NR 115.04(3)(f)(f) The construction and maintenance of duck blinds provided that no filling, flooding, draining, dredging, ditching, tiling or excavating is done.
NR 115.04(3)(g)(g) The construction and maintenance of nonresidential structures, not to exceed 500 square feet, used solely in conjunction with the raising of waterfowl, minnows, or other wetland or aquatic animals, or used solely for some other purpose which is compatible with wetland preservation if the structure cannot as a practical matter be located outside the wetland, provided that no filling, flooding, draining, dredging, ditching, tiling or excavating is done.
NR 115.04(3)(h)(h) The construction and maintenance of piers, docks and walkways, including those built on pilings, provided that no filling, flooding, dredging, draining, ditching, tiling or excavating is done.
NR 115.04(3)(i)(i) The establishment and development of public and private parks and recreation areas, boat access sites, natural and outdoor education areas, historic and scientific areas, wildlife refuges, game preserves and private wildlife habitat areas, provided that no filling is done and that any private wildlife habitat area is used exclusively for that purpose. The owner or operator of a new private recreation or wildlife area to be located in a shoreland-wetland zoning district shall be required to notify the county zoning agency of the proposed project before beginning construction. Ditching, excavating, dredging, dike and dam construction shall be allowed in wildlife refuges, game preserves, and private wildlife habitat areas for the purpose of improving wildlife habitat or to otherwise enhance wetland values.
NR 115.04(3)(j)(j) The construction and maintenance of electric, gas, telephone water and sewer transmission and distribution lines, and related facilities, by public utilities and cooperative associations organized for the purpose of producing or furnishing heat, light, power or water to their members, which cannot as a practical matter be located outside the wetland, provided that any filling, excavating, ditching or draining necessary for such construction or maintenance is done in a manner designed to minimize flooding and other adverse impacts upon the natural functions of the wetland.
NR 115.04 NoteNote: Major electrical generating facilities and high-voltage transmission lines that have obtained a certificate of public convenience and necessity under s. 196.491, Stats., are not subject to the requirements of local ordinances.
NR 115.04(3)(k)(k) The construction and maintenance of railroad lines which cannot as a practical matter be located outside the wetland, provided that any filling, excavating, ditching or draining necessary for the construction or maintenance is done in a manner designed to minimize flooding and other adverse impacts upon the natural functions of the wetland.
NR 115.04(3)(L)(L) The maintenance, repair, replacement, and reconstruction of existing town and county highways and bridges.
NR 115.04(4)(4)Prohibited uses in shoreland-wetland zoning districts. Any use not permitted in sub. (3) is prohibited in a shoreland-wetland zoning district unless the wetland or portion thereof is rezoned by amendment of the county shoreland zoning ordinance in accordance with s. 59.69 (5) (e), Stats., and the procedures outlined in sub. (2) (c).
NR 115.04 HistoryHistory: CR 05-058: cr. Register January 2010 No. 649, eff. 2-1-10.
NR 115.05NR 115.05Minimum zoning standards for shorelands.
NR 115.05(1)(1)Establishment of shoreland zoning standards. The shoreland zoning ordinance adopted by each county shall control use of shorelands to afford the protection of water quality as specified in chs. NR 102 and 103. At a minimum, the ordinance shall include all of the following provisions:
NR 115.05(1)(a)(a) Minimum lot sizes. Minimum lot sizes in the shoreland area shall be established to afford protection against danger to health, safety and welfare, and protection against pollution of the adjacent body of water.
NR 115.05(1)(a)1.1. ‘Sewered lots.’ Lots served by public sanitary sewer shall have a minimum average width of 65 feet and a minimum area of 10,000 square feet.
NR 115.05(1)(a)2.2. ‘Unsewered lots.’ Lots not served by public sanitary sewer shall have a minimum average width of 100 feet and a minimum area of 20,000 square feet.
NR 115.05(1)(a)3.3. ‘Substandard lots.’ A legally created lot or parcel that met minimum area and minimum average width requirements when created, but does not meet current lot size requirements, may be used as a building site if all of the following apply:
NR 115.05 NoteNote: Effective April 17, 2012, 2011 Wisconsin Act 170 created s. 59.692 (2m), Stats., which prohibits a county from enacting, and a county, city, or village from enforcing, any provision in a county shoreland or subdivision ordinance that regulates the construction of a structure or building on a substandard lot if the provision is more restrictive than the standards for substandard lots under ch. NR 115.
NR 115.05(1)(a)3.a.a. The substandard lot or parcel was never reconfigured or combined with another lot or parcel by plat, survey, or consolidation by the owner into one property tax parcel.
NR 115.05(1)(a)3.b.b. The substandard lot or parcel has never been developed with one or more of its structures placed partly upon an adjacent lot or parcel.
NR 115.05(1)(a)3.c.c. The substandard lot or parcel is developed to comply with all other ordinance requirements.
NR 115.05(1)(a)4.4. ‘Planned unit development.’ A non-riparian lot may be created which does not meet the requirements of subd. 1. if the county has approved and recorded a plat or certified survey map including that lot within a planned unit development, if the planned unit development contains at least 2 acres or 200 feet of frontage, and if the reduced non-riparian lot sizes are allowed in exchange for larger shoreland buffers and setbacks on those lots adjacent to navigable waters that are proportional to and offset the impacts of the reduced lots on habitat, water quality and natural scenic beauty.
NR 115.05(1)(b)(b) Building setbacks. Permitted building setbacks shall be established to conform to health, safety and welfare requirements, preserve natural beauty, reduce flood hazards and avoid water pollution.
NR 115.05(1)(b)1.1. ‘Shoreland setback.’ Except where exempt under subd. 1m., a setback of 75 feet from the ordinary high-water mark of any navigable waters to the nearest part of a building or structure shall be required for all buildings and structures. Where an existing development pattern exists, the shoreland setback for a proposed principal structure may be reduced to the average shoreland setback of the principal structure on each adjacent lot, but the shoreland setback may not be reduced to less than 35 feet from the ordinary high-water mark of any navigable waters.
NR 115.05 NoteNote: A property owner may seek a variance to a dimensional standard of the county ordinance and a county board of adjustment may review the request pursuant to s. 59.694 (7) (c), Stats.
NR 115.05(1)(b)1m.1m. ‘Exempt structures.’ All of the following structures are exempt from the shoreland setback standards in subd. 1.:
NR 115.05(1)(b)1m.a.a. Boathouses located entirely above the ordinary high-water mark and entirely within the access and viewing corridor that do not contain plumbing and are not used for human habitation.
NR 115.05 NoteNote: This chapter does not prohibit repair and maintenance of boathouses located above the ordinary high-water mark.
NR 115.05(1)(b)1m.b.b. Open sided and screened structures such as gazebos, decks, patios and screen houses in the shoreland setback area that satisfy the requirements in s. 59.692 (1v), Stats.
NR 115.05(1)(b)1m.c.c. Fishing rafts that are authorized on the Wolf river and Mississippi river under s. 30.126, Stats.