NR 440.216(12)(L)1.1. Method 9 of 40 CFR part 60, Appendix A, incorporated by reference in s. NR 440.17 (1), shall be used for determining compliance with the opacity limit.
NR 440.216(12)(L)2.2. The owner or operator of the air curtain incinerator shall conduct an initial performance test for opacity as required under s. NR 440.08.
NR 440.216(12)(L)3.3. Following the date that the initial performance test is completed or is required to be completed under s. NR 440.08, the owner or operator of the air curtain incinerator shall conduct a performance test for opacity on an annual basis, no more than 12 calendar months following the previous performance test.
NR 440.216(12)(m)(m) The owner or operator of an affected facility where activated carbon injection is used to comply with the mercury emission limit under sub. (3) (e), or the dioxin/furan emission limits under sub. (5), or the dioxin/furan emission level specified in sub. (12) (g) 5. c., shall comply with the following procedures:
NR 440.216(12)(m)1.1. During the performance tests for dioxins/furans and mercury, as applicable, the owner or operator shall estimate an average carbon mass feed rate based on carbon injection system operating parameters such as the screw feeder speed, hopper volume, hopper refill frequency or other parameters appropriate to the feed system being employed, as follows:
NR 440.216(12)(m)1.a.a. An average carbon mass feed rate in kilograms per hour or pounds per hour shall be estimated during the initial performance test for mercury emissions and each subsequent performance test for mercury emissions.
NR 440.216(12)(m)1.b.b. An average carbon mass feed rate in kilograms per hour or pounds per hour shall be estimated during the initial performance test for dioxin/furan emissions and each subsequent performance test for dioxin/furan emissions.
NR 440.216(12)(m)2.2. During operation of the affected facility, the carbon injection system operating parameters that are the primary indicators of the carbon mass feed rate, for example, screw feeder setting, shall equal or exceed the levels documented during the performance tests specified under subd. 1. a. and b.
NR 440.216(12)(m)3.3. The owner or operator of an affected facility shall estimate the total carbon usage of the plant, kilograms or pounds, for each calendar quarter by 2 independent methods, according to the following procedures:
NR 440.216(12)(m)3.a.a. The weight of carbon delivered to the plant.
NR 440.216(12)(m)3.b.b. Estimate the average carbon mass feed rate in kilograms per hour or pounds per hour for each hour of operation for each affected facility based on the parameters specified under subd. 1., and sum the results for all affected facilities at the plant for the total number of hours of operation during the calendar quarter.
NR 440.216(13)(13)Reporting and recordkeeping requirements.
NR 440.216(13)(a)(a) The owner or operator of an affected facility with a capacity to combust greater than 250 tons per day shall submit, on or before the date the application for a construction permit is submitted under ch. NR 405 or 408, the following items:
NR 440.216(13)(a)1.1. The preliminary and final draft materials separation plans required by sub. (11) (a) 1. and 5.
NR 440.216(13)(a)2.2. A copy of the notification of the public meeting required by sub. (11) (a) 1. b.
NR 440.216(13)(a)3.3. A transcript of the public meeting required by sub. (11) (a) 2.
NR 440.216(13)(a)4.4. A copy of the document summarizing responses to public comments required by sub. (11) (a) 3.
NR 440.216(13)(b)(b) The owner or operator of an affected facility with a capacity to combust greater than 250 tons per day shall submit a notification of construction, which includes the following information:
NR 440.216(13)(b)1.1. Intent to construct.
NR 440.216(13)(b)2.2. Planned initial startup date.
NR 440.216(13)(b)3.3. The types of fuels that the owner or operator plans to combust in the affected facility.
NR 440.216(13)(b)4.4. The municipal waste combustor unit capacity, and supporting capacity calculations prepared in accordance with sub. (12) (j).
NR 440.216(13)(b)5.5. All of the following documents associated with the siting requirements under sub. (11) (a) and (b):
NR 440.216(13)(b)5.a.a. The siting analysis required by sub. (11) (b) 1. and 2.
NR 440.216(13)(b)5.b.b. The final materials separation plan for the affected facility required by sub. (11) (a) 10.
NR 440.216(13)(b)5.c.c. A copy of the notification of the public meeting required by sub. (11) (b) 3. b.
NR 440.216(13)(b)5.d.d. A transcript of the public meeting required by sub. (11) (b) 4.
NR 440.216(13)(b)5.e.e. A copy of the document summarizing responses to public comments required by sub. (11) (a) 9. and (b) 5.
NR 440.216(13)(c)(c) The owner or operator of an air curtain incinerator subject to the opacity limit under sub. (10) shall provide a notification of construction that includes the information specified in par. (b) 1. to 4.