PSC 134.25(3)(3) Unless specifically directed otherwise a calorimeter shall be maintained and used to measure the heating value of the gas actually sold to customers in those cases where mixed gases are used. PSC 134.25(4)(4) Tests of heating value of the gas shall be made daily whenever gas is supplied at the calorimeter location unless specifically directed otherwise by the commission. The original records of the tests shall be dated, labeled and kept on file for 6 years. A copy of the daily average heating value of gas sold to customers shall be sent to the commission each calendar month. PSC 134.25(5)(5) The calorimeter equipment shall be maintained so as to give results within + or - 1%. Recording calorimeters used to test or control the production or mixing of gas or measure the heating value of purchased gas when therm rates are not applicable shall be tested with a gas of known heating value at least 3 times a year or when the accuracy is in question. Recording calorimeters used only with standby or peak shaving production plants shall be tested with a gas of known heating value at least 2 times a year. Non-recording calorimeter equipment such as the Junkers shall be tested with a gas of known heating value at least once a year or tested against another calorimeter of known accuracy at least once a year. PSC 134.25 HistoryHistory: Cr. Register, February, 1959, No. 38, eff. 3-1-59; am. (5), Register, January, 1965, No. 109, eff. 2-1-65. PSC 134.251PSC 134.251 Use of recording calorimeter for therm billing. PSC 134.251(1)(1) In the application of gas rates based on the therm, a recording calorimeter shall be used to determine the heating value of the gas being distributed to utility customers. These calorimeters will be located as set forth in s. PSC 134.25 (2) and (3). They shall have such accuracy characteristics as to be able to measure the heating value of the gas to within + or -2 B.t.u., shall be able to reproduce these readings to within +or - 2 B.t.u., and shall be able to hold their accuracy over an extended period of time. The instruments shall be installed in accordance with the manufacturer’s recommendations. PSC 134.251(2)(2) Each utility selling gas shall file with the commission a complete installation report stating the following information: location of calorimeter, kind of gas tested, type of scale, uniform or split scale range, date installed, publication number of manufacturer’s applicable book of instructions, outline of the building, the location of the calorimeter or calorimeters within the building, the size, length, gas pressure, and general route of the gas sample pipe from the supply main to each calorimeter and location of all secondary equipment necessary for the operation of the recording calorimeter. PSC 134.251(3)(a)(a) Each utility selling gas shall keep a chronological record of dates and results of tests and operations performed on the calorimeter to test and maintain accuracy. PSC 134.251(3)(b)1.1. Two days of each month shall be selected for the performance of an “as found” accuracy test, mechanical tests, adjustments, and an “as left” accuracy test of each recording calorimeter, and thereafter the specified accuracy tests, adjustments, and maintenance work shall be performed on the same days of each month insofar as practicable. PSC 134.251(3)(b)2.2. In making the accuracy tests on the calorimeter, the utility shall use reference natural gas which has been certified by the Institute of Gas Technology before cleaning parts or making any adjustments to either the tank unit or the recorder mechanism. The change from line gas to the certified gas should be made so as to have a continuous chart recording. The inlet pressure used should be the same for both calibration and subsequent operation. PSC 134.251(3)(b)3.3. If the “as found” accuracy test is within + or -3 B.t.u., no adjustment will be required and the instrument may be returned to service. If the “as found” accuracy test is not within + or - 3 B.t.u., maintenance shall be performed to restore the accuracy of the instrument. PSC 134.251(3)(b)4.4. In order that adequate information concerning each cylinder of natural gas which is to be used for the semi-monthly check tests be available at all times, the following information shall be entered on a form or in a log book provided for the purpose and also on a label or tag securely attached to each cylinder in which the gas is stored: PSC 134.251(3)(b)4.g.g. Heating value to be used in the semi-monthly accuracy tests. This heating value will not include any plus or minus values. For example, if the heating value is 1,000 + or - 0.9 B.t.u. per cubic foot, the heating value is 1,000 B.t.u. per cubic foot. PSC 134.251(5)(5) The original chart records produced by the recording calorimeters shall be dated, labeled, and kept on file for 6 years. A copy of the daily average heating value of gas and the results of the semi-monthly“as found” and “as left” test shall be sent to the commission each calendar month. PSC 134.251(6)(6) A gravitometer may be substituted for the calorimeter equipment required to control standby or peak shaving plants in subs. (1) and (5) provided the heat content of the standby or peak shaving gas produced does not directly affect the therm billing of the gas customer receiving it. PSC 134.251 HistoryHistory: Cr. Register, January, 1965, No. 109, eff. 2-1-65; cr. (6), Register, July, 1983, No. 331, eff. 8-1-83. PSC 134.26PSC 134.26 Meter testing and testing equipment. PSC 134.26(1)(1) Each public utility giving gas service is responsible for the accuracy of equipment used to measure service to its customers and all gas supplied by the utility shall be metered unless specific exemption is obtained from the public service commission. The utility shall own and maintain the equipment and facilities necessary for accurately testing the various types and sizes of meters used by the utility for the measurement of gas, shall make the tests required by these rules, shall maintain the measuring devices, and maintain their accuracy; unless arrangements are made to have the work done by others who have properly equipped laboratories, are approved by the commission and arrangements are also made to have equipment and procedures checked by the public service commission. A test by the manufacturer of a metering device is not acceptable unless witnessed by a utility representative. PSC 134.26(2)(2) Each public utility giving gas service shall own and maintain, except as provided in sub. (1), a meter prover of sufficient capacity to test meters in accordance with s. PSC 134.28. The meter prover shall be complete with all accessories needed for accurate meter testing, shall be suitably located for meter testing, and shall be protected from drafts and excessive temperature changes. The equipment shall be maintained in good condition and correct adjustment and be capable of determining the accuracy of service meters to within one-half of one per cent. When the meter prover is used to test temperature-compensating meters, there shall be present a temperature-indicating device to accurately determine the temperature of the prover to within + or - 1° Fahrenheit. PSC 134.26(3)(3) Each public utility giving gas service through turbine or rotary displacement type meters shall a) own and maintain, except as provided in sub. (1), a flow or volumetric meter of suitable capacity, together with necessary accessories, and it shall maintain such equipment in proper adjustment so that it will be capable of determining the accuracy of turbine or rotary displacement type meters to within one-half of one percent; or b) have a record of tests of each turbine or rotary displacement type meter made by an acceptable laboratory or by a manufacturer witnessed by a representative of the utility. The record should show that the test included a check of the recording device.