b. Fifty feet above ground level.
3. The height of a small wireless facility installed, or modified, in a right-of-way may not exceed the greater of:
a. A height that is 10 percent taller than the existing utility pole or wireless support structure on which the small wireless facility is located.
b. Fifty feet above ground level.
4. A wireless provider may construct, modify, and maintain a utility pole, wireless support structure, or small wireless facility along, across, upon, and under a right-of-way that exceeds the height limits in this paragraph if the wireless provider complies with height limits under the zoning ordinances enacted by a political subdivision under s. 59.69, 60.61, 60.62, or 62.23.
5. With regard to the rights of a wireless provider to construct or modify a utility pole as described in subd. 1., a political subdivision may propose an alternate location for collocation, which the wireless provider shall use if it has the right to use the alternate structure on reasonable terms and conditions and the alternate location is technically feasible and does not impose material additional costs.
(f) Damage and repair. The state or a political subdivision may require a wireless provider to repair all damage that is directly caused by the activities of the wireless provider in a right-of-way involving its small wireless facilities or structures, and to return the right-of-way to its former condition before it was so damaged. If the wireless provider fails to make the required repairs within a reasonable amount of time after receiving a written request to do so from the state or a political subdivision, the state or political subdivision may make the necessary repairs and charge the liable party for the cost of the repairs. This paragraph does not prohibit a political subdivision from recovering damages under s. 86.02.
(g) Nondiscrimination. The state and political subdivisions must administer and regulate a right-of-way in a competitively neutral manner with regard to all users of the right-of-way.
(3) Permitting process. (a)
Applicability. This subsection applies to the permitting for the collocation of small wireless facilities by a wireless provider within and outside a right-of-way and to the permitting for the installation, modification, and replacement of associated utility poles by a wireless provider inside a right-of-way. Except as provided in this subsection and in subs. (2) and (4), neither the state nor a political subdivision may prohibit, regulate, or charge any person for the collocation of small wireless facilities.
(b) Zoning. Notwithstanding an ordinance enacted under s. 59.69, 60.61, 60.62, or 62.23, and except as provided in par. (c) 4. and 5., small wireless facilities shall be classified as permitted uses and are not subject to a political subdivision's zoning ordinances if they are collocated in a right-of-way or outside a right-of-way if the property is not zoned exclusively for single-family residential use. For purposes of this paragraph and notwithstanding sub. (1) (u) 3., the volume of a small wireless facility does not include preexisting associated wireless equipment on a structure outside the right-of-way.
(c) Permits. 1. Subject to subds. 4. and 5., the state or a political subdivision may require an application for a permit to collocate a small wireless facility and to construct, modify, maintain, or operate a new or replacement utility pole, provided such permit is of general applicability and does not apply exclusively to small wireless facilities. All of the following apply to such permit applications filed by an applicant:
a. Neither the state nor a political subdivision may require an applicant to perform services unrelated to the approval sought.
b. Neither the state nor a political subdivision may require an applicant that is a wireless provider to provide more information in its permit application than such a governmental unit requires from a communications service provider that is not a wireless provider and that applies for the same type of permit. The state or a political subdivision may require the types of information specified in subd. 2. in an application.
c. The state or a political subdivision shall notify an applicant in writing, within 10 days of receiving an application, whether it is complete. If an application is incomplete, the state or political subdivision shall specify why the application is incomplete. The processing deadlines under subd. 1. d., e., and f. restart at zero on the date that the applicant submits to the state or a political subdivision an application that includes information identified by the state or political subdivision to render the application complete.
d. Except as provided in subd. 1. g., if a permit application involves a new or replacement utility pole, and the state or a political subdivision fails to approve or deny the permit application under this section not later than 90 days after its receipt, the applicant may consider its permit application approved.
e. Except as provided in subd. 1. g., if a permit application proposes to collocate small wireless facilities on an existing structure and the state or a political subdivision fails to approve or deny the permit application under this section not later than 60 days after its receipt, the applicant may consider its permit application approved.
f. Except as provided in subd. 1. g., if there is any type of construction, building, or encroachment permit required by a political subdivision that relates to a permit under subd. 1. d. or e., and the political subdivision fails to approve or deny that permit application within the specified 60-day or 90-day time frame, the applicant may consider its permit application approved.
g. The applicant and the state or political subdivision may mutually agree to extend the deadline for the state or political subdivision to approve or deny a permit application under subd. 1. d., e., or f.
h. Subject to subd. 1. i., the state or a political subdivision shall approve a permit application unless it does not meet the applicable codes, sub. (2) (e) 1., or the standards of an ordinance enacted pursuant to sub. (2) (e) 1. If the permit application is denied for any of these reasons, the state or political subdivision shall provide the applicant with written documentation explaining the basis for the denial no later than the date that the permit application is denied. An applicant may cure the deficiencies identified in the documentation and resubmit the permit application no later than 30 days after receipt of the documentation without being required to pay an additional application fee. The state or a political subdivision shall approve or deny the revised permit application not later than 30 days after its receipt.
i. The state or a political subdivision may condition approval of a permit on compliance with reasonable and nondiscriminatory relocation, abandonment, or bonding requirements that are consistent with state law applicable to other occupiers of rights-of-way.
j. An applicant may file a consolidated permit application to collocate up to 30 small wireless facilities, or a greater number if agreed to by a political subdivision, provided that all the small wireless facilities in the application consist of substantially similar equipment and are to be placed on similar types of structures. In rendering a decision on a consolidated permit application, a political subdivision may approve a permit for some small wireless facilities and deny a permit for others, but the political subdivision may not use the denial of one or more permits as a basis to deny permits for all of the small wireless facilities in the application.
k. If an applicant's permit application is approved, the applicant shall commence the activity authorized by the permit no later than 365 days after its receipt and shall pursue work on the activity until completion. Neither the state nor a political subdivision may place any time limitation on an applicant that is related to the permit. An applicant may request that the state or a political subdivision terminate the applicant's permit.
2. The state or a political subdivision may require any of the following types of information in an application for a permit specified in subd. 1. (intro.):
a. The applicant's name, address, telephone number, e-mail address, and emergency contact information.
b. The names, addresses, telephone numbers, and e-mail addresses of all duly authorized representatives and consultants, if any, acting on behalf of the applicant with respect to the filing of the application.
c. A general description of the proposed small wireless facility and associated utility pole, if applicable. The scope and detail of such description shall be appropriate to the nature and character of the work to be performed, with special emphasis on those matters likely to be affected or impacted by the physical work proposed.
d. Site plans and detailed construction drawings to scale that identify the proposed small wireless facility and the proposed use of the right-of-way.
e. To the extent the proposed facility involves collocation on a new utility pole, existing utility pole, or existing wireless support structure, a structural report performed by a duly licensed engineer evidencing that the utility pole or wireless support structure will structurally support the collocation, or that the utility pole or wireless support structure may and will be modified to meet structural requirements, in accordance with applicable codes.
f. If the small wireless facility will be collocated on a utility pole or wireless support structure owned by a 3rd party, other than a governmental pole or a utility pole for designated services, a certification that the wireless provider has permission from the owner to collocate on the utility pole or wireless support structure.