(b) “Antenna equipment” or “wireless equipment” means equipment, switches, wiring, cabling, power sources, shelters, or cabinets associated with an antenna, located at the same fixed location as the antenna, and, when collocated on a structure, is mounted or installed at the same time as such antenna.
(c) “Antenna facility” means an antenna and associated antenna equipment, including ground-mounted antenna equipment.
(d) “Applicable codes” means the state electrical wiring code, as defined in s. 101.80 (4), the state plumbing code specified in s. 145.13, the fire prevention code under ch. SPS 314, Wis. adm. code, the Wisconsin commercial building code under chs. SPS 361 to 366, the Wisconsin uniform dwelling code under chs. SPS 320 to 325, and local amendments to those codes enacted solely to address imminent threats of destruction of property or injury to persons.
(e) “Applicant” means a wireless provider that submits an application.
(f) “Application” means an application for a permit under this section to collocate a small wireless facility or to install, modify, or replace a utility pole.
(g) “Collocate,” “collocate on,” or “collocation” means the placement, mounting, replacement, modification, operation, or maintenance of a small wireless facility on, or of ground-mounted antenna equipment adjacent to, a structure.
(h) “Communications facilities” means the set of equipment and network components, including wires and cables and associated facilities, used by a communications service provider to provide communications service.
(i) “Communications network” means a network used to provide a communications service.
(j) “Communications service” means cable service, as defined in 47 USC 522 (6), telecommunications service, as defined in 47 USC 153 (53), information service, as defined in 47 USC 153 (24), or wireless service.
(k) “Communications service provider” means a person that provides communications service.
(L) “Facility” means an antenna facility or a structure.
(m) “Fee” means a one-time charge.
(n) “Governmental pole” means a utility pole that is owned or operated by the state or by a political subdivision in a right-of-way.
(o) “Investor-owned electric utility” means a public utility whose purpose is the generation, transmission, delivery, or furnishing of electric power but does not include a public utility owned and operated wholly by a municipality or a cooperative association organized under ch. 185.
(p) “Micro wireless facility” means a small wireless facility that does not exceed 24 inches in length, 15 inches in width, and 12 inches in height and that has no exterior antenna longer than 11 inches.
(q) “Permit” means written authorization required by the state or a political subdivision to perform an action, or initiate, continue, or complete a project.
(r) “Political subdivision” means any city, village, town, or county.
(s) “Rate” means a recurring charge.
(t) “Right-of-way” means the area on, below, or above a highway, as defined in s. 340.01 (22), other than a federal interstate highway; sidewalk; utility easement, other than a utility easement for a cooperative association organized under ch. 185 for purposes of providing or furnishing heat, light, power, or water to its members only; or other similar property, including property owned or controlled by the department of transportation.
(u) “Small wireless facility” means a wireless facility to which all of the following apply:
1. The wireless facility satisfies any of the following:
a. The wireless facility is mounted on a structure 50 feet or less in height including any antenna.
b. The wireless facility is mounted on a structure no more than 10 percent taller than any other adjacent structure.
c. The wireless facility does not increase the height of an existing structure on which the wireless facility is located to a height of more than 50 feet or by 10 percent, whichever is greater.
2. Each antenna associated with the deployment of the wireless facility, excluding associated antenna equipment, is no more than 3 cubic feet in volume.
3. All other wireless equipment associated with the wireless facility specified in subd. 1., including the wireless equipment associated with the antenna and any preexisting associated equipment on the structure, is no more than 28 cubic feet in volume.
4. The wireless facility does not require registration as an antenna structure under 47 CFR part 17.
5. The wireless facility is not located on tribal land, as defined in 36 CFR 800.16 (x).
6. The wireless facility does not result in human exposure to radio frequency in excess of the applicable safety standards specified in 47 CFR 1.1307.
(v) Except in par. (zp), “structure” means a utility pole or wireless support structure, whether or not it has an existing antenna facility.
(w) “Technically feasible” means that by virtue of engineering or spectrum usage the proposed placement for a small wireless facility, or its design, concealment measures, or site location can be implemented without a reduction in the functionality of the small wireless facility.
(x) “Utility pole” means a pole that is used in whole or in part by a communications service provider; used for electric distribution, lighting, traffic control, signage, or a similar function; or used for the collocation of small wireless facilities. “Utility pole” does not include a wireless support structure or electric transmission structure.
(y) “Utility pole for designated services” means a utility pole owned or operated in a right-of-way by the state, a political subdivision, or a utility district that is designed to, or used to, carry electric distribution lines, or cables or wires for telecommunications, cable, or electric service.
(z) 1. “Wireless facility” means an antenna facility at a fixed location that enables wireless services between user equipment and a communications network, and includes all of the following:
a. Equipment associated with wireless services.
b. Radio transceivers, antennas, or coaxial, metallic, or fiber-optic cable located on, in, under, or otherwise adjacent to a utility pole or wireless support structure.
c. Regular and backup power supplies.
d. Equipment that is comparable to equipment specified in this subdivision regardless of technical configuration.
2. “Wireless facilities” does not include any of the following:
a. The structure or improvements on, under, or within which equipment specified in subd. 1. is collocated.
b. Wireline backhaul facilities.
c. Coaxial, metallic, or fiber-optic cable that is between utility poles or wireless support structures or that is not adjacent to a particular antenna.
(za) “Wireless infrastructure provider” means any person, other than a wireless services provider, that builds or installs wireless communication transmission equipment, antenna equipment, or wireless support structures.
(zc) “Wireless provider” means a wireless infrastructure provider or a wireless services provider.
(zg) “Wireless services” means any service using licensed or unlicensed wireless spectrum, including the use of a Wi-Fi network, whether at a fixed location or by means of a mobile device.
(zL) “Wireless services provider” means any person who provides wireless services.
(zp) “Wireless support structure” means an existing freestanding structure that is capable of supporting small wireless facilities, except that “wireless support structure” does not include any of the following:
1. A utility pole.
2. A structure designed solely for the collocation of small wireless facilities.
(zt) “Wireline backhaul facility” means a facility for providing wireline backhaul service.
(zx) “Wireline backhaul service” means the transport of communications services by wire from small wireless facilities to a communications network.
(2) Rights-of-way. (a) Applicability. This subsection applies only to the activities of a wireless provider within a right-of-way.
(b) Exclusive use prohibited. Neither the state nor a political subdivision may enter into an exclusive arrangement with any person for the use of a right-of-way for the construction, operation, marketing, maintenance, or collocation of small wireless facilities or wireless support structures.
(c) Rates and fees. Subject to sub. (3) (e) 3., the state or a political subdivision may charge a wireless provider a nondiscriminatory rate or fee for the use of a right-of-way with respect to the collocation of a small wireless facility or the installation, modification, or replacement of a utility pole in the right-of-way only if the state or political subdivision charges other entities for the use of the right-of-way. If the state or a political subdivision charges a wireless provider a rate or fee as described in this paragraph, all of the following apply:
1. Subject to subd. 5., the fee or rate must be limited to no more than the direct and actual cost of managing the right-of-way.
2. Except as provided in par. (d), the fee or rate must be competitively neutral with regard to other users of the right-of-way.
3. The fee or rate may not result in a double recovery by the state or political subdivision if existing fees, rates, or taxes imposed by a political subdivision on the wireless provider already recover the direct and actual cost of managing the right-of-way.
4. The fee or rate may not be in the form of a franchise or other fee based on revenue or customer counts.
5. The fee or rate may not exceed an annual amount equal to $20 multiplied by the number of small wireless facilities in the right-of-way in the state's or political subdivision's geographic jurisdiction.
6. Beginning on the effective date of this subdivision .... [LRB inserts date], the state or a political subdivision may adjust a rate or fee allowed under this paragraph by 10 percent every 5 years, rounded to the nearest dollar. During each 5-year period, the adjustment may be applied incrementally or as a single adjustment.
(d) Rate or fee adjustment. 1. Except as provided in subd. 2., by the later of the first day of the 3rd month beginning after the effective date of this subdivision .... [LRB inserts date], or 3 months after receiving its first request for access to the right-of-way by a wireless provider, the state or a political subdivision shall implement rates, fees, and terms for such access that comply with this subsection.
2. Agreements between a wireless provider and the state or a political subdivision that are in effect on the effective date of this subdivision .... [LRB inserts date], and that relate to access to the right-of-way, remain in effect, subject to applicable termination provisions, except that by the first day of the 25th month beginning after the effective date of this subdivision .... [LRB inserts date], the state or political subdivision shall amend any such agreement to comply with the rates, fees, and terms required under this subsection.
(e) Right of access. 1. Except as otherwise provided in this subsection and subs. (3) (c) 4. and 5. and (4), and notwithstanding ss. 182.017 and 196.58 and any zoning ordinance enacted by a political subdivision under s. 59.69, 60.61, 60.62, or 62.23, a wireless provider shall have the right to collocate small wireless facilities and construct, modify, maintain, and replace its own utility poles, or, with the permission of the owner, a 3rd party's utility pole, that supports small wireless facilities along, across, upon, and under a right-of-way. Such small wireless facilities and utility poles, and activities related to the installation and maintenance of the small wireless facilities and utility poles, may not obstruct or hinder travel, drainage, maintenance, or the public health, safety, and general welfare on or around the right-of-way, or obstruct the legal use of the right-of-way for other communications providers, public utilities, cooperative associations organized under ch. 185 for the purpose of producing or furnishing heat, light, power, or water to their members only, or pipes or pipelines transmitting liquid manure. A political subdivision may enact an ordinance consistent with this subdivision.
2. Except as provided in subd. 4., the height of a utility pole installed, or modified, in a right-of-way may not exceed the greater of:
a. A height that is 10 percent taller than the tallest existing utility pole as of the effective date of this subd. 2. a. .... [LRB inserts date], that is located within 500 feet of the new or modified utility pole in the same right-of-way.
b. Fifty feet above ground level.
3. The height of a small wireless facility installed, or modified, in a right-of-way may not exceed the greater of:
a. A height that is 10 percent taller than the existing utility pole or wireless support structure on which the small wireless facility is located.
b. Fifty feet above ground level.
4. A wireless provider may construct, modify, and maintain a utility pole, wireless support structure, or small wireless facility along, across, upon, and under a right-of-way that exceeds the height limits in this paragraph if the wireless provider complies with height limits under the zoning ordinances enacted by a political subdivision under s. 59.69, 60.61, 60.62, or 62.23.
5. With regard to the rights of a wireless provider to construct or modify a utility pole as described in subd. 1., a political subdivision may propose an alternate location for collocation, which the wireless provider shall use if it has the right to use the alternate structure on reasonable terms and conditions and the alternate location is technically feasible and does not impose material additional costs.
(f) Damage and repair. The state or a political subdivision may require a wireless provider to repair all damage that is directly caused by the activities of the wireless provider in a right-of-way involving its small wireless facilities or structures, and to return the right-of-way to its former condition before it was so damaged. If the wireless provider fails to make the required repairs within a reasonable amount of time after receiving a written request to do so from the state or a political subdivision, the state or political subdivision may make the necessary repairs and charge the liable party for the cost of the repairs. This paragraph does not prohibit a political subdivision from recovering damages under s. 86.02.
(g) Nondiscrimination. The state and political subdivisions must administer and regulate a right-of-way in a competitively neutral manner with regard to all users of the right-of-way.
(3) Permitting process. (a)
Applicability. This subsection applies to the permitting for the collocation of small wireless facilities by a wireless provider within and outside a right-of-way and to the permitting for the installation, modification, and replacement of associated utility poles by a wireless provider inside a right-of-way. Except as provided in this subsection and in subs. (2) and (4), neither the state nor a political subdivision may prohibit, regulate, or charge any person for the collocation of small wireless facilities.
(b) Zoning. Notwithstanding an ordinance enacted under s. 59.69, 60.61, 60.62, or 62.23, and except as provided in par. (c) 4. and 5., small wireless facilities shall be classified as permitted uses and are not subject to a political subdivision's zoning ordinances if they are collocated in a right-of-way or outside a right-of-way if the property is not zoned exclusively for single-family residential use. For purposes of this paragraph and notwithstanding sub. (1) (u) 3., the volume of a small wireless facility does not include preexisting associated wireless equipment on a structure outside the right-of-way.
(c) Permits. 1. Subject to subds. 4. and 5., the state or a political subdivision may require an application for a permit to collocate a small wireless facility and to construct, modify, maintain, or operate a new or replacement utility pole, provided such permit is of general applicability and does not apply exclusively to small wireless facilities. All of the following apply to such permit applications filed by an applicant:
a. Neither the state nor a political subdivision may require an applicant to perform services unrelated to the approval sought.
b. Neither the state nor a political subdivision may require an applicant that is a wireless provider to provide more information in its permit application than such a governmental unit requires from a communications service provider that is not a wireless provider and that applies for the same type of permit. The state or a political subdivision may require the types of information specified in subd. 2. in an application.
c. The state or a political subdivision shall notify an applicant in writing, within 10 days of receiving an application, whether it is complete. If an application is incomplete, the state or political subdivision shall specify why the application is incomplete. The processing deadlines under subd. 1. d., e., and f. restart at zero on the date that the applicant submits to the state or a political subdivision an application that includes information identified by the state or political subdivision to render the application complete.
d. Except as provided in subd. 1. g., if a permit application involves a new or replacement utility pole, and the state or a political subdivision fails to approve or deny the permit application under this section not later than 90 days after its receipt, the applicant may consider its permit application approved.
e. Except as provided in subd. 1. g., if a permit application proposes to collocate small wireless facilities on an existing structure and the state or a political subdivision fails to approve or deny the permit application under this section not later than 60 days after its receipt, the applicant may consider its permit application approved.
f. Except as provided in subd. 1. g., if there is any type of construction, building, or encroachment permit required by a political subdivision that relates to a permit under subd. 1. d. or e., and the political subdivision fails to approve or deny that permit application within the specified 60-day or 90-day time frame, the applicant may consider its permit application approved.
g. The applicant and the state or political subdivision may mutually agree to extend the deadline for the state or political subdivision to approve or deny a permit application under subd. 1. d., e., or f.
h. Subject to subd. 1. i., the state or a political subdivision shall approve a permit application unless it does not meet the applicable codes, sub. (2) (e) 1., or the standards of an ordinance enacted pursuant to sub. (2) (e) 1. If the permit application is denied for any of these reasons, the state or political subdivision shall provide the applicant with written documentation explaining the basis for the denial no later than the date that the permit application is denied. An applicant may cure the deficiencies identified in the documentation and resubmit the permit application no later than 30 days after receipt of the documentation without being required to pay an additional application fee. The state or a political subdivision shall approve or deny the revised permit application not later than 30 days after its receipt.
i. The state or a political subdivision may condition approval of a permit on compliance with reasonable and nondiscriminatory relocation, abandonment, or bonding requirements that are consistent with state law applicable to other occupiers of rights-of-way.
j. An applicant may file a consolidated permit application to collocate up to 30 small wireless facilities, or a greater number if agreed to by a political subdivision, provided that all the small wireless facilities in the application consist of substantially similar equipment and are to be placed on similar types of structures. In rendering a decision on a consolidated permit application, a political subdivision may approve a permit for some small wireless facilities and deny a permit for others, but the political subdivision may not use the denial of one or more permits as a basis to deny permits for all of the small wireless facilities in the application.
k. If an applicant's permit application is approved, the applicant shall commence the activity authorized by the permit no later than 365 days after its receipt and shall pursue work on the activity until completion. Neither the state nor a political subdivision may place any time limitation on an applicant that is related to the permit. An applicant may request that the state or a political subdivision terminate the applicant's permit.
2. The state or a political subdivision may require any of the following types of information in an application for a permit specified in subd. 1. (intro.):
a. The applicant's name, address, telephone number, e-mail address, and emergency contact information.