ATCP 79.09(2)(a)(a) Changes to or replacement of equipment or construction.
ATCP 79.09(2)(b)(b) Changes in or cessations of any operation or method of operation of the equipment or premises.
ATCP 79.09 NoteNote: A request for hearing, under sub. (2), shall be submitted to the DATCP Secretary via e-mail at datcpappeals@wisconsin.gov, faxed to (608) 224-5034, mailed to PO Box 8911, Madison, Wisconsin 53708-8911, or hand delivered to 2811 Agriculture Drive, Madison, Wisconsin 53718. The hearing may be conducted by the department secretary or designee.
ATCP 79.09(3)(3)If the department voids a license for failure to pay fees under s. ATCP 79.05 (6), the operator shall submit, within 15 days after receipt of the notice of the department’s action, documentary evidence that all applicable fees, late fees and processing charges have been paid and that there are no outstanding payments due to the department.
ATCP 79.09 HistoryHistory: CR 15-001: cr. Register October 2015 No. 718, eff. 2-1-16; renum. from DHS 178.09 Register June 2016 No. 726; correction in (1) (a), (2) (intro.), (3) made under s. 13.92 (4) (b) 7., Stats., Register June 2016 No. 726; CR 18-019: am. (1) (a), (e), (3) Register January 2020 No. 769, eff. 2-1-20.
ATCP 79.10ATCP 79.10Appeals of actions by agent health departments. If an agent issues a license under this chapter, the operator shall appeal enforcement action to the agent health department.
ATCP 79.10 HistoryHistory: CR 15-001: cr. Register October 2015 No. 718, eff. 2-1-16; renum. from DHS 178.10 Register June 2016 No. 726; CR 18-019: am. Register January 2020 No. 769, eff. 2-1-20.
ATCP 79.11ATCP 79.11Campsite use, designation, location, and density.
ATCP 79.11(1)(1)Campsite use. No operator may allow a campsite to be occupied by the same individual for more than 8 continuous months in any 12 month period.
ATCP 79.11(2)(2)Campsite designation. The operator shall clearly mark each campsite with an alpha or numeric symbol that is a minimum of 2 inches in height and visible from the campground’s internal road system. This rule first applies to an existing campground symbol when the symbol is changed or replaced on or after February 1, 2016.
ATCP 79.11(3)(3)Campground map. The operator shall maintain a current and accurate map of the campground. The map shall the show the layout and location of each campsite and operator-provided camping unit or tourist rooming house. The operator shall make the map available to all campground occupants during registration or on request.
ATCP 79.11(4)(4)Campsite location.
ATCP 79.11(4)(a)(a) Hazards. A campsite may not be located in an area of a campground that is subject to the accumulation of water or in any other area that would constitute a health or safety hazard.
ATCP 79.11 NoteNote: The location of campsites and campground attributes in a flood plain or shore land area must be approved by local zoning or the DNR. See ch. NR 115 and s. NR 116.12 (2) (b) as enforced by the department of natural resources. Contact your local DNR office or local zoning office for more information.
ATCP 79.11(4)(b)(b) Sources of odor or flies.
ATCP 79.11(4)(b)1.1. A campsite may not be located within 100 feet of a barn or enclosure housing an animal, a petting zoo, or other source of odors or flies. This paragraph first applies to campsites created after February 1, 2016.
ATCP 79.11(4)(b)2.2. This provision does not apply to dogs and cats in individual campsites or for other animals as approved by a variance under s. ATCP 79.02 (2).
ATCP 79.11(5)(5)Campground density. Except as provided under s. ATCP 79.27, the operator shall ensure that the density of the campground is as follows:
ATCP 79.11(5)(a)(a) Individual campsites. An operator may designate no more than 20 individual campsites per acre of campground. Each campsite is limited to 6 campers or an individual family.
ATCP 79.11(5)(b)(b) Group campsites. An operator may allow no more than 80 campers per acre in a group campsite.
ATCP 79.11 HistoryHistory: CR 15-001: cr. Register October 2015 No. 718, eff. 2-1-16; renum. from DHS 178.11 Register June 2016 No. 726; correction in (4) (b) 2., (5) made under s. 13.92 (4) (b) 7., Stats., Register June 2016 No. 726.
ATCP 79.12ATCP 79.12Campground access and road systems.
ATCP 79.12(1)(1)Access. Access to a campground shall be designed to minimize congestion and hazards at the entrance and exit.
ATCP 79.12(2)(2)Roadways. All roads within the campground shall be graded and maintained to provide drainage.
ATCP 79.12 HistoryHistory: CR 15-001: cr. Register October 2015 No. 718, eff. 2-1-16; renum. from DHS 178.12 Register June 2016 No. 726.
ATCP 79.13ATCP 79.13Camping units.
ATCP 79.13(1)(1)Distance separation requirements.
ATCP 79.13(1)(a)(a) Distance requirement.
ATCP 79.13(1)(a)1.1. The operator shall require a minimum distance of 10 feet between camping units measured from the outside edge of one camping unit to the outside edge of another camping unit, excluding slideouts.