Adm 24.02(9)(9) “Hearing examiner” means a designee of the secretary who is authorized to conduct a fact-finding hearing and to prepare written findings of fact and who may be authorized to issue debarment and suspension decisions pursuant to this chapter.
Adm 24.02(10)(10) “Indictment” includes an indictment for a criminal offense, an information or any other filing by a competent authority charging a criminal offense that results in finding probable cause to believe a felony has been committed and in binding the defendant over for trial.
Adm 24.02(11)(11) “Ineligible” means excluded from contracting with the department and, if appropriate, from department-approved subcontracting, under statute, rule, order or legal authority other than this chapter.
Adm 24.02 NoteNote: Examples of reasons for ineligibility are wage-rate violations, civil rights violations and deficient progress.
Adm 24.02(12)(12) “Secretary” means the secretary of the department or an authorized representative or designee.
Adm 24.02(13)(13) “Suspension” means action taken by the department under s. Adm 24.06 to exclude a contractor from contracting with the department or from department-approved subcontracting temporarily pending the completion of an investigation or of a debarment decision-making proceeding. A contractor so excluded is “suspended.”
Adm 24.02 HistoryHistory: CR 10-063: cr. Register December 2010 No. 660, eff. 1-1-11.
Adm 24.03Adm 24.03List and records of debarred and suspended contractors.
Adm 24.03(1)(1)List.
Adm 24.03(1)(a)(a) The department shall compile and maintain a current, consolidated list of debarred, suspended and ineligible contractors.
Adm 24.03(1)(b)(b) The department shall use the consolidated list to ensure that it does not solicit offers from, award contracts to, or consent to subcontract with listed contractors, except as otherwise provided in this chapter.
Adm 24.03(2)(2)Records. The department shall maintain records relating to each debarred or suspended contractor. Records shall contain all of the following:
Adm 24.03(2)(a)(a) Names and addresses of all debarred or suspended contractors.
Adm 24.03(2)(b)(b) Cause or causes for each debarment or suspension.
Adm 24.03(2)(c)(c) Any limitations on or deviations from the normal effect of debarment or suspension.
Adm 24.03(2)(d)(d) Effective date of the debarment or suspension and, in the case of a debarment, during the term of the contract.
Adm 24.03 HistoryHistory: CR 10-063: cr. Register December 2010 No. 660, eff. 1-1-11.
Adm 24.04Adm 24.04Treatment of listed contractors.
Adm 24.04(1)(1)Effect.
Adm 24.04(1)(a)(a) The department may not knowingly solicit bids from, award contracts to, renew an existing contract with, or consent to subcontracts with a debarred or suspended contractor, unless the secretary determines, in writing, that a compelling reason for such dealing with the contractor exists.
Adm 24.04(1)(b)(b) The department may not enter a contract with an ineligible contractor and, if applicable, shall exclude ineligible contractors from subcontracts under the conditions and for the period set forth in the applicable statutes, rules, orders or other legal authority. The department may not knowingly solicit bids from, award contracts to, renew an existing contract with, or consent to subcontract with these contractors except in accord with the applicable statutes, rules, orders or other legal authority.
Adm 24.04(2)(2)Current contract continuation.
Adm 24.04(2)(a)(a) Notwithstanding the listing of a contractor, the department may continue contracts or subcontracts in existence at the time the contractor was debarred or suspended, unless the secretary determines that contract termination is in the public interest.
Adm 24.04(2)(b)(b) Contract termination decisions under par. (a), if any, may be made only after review by and consultation with both department contracting personnel and department legal counsel to assure the propriety of the proposed contract termination.
Adm 24.04(2)(c)(c) The department may not renew existing contracts or subcontracts with debarred or suspended contractors, unless the secretary determines and states in writing a compelling reason for the contract renewal or extension.
Adm 24.04(3)(3)Subcontract restrictions. When a debarred or suspended contractor is proposed as a subcontractor for any subcontract subject to department approval, the department may not give approval unless the secretary determines and states in writing a compelling reason for the approval.
Adm 24.04 HistoryHistory: CR 10-063: cr. Register December 2010 No. 660, eff. 1-1-11.
Adm 24.05Adm 24.05Debarment.
Adm 24.05(1)(1)General.