agreement, any proposed construction or major 10investment, and any transmission or distribution infrastructure necessary to 11support proposed construction or major investments. SB125-SSA1,4,1412j. An analysis of the cost, capacity factor, and viability of all reasonable 13options available to meet projected energy and capacity needs, including existing 14electric generating facilities in this state. SB125-SSA1,4,1515k. Projected total costs for each scenario reviewed under this subdivision. SB125-SSA1,4,1816L. If applicable, projected long-term natural gas transportation contracts or 17natural gas storage that the electric utility will hold to provide an adequate supply 18of natural gas to new electric generating facilities. SB125-SSA1,4,1919m. Any other information required by the commission by order. SB125-SSA1,4,20203. This paragraph does not apply to cooperative associations.