PSC 111.53(1)(f)7.f.f. Secondary impacts, including effects on revenue, jobs, and development.
PSC 111.53(1)(f)7.g.g. Visual and noise impact.
PSC 111.53(1)(f)8.8. Aesthetics.
PSC 111.53(1)(f)9.9. If a CPCN is needed for construction of transmission lines as part of this application, the required information under s. PSC 111.55.
PSC 111.53(1)(g)(g) Any additional information the commission may request, including information necessary for it to make the determinations listed in s. 196.491 (3) (d), Stats., or to prepare an environmental assessment or an environmental impact statement under s. 1.11, Stats.
PSC 111.53(2)(2)Exceptions to filing requirements.
PSC 111.53(2)(a)(a) An application for a wholesale merchant plant need not include the information identified in sub. (1) (b) to (d). In addition, an application for a wholesale merchant plant that will be owned, controlled, or operated by an affiliated interest of a public utility, shall include any additional information required by the commission in order to make a determination under s. 196.491 (3m) (a), Stats.
PSC 111.53(2)(b)(b) Based on the pre-application consultation required under s. PSC 111.51 (2) (b), an application for a generation facility may include the detailed information listed under sub. (1) (f) for only one site if none of the needed infrastructure improvements would constitute a major action significantly affecting the quality of the human environment under s. 1.11 (2) (c), Stats., and the application is for any of the following:
PSC 111.53(2)(b)1.1. Construction of a cogeneration facility located at the steam host’s existing industrial plant, if the cogeneration facility will be a qualifying facility under 18 CFR 292.205.
PSC 111.53(2)(b)2.2. Modifying, rebuilding, replacing or repowering, as defined under s. 79.005 (4), Stats., an existing generating facility at its current location.
PSC 111.53(2)(b)3.3. Construction of a generating facility proposed to be located on an existing brownfield site, as defined in s. 16.287 (1) (a), Stats., and interpreted by the commission, or on the site of a former or existing large electric generating facility.
PSC 111.53 NoteNote: See sub. (1) (e) concerning information that must be included about both the site in sub. (2) (b) and any alternatives.
PSC 111.53 HistoryHistory: Cr. Register, June, 2000, No. 534, eff. 7-1-00; CR 07-044: am. (1) (e) and (f) (intro.), cr (1) (em), (2) (b) 1. and 3., renum. (2) (b) 1. to be (2) (b) (intro.) and am., r. and recr. (2) (b) 2. Register May 2008 No. 629, eff. 6-1-08; correction to (1) (em), (2) (b) 3. made under s. 13.92 (4) (b) 7., Stat., Register January 2012 No. 673.
PSC 111.55PSC 111.55CPCN applications for high-voltage transmission lines. A CPCN application for a high-voltage transmission line is not complete until the applicant has filed all of the following information with the commission:
PSC 111.55(1)(1)Need. The need for the proposed project, including all planning criteria, assumptions, historical outage data, stability, and power-flow studies that address need.
PSC 111.55(2)(2)Design. The physical design characteristics, including structure type, design span length, conductor size and type, foundation type, operating voltage, and feasibility of future increases in operating voltage.
PSC 111.55(3)(3)Basis for design selection. The basis for selection of physical design characteristics.
PSC 111.55(4)(4)EMF levels. The estimated magnetic field levels.
PSC 111.55(5)(5)Substation design. The substation design or modifications to existing substations.
PSC 111.55(6)(6)Owners and investors. The names and addresses of owners and investors, and percent of ownership.
PSC 111.55(7)(7)Construction schedule and approvals. The construction schedule and required regulatory approvals.
PSC 111.55(8)(8)Additional information. Any additional information the commission may request, including information necessary for it to make the determinations listed in s. 196.491 (3) (d), Stats., or to prepare an environmental assessment or environmental impact statement under s. 1.11, Stats.
PSC 111.55(9)(9)Tariff filings. Whether an open-access tariff has been filed with the FERC.
PSC 111.55(10)(10)Proposed routes. Except as otherwise submitted under this section, proposed routes and the pertinent factors considered in choosing them, including engineering, economic, safety, reliability and environmental considerations. All of the following information shall be filed for each of the proposed routes:
PSC 111.55(10)(a)(a) Estimated construction cost and assumptions.
PSC 111.55(10)(b)(b) Geology.
PSC 111.55(10)(c)(c) Topography.
PSC 111.55(10)(d)(d) General soil associations.
PSC 111.55(10)(e)(e) Water resources, including wetlands, lakes, rivers, and streams.