NR 811.09(1)(f)(f) Pumping facilities. The plan shall show a general layout of the pumping equipment, pump bases, suction and discharge lines and related appurtenances. NR 811.09(1)(g)(g) Buildings. The plans shall show the locations of all buildings and other site improvements in relation to the site property boundaries. The following details shall be included, where applicable: NR 811.09(1)(g)1.1. Building dimensions, profiles, elevations, architectural details, plumbing details, HVAC details, security details, and other building appurtenances. NR 811.09(1)(g)3.3. The diameter and locations of all water mains, water service laterals, and appurtenances such as valves and hydrants. NR 811.09(1)(g)4.4. The diameters and locations of all floor drains, building drain, building sewer, and POWTS components. NR 811.09(1)(g)5.5. The location, elevations, construction details, and appurtenances of any on-site storm water retention or detention ponds. NR 811.09(1)(g)6.6. Construction details for any non-water system related improvements to be located or constructed on the property. NR 811.09(1)(h)1.1. ‘Location plan.’ The plan shall show the proposed water main extensions in relation to existing facilities. A map, such as required by s. NR 810.26 (2), of the existing system or a portion thereof with the proposed extensions shown will satisfy this requirement. NR 811.09(1)(h)2.a.a. The location of the proposed water main within the street right-of-way or easement. NR 811.09(1)(h)2.c.c. Elevations at intersections and hydrants or a profile of the proposed water main, proposed or existing sanitary sewers, and storm sewers. NR 811.09(1)(h)2.g.g. Profile views including the ground surface, the proposed water main, the proposed sanitary or storm sewer, and rock depths when approval of a common trench is being requested in areas of high bedrock. NR 811.09(1)(h)3.3. ‘Worksheet submittal.’ Complete information as requested on any required worksheet shall be provided. The forms shall be completed for all water main projects including revisions to existing projects, upgrading of existing mains and resubmittals of projects previously approved by the department. NR 811.09(1)(i)1.1. ‘Location plan.’ The plan shall show the location of the proposed facility in relation to existing facilities. NR 811.09(1)(i)2.2. ‘Detailed plans.’ Plans shall show contour lines at the site and complete construction details. Overflow elevations for existing and proposed facilities shall be noted. NR 811.09(2)(2) Specifications. Complete, detailed material and construction specifications shall be supplied for all phases of the proposed project. Specifications shall contain a program for keeping existing waterworks facilities in operation during construction of additional facilities so as to minimize interruptions of service. Specifications shall be included for controlling erosion on the construction site as a result of construction activity as specified in subch. V of ch. NR 151. NR 811.09 NoteNote: Department approved Construction Site Erosion and Sediment Control Technical Standards can be found on the department’s internet web site.
NR 811.09(3)(3) Engineering report. An engineering report shall be submitted with all reviewable projects with the exception of water main extensions. The engineering report, required by s. NR 108.04 (2) (a), shall contain the controlling assumptions made and the factors used in determining the functional design of the proposed waterworks improvements as a whole and of each of the component parts or units. Where applicable, the report shall make reference to available regional, metropolitan, county or local water supply or water quality management plans and shall clearly indicate whether the proposed project is in conformance with the plans. NR 811.09 NoteNote: It is recommended that the report also include an energy efficiency analysis.
NR 811.09(4)(4) Engineering report requirements. The engineering report required under sub. (3) shall, in all cases, indicate the basis of design and shall include the following specific data, if applicable: NR 811.09(4)(a)(a) Description. A brief description of the project and the need for improvements. NR 811.09(4)(b)(b) Location. A description of the geographic location of the project, including reference to maps or exhibits and the location of existing facilities.