NR 169.23(3)(e)(e) An owner or operator requesting reimbursement from the department shall keep copies of all workplans and proposals required under this subsection, and shall make those copies available to the department for inspection and copying upon request. The owner or operator shall keep copies of the bids and cost estimates for at least 3 years beyond the completion of the project.
NR 169.23(4)(4)Interim action proposal estimate contents. Interim action activities included in the proposals shall include the need for and scope of the interim action, the implementation of the interim action, the design and documentation report at the conclusion of the action. Interim action proposals shall be consistent with s. NR 708.11.
NR 169.23(5)(5)Site investigation workplan estimate contents. Every site investigation workplan under sub. (2) (b) shall include all the following:
NR 169.23(5)(a)(a) A clear description and itemization of the consultant and contract services included in the workplan based on the site investigation scoping report or, if there is no scoping report, on a good faith estimate of the scope of the project.
NR 169.23(5)(b)(b) A form provided by the department containing a description of the overall strategy for assessing the impacts from the site; a monitoring strategy to include parameters necessary to evaluate enhanced natural attenuation or monitored natural attenuation as a remedy, including a minimum of 4 rounds of groundwater sampling; and a discussion of the management of investigative derived waste.
NR 169.23 NoteNote: Forms are available at no charge from the remediation and redevelopment program in any department regional or central office or by contacting the department at (608) 266-2111.
NR 169.23(5)(c)(c) A total cost estimate for all the consultant and contract services included in the workplan and a subtotal price for each of the component services itemized in the workplan.
NR 169.23(5)(d)(d) All the following information related to every service priced on an hourly or per unit basis:
NR 169.23(5)(d)1.1. The price per hour or per unit of service.
NR 169.23(5)(d)2.2. A reasonable, good faith estimate of the number of hours or units of service to be provided.
NR 169.23(5)(d)3.3. The total estimated price for the service, based on the estimate under subd. 2.
NR 169.23(5)(d)4.4. The estimated date by which the consultant and contractor will perform their services.
NR 169.23(5)(e)(e) Every certification required under sub. (9).
NR 169.23(6)(6)Remedial action proposal estimate content. Every remedial action proposal submitted under sub. (2) (c), and every cost estimate under sub. (3) (a) shall include all of the following information on a form provided by the department:
NR 169.23(6)(a)(a) A ch. NR 722 evaluation of technical and economic feasibility for appropriate alternatives at a site, including an evaluation of natural attenuation and enhanced natural attenuation.
NR 169.23(6)(b)(b) A description of the remedy proposed for the site. The description shall include an explanation of how that remedy will result in compliance with ch. NR 726 pertaining to case closure.
NR 169.23(6)(c)(c) A clear description and itemization of the consultant and contract services included in the proposal. The description and itemization shall be based on the proposed remedy selected for the site.
NR 169.23(6)(d)(d) A description and cost estimate for the implementation, analysis and interpretation of a pilot test for all active remediation systems, unless the consultant can justify to the department’s satisfaction that a pilot test is not necessary.
NR 169.23(6)(e)(e) A total cost estimate for all the consultant and contract services included in the proposal and a subtotal price for each component service itemized in the proposal.
NR 169.23(6)(f)(f) All the following information related to every service priced on an hourly or per unit basis:
NR 169.23(6)(f)1.1. The price per hour or per unit of service.
NR 169.23(6)(f)2.2. A reasonable, good faith estimate of the number of hours or units of service to be provided.
NR 169.23(6)(f)3.3. The total estimated price for the service, based on the estimate under subd. 2.
NR 169.23(6)(f)4.4. The estimated schedule by which the consultant and contractor will perform their services.
NR 169.23(6)(g)(g) Every certification required under sub. (9).
NR 169.23(7)(7)Services priced on an hourly or per unit basis.
NR 169.23(7)(a)(a) Cost estimates for the following services shall be priced on an hourly or per unit basis:
NR 169.23(7)(a)1.1. Excavating.
NR 169.23(7)(a)2.2. Trucking.