NR 440.20(9)(c)5.5. The ratio of the upper confidence limit for the mean outlet emission rate (Eo*) and the allowable emission rate (Estd), as applicable.
NR 440.20(9)(d)(d) If any standards under sub. (4) are exceeded during emergency conditions because of control system malfunction, the owner or operator of the affected facility shall submit a signed statement:
NR 440.20(9)(d)1.1. Indicating if emergency conditions existed and requirements under sub. (6) (d) were met during each period, and
NR 440.20(9)(d)2.2. Listing the following information:
NR 440.20(9)(d)2.a.a. Time periods the emergency condition existed;
NR 440.20(9)(d)2.b.b. Electrical output and demand on the owner or operator’s electric utility system and the affected facility;
NR 440.20(9)(d)2.c.c. Amount of power purchased from interconnected neighboring utility companies during the emergency period;
NR 440.20(9)(d)2.d.d. Percent reduction in emissions achieved;
NR 440.20(9)(d)2.e.e. Atmospheric emission rate (ng/J) of the pollutant discharged; and
NR 440.20(9)(d)2.f.f. Actions taken to correct control system malfunction.
NR 440.20(9)(e)(e) If fuel pretreatment credit toward the sulfur dioxide emission standard under sub. (4) is claimed, the owner or operator of the affected facility shall submit a signed statement:
NR 440.20(9)(e)1.1. Indicating what percentage cleaning credit was taken for the calendar quarter, and whether the credit was determined in accordance with the provisions of sub. (8) and Method 19 of 40 CFR part 60, Appendix A, incorporated by reference in s. NR 440.17; and
NR 440.20(9)(e)2.2. Listing the quantity, heat content, and date each pretreated fuel shipment was received during the previous quarter; the name and location of the fuel pretreatment facility; and the total quantity and total heat content of all fuels received at the affected facility during the previous quarter.
NR 440.20(9)(f)(f) For any periods for which opacity, sulfur dioxide or nitrogen oxides emissions data are not available, the owner or operator of the affected facility shall submit a signed statement indicating if any changes were made in operation of the emission control system during the period of data unavailability. Operations of the control system and affected facility during periods of data unavailability are to be compared with operation of the control system and affected facility before and following the period of data unavailability.
NR 440.20(9)(g)(g) The owner or operator of the affected facility shall submit a signed statement indicating whether:
NR 440.20(9)(g)1.1. The required continuous monitoring system calibration, span, and drift checks or other periodic audits have or have not been performed as specified.
NR 440.20(9)(g)2.2. The data used to show compliance was or was not obtained in accordance with approved methods and procedures of this chapter and is representative of plant performance.
NR 440.20(9)(g)3.3. The minimum data requirements have or have not been met; or, the minimum data requirements have not been met for errors that were unavoidable.
NR 440.20(9)(g)4.4. Compliance with the standards has or has not been achieved during the reporting period.
NR 440.20(9)(h)(h) For the purposes of the reports required under s. NR 440.07, periods of excess emissions are defined as all 6-minute periods during which the average opacity exceeds the applicable opacity standards under sub. (3) (b). Opacity levels in excess of the applicable opacity standard and the date of such excesses shall be submitted to the department each calendar quarter.
NR 440.20(9)(i)(i) The owner or operator of an affected facility shall submit the written reports required under this subsection and ss. NR 440.01 to 440.15 to the department semiannually for each 6-month period. All semiannual reports shall be postmarked by the 30th day following the end of each 6-month period.
NR 440.20(9)(j)(j) The owner or operator of an affected facility may submit electronic quarterly reports for SO2, NOx and opacity in lieu of submitting the written reports required under pars. (b) and (h). The format of each quarterly electronic report shall be coordinated with the department. The electronic report shall be submitted no later than 30 days after the end of the calendar quarter and shall be accompanied by a certification statement from the owner or operator, indicating whether compliance with the applicable emission standards and minimum data requirements of this section was achieved during the reporting period. Before submitting reports in the electronic format, the owner or operator shall coordinate with the department to obtain agreement to submit reports in this alternative format.
NR 440.20 HistoryHistory: Cr. Register, January, 1984, No. 337, eff. 2-1-84; am. (7) (h) 1., 3., 4., (L) 1. and (8) (a) 1., Register, September, 1986, No. 369, eff. 10-1-86; am. (2) (intro.), (7) (h) 1. to 3., (i) 1., (8) (a) 1. to 6., r. (8) (a) 7., Register, September, 1990, No. 417, eff. 10-1-90; am. (4) (h) 1. and 2., (5) (a) 1., (c), (6) (d) 3. (intro.) and (h), r. and recr. (7) (f), (h), (i) (intro.) to 2. and (8), cr. (7) (j), Register, July, 1993, No. 451, eff. 8-1-93; am. (2) (n), (y), (5) (a) 1., (7) (h) 2., (8) (b) 2., Register, December, 1995, No. 480, eff. 1-1-96; correction in (4) (b) (intro.) made under s. 13.93 (2m) (b) 7., Stats., Register, November, 1999, No. 527; CR 06-109: am. (1) (b), (2) (b), (n), (q) 1. b. and (y), (4) (d) 2., (f), (5) (a) (intro.), 1. and 2., (b) and (c), (7) (e) and (i) 1. and 3., (8) (title) and (b) 2. b. and (9) (i), cr. (2) (gr) and (Lm), (5) (d), (6) (a) (title), (b) (title), (c) (title), (d) (title), (e) (title), (f) (title), (g) (title) and (h) (title), (i) to (k), (7) (c) 2. and (k) to (n), (8) (f) and (9) (j), renum. (7) (c) to be (7) (c) 1. Register May 2008 No. 629, eff. 6-1-08.
NR 440.205NR 440.205Industrial - commercial - institutional steam generating units.
NR 440.205(1)(1)Applicability.
NR 440.205(1)(a)(a) The affected facility to which this section applies is each steam generating unit that commences construction, modification, or reconstruction after June 19, 1984, and that has a heat input capacity from fuels combusted in the steam generating unit of more than 29 MW (100 million Btu/hour).
NR 440.205(1)(b)(b) Any affected facility meeting the applicability requirements under par. (a) and commencing construction, modification, or reconstruction after June 19, 1984, but on or before June 19, 1986, is subject to the following standards:
NR 440.205(1)(b)1.1. Coal-fired affected facilities having a heat input capacity between 29 and 73 MW (100 and 250 million Btu/hour), inclusive, are subject to the particulate matter and nitrogen oxides standards under this section.
NR 440.205(1)(b)2.2. Coal-fired affected facilities having a heat input capacity greater than 73 MW (250 million Btu/hour) and meeting the applicability requirements under s. NR 440.19 (standards of performance for fossil fuel-fired steam generators) are subject to the particulate matter and nitrogen oxides standards under this section and to the sulfur dioxide standards in s. NR 440.19 (4).