NR 811.47(7)(c)5.5. ‘Other designs.’ Baffling may be used to provide flocculation only after approval by the department. The design shall be such that the velocities and flows in this section shall be maintained.
NR 811.47(7)(c)6.6. ‘Superstructure.’ A superstructure shall be provided over the flocculation basins.
NR 811.47(7)(d)(d) Sedimentation. Sedimentation shall follow flocculation. The detention time for effective clarification is dependent upon factors related to basin design as well as the nature of the raw water, such as turbidity, color and colloidal matter, and taste and odor causing compounds.
NR 811.47(7)(d)1.1. ‘Detention time.’ Plants with conventional sedimentation shall provide a minimum of 4 hours of settling time. This may be reduced to 2 hours for lime-soda softening facilities treating only groundwater. Also, reduced sedimentation time may be approved when equivalent effective settling is demonstrated or when overflow rate is not more than 0.5 gallons per minute per square foot.
NR 811.47(7)(d)2.2. ‘Inlet devices.’ Inlets shall be designed to distribute the water equally and at uniform velocities. Open ports, submerged ports, and similar entrance arrangements are required. A baffle shall be constructed across the basin, close to the inlet end, and project several feet below the water surface to dissipate inlet velocities and provide uniform flows across the basin.
NR 811.47(7)(d)3.3. ‘Outlet devices.’ Outlet devices shall be designed to maintain velocities suitable for settling in the basin and to minimize short circuiting. The use of submerged orifices is recommended in order to provide volume above the orifices for storage when there are fluctuations in flow.
NR 811.47(7)(d)4.4. ‘Weir overflow rate.’ The rate of flow over the outlet weir may not exceed 20,000 gallons per day per foot of weir length. If submerged ports or orifices are used as an alternate for overflow weirs, they may not be lower than 3 feet below the flow line with flow rates equivalent to weir loadings. The entrance velocity through the submerged orifices shall not exceed 0.5 feet per second.
NR 811.47(7)(d)5.5. ‘Drainage.’ Basins shall be provided with a means for dewatering. Basin bottoms shall slope toward the drain not less than one foot in 12 feet where mechanical sludge collection is not provided.
NR 811.47(7)(d)6.6. ‘Covers.’ Covers or superstructures are required at all plants. Where covers are used, access hatches shall be provided as well as drop light connections so that observation of the floc can take place at the inlet, midpoint and outlet of the basin.
NR 811.47(7)(d)7.7. ‘Velocity.’ The velocity through settling basins may not exceed 0.5 feet per minute. The basins shall be designed to minimize short circuiting. Fixed or adjustable baffles shall be provided as necessary to achieve the maximum potential for clarification.
NR 811.47(7)(d)8.8. ‘Overflow.’ An overflow weir or pipe shall be installed, which will establish the maximum water level desired on top of the filters. It shall discharge by gravity with a downturned pipe elbow a minimum of one foot above a concrete splash pad and shall be covered with 4-mesh corrosion resistant screen at a location where the discharge is visible and where the water can be appropriately drained.
NR 811.47(7)(d)9.9. ‘Safety.’ Guard rails shall be installed around openings which may be hazardous to maintenance personnel. Permanent holders or handholds shall be provided on the inside walls of basins above the water level.
NR 811.47(7)(d)10.10. ‘Sludge collection.’ Mechanical sludge collection equipment may be provided.
NR 811.47(7)(d)11.11. ‘Sludge removal.’ Facilities for disposal of sludge are required by the department. Sludge removal design shall provide:
NR 811.47(7)(d)11.a.a. Sludge pipes not less than 3 inches in diameter and so arranged as to facilitate cleaning.
NR 811.47(7)(d)11.b.b. Entrance to sludge withdrawal piping to prevent clogging.
NR 811.47(7)(d)11.c.c. Valves located outside the tank for accessibility.
NR 811.47(7)(d)11.d.d. Provisions for the operator to observe and sample sludge being withdrawn from the unit.
NR 811.47(7)(d)12.12. ‘Sludge disposal.’ Sections NR 811.858 and 811.861 contain additional specific requirements for sludge disposal. Flushing lines or hydrants shall be provided to backflush sludge lines and basins or for other purposes. Protection shall be provided for all potable water lines used if potable water could become contaminated by nonpotable water.
NR 811.47(7)(e)(e) Solids contact unit. Units designed for combined softening and clarification, if water characteristics, especially temperature, do not fluctuate rapidly and flow rates are uniform and operation is continuous, may be used if specifically approved by the department. Units shall be designed for the maximum uniform rate and be adjustable to changes in flow, which are less than the design rate and for changes in water characteristics. A minimum of 2 units are required unless the department waives this requirement. For plants with multiple units, the rated capacity of the plant shall be available with one unit out of service.
NR 811.47(7)(e)1.1. ‘Installation of equipment.’ Supervision by a representative of the manufacturer shall be provided whenever mechanical equipment is installed and at the time of initial operation.
NR 811.47(7)(e)2.2. ‘Operating equipment.’ A complete outfit of tools and accessories shall be provided. Laboratory equipment to control the treatment process shall be provided at all waterworks. In addition, sampling taps with adequate piping located to permit the collection of samples of water from critical portions of the units shall be provided.
NR 811.47(7)(e)3.3. ‘Chemical feed.’ Chemicals shall be applied at points and by means as to ensure satisfactory mixing of the chemicals with the water.
NR 811.47(7)(e)4.4. ‘Mixing.’ Mixing devices employed shall be constructed to provide adequate mixing of the raw water with previously formed sludge particles and to prevent deposition of solids in the mixing zone. A rapid mix device or chamber ahead of the solids contact unit may be required by the department.
NR 811.47(7)(e)5.5. ‘Flocculation.’ Flocculation equipment shall be adjustable by speed, or pitch or both, provide for coagulation to occur in a separate chamber or baffled zone within the unit, and provide a flocculation and mixing period of not less than 30 minutes.
NR 811.47(7)(e)6.6. ‘Sludge concentrators.’ Sludge concentrators shall provide either internal or external concentrators in order to obtain a concentrated sludge with a minimum of wastewater.
NR 811.47(7)(e)7.7. ‘Sludge removal.’ Sludge removal design shall provide all of the following:
NR 811.47(7)(e)7.a.a. Sludge pipes not less than 3 inches in diameter, arranged to facilitate cleaning.
NR 811.47(7)(e)7.b.b. Entrance to sludge withdrawal piping to prevent clogging.