NR 504.06(6)(f)1.1. Sweep bends at all changes of alignment, using a minimum radius of 10 pipe diameters, consisting of prefabricated PVC sweep bends or smooth pipe bends or prefabricated sweep bends for HDPE or other pipe materials.
NR 504.06(6)(f)2.2. Pipe alignments that minimize horizontal and vertical alignment changes for the entire leachate collection pipe length.
NR 504.06(6)(f)3.3. Elimination or minimization of obstructions or artifacts of construction which impose drag on pipe cleaning jetter hose or nozzles.
NR 504.06(7)(7)Composite-lined landfills using GCLs. Use of GCLs in construction of a composite liner may not be used except in landfills which do not accept municipal solid waste, unless the GCL is used as a pad for the upper surface of the 4 foot clay component of a composite liner for a municipal solid waste landfill. The GCL and soil barrier layer components of a barrier system shall meet all of the following requirements:
NR 504.06(7)(a)(a) The hydraulic performance of the GCL shall be assessed by the use of compatibility testing. The testing protocol shall be provided to the department for review and concurrence prior to the initiation of compatibility testing. The compatibility testing shall utilize percolation fluids that simulate the leachate that will be produced by the landfill.
NR 504.06(7)(b)(b) The GCL shall meet the specifications of s. NR 504.07 (4) (a) 1. to 11.
NR 504.06(7)(c)(c) The GCL shall be underlain by a soil barrier layer that is a minimum of 2 feet thick and that meets the specifications of s. NR 504.07 (4) (a) 12. to 17.
NR 504.06 HistoryHistory: Cr. Register, January, 1988, No. 385, eff. 2-6-88; r. and recr., Register, June, 1996, No. 486, eff. 7-1-96; am. (5) (e) and (t), Register, August, 1997, No. 500; CR 04-077: cr. (5) (cm), (dm), (j) 4., 5., (tm) and (6), am. (5) (d), (e), and (t) Register November 2005 No. 599, eff. 12-1-05; CR 05-020: cr. (7) Register January 2006 No. 601, eff. 2-1-06; correction made under s. 13.93 (2m) (b) 1., Stats., Register January 2006 No. 601; CR 06-026: am. (5) (dm) and (e), Register December 2006 No. 612, eff. 1-1-07.
NR 504.07NR 504.07Minimum design and construction criteria for final cover systems.
NR 504.07(1)(1)General.
NR 504.07(1)(a)(a) All final cover systems shall be designed to minimize leachate generation by limiting the amount of percolation through the cap system, reduce landfill maintenance by stabilizing the final surface through design of compatible slopes and establishment of vegetation, account for differential settlement and other stresses on the capping layer, minimize the climatic effects of freeze-thaw and desiccation on the clay capping layer of the final cover system, and provide removal of leachate and venting of gas from those landfills which accept wastes with a high moisture content or which readily biodegrade.
NR 504.07(1)(b)(b) All new landfills and expansions of existing landfills shall be designed with a final cover system meeting the requirements in subs. (2) to (9) unless it is established to the satisfaction of the department that portions of the final cover system are not needed based on the proposed waste types and the proposed design. The geomembrane component in sub. (5) does not apply to landfills designed exclusively for the disposal of high volume industrial waste, or to other landfills which are not designed to accept municipal solid waste unless the landfill is composite lined.
NR 504.07(1)(c)(c) Any phases of an existing landfill which have been designed and constructed with a composite liner shall be designed and constructed with a final cover system meeting the requirements in subs. (2) to (9), except that the requirement for the geomembrane layer in sub. (5) does not apply to composite lined phases of existing landfills which have completed final cover placement by July 1, 1996.
NR 504.07(1)(d)(d) Landfills which accept papermill sludges or other industrial solid wastes with high water contents and low strength may propose alternate final cover systems if the strength of the waste mass will not allow for the construction of the cover system required in this section.
NR 504.07(2)(2)Grading layer. A minimum 6 inch thick grading layer shall be designed over the final waste elevation of landfills proposing to accept municipal solid waste to attain the required slope and provide for a stable base for subsequent system components. Daily and intermediate cover may be used for this purpose.
NR 504.07(3)(3)Support layer for low-strength wastes. A support layer shall be designed for stabilization, reinforcement and removal of leachate and gas over the final waste elevations for landfills which accept industrial solid wastes with high water contents and low strength.
NR 504.07(4)(4)Clay capping layer. A minimum 2 foot thick clay cap shall be designed to provide a low hydraulic conductivity barrier to percolation. Clay used for this layer shall meet the specifications in s. NR 504.06 (2) (a). The clay capping layer shall be constructed according to s. NR 504.06 (2) (f). Final cover systems that are required to include a geomembrane layer may be designed with the following alternatives to the clay component of the composite capping layer:
NR 504.07(4)(a)(a) The clay component of the capping layer may be replaced by a GCL overlying a minimum of 2 feet of soil barrier layer. This GCL layer and the soil barrier layer shall meet the following material and construction specifications:
NR 504.07(4)(a)1.1. The GCL shall consist of a layer of sodium bentonite clay encapsulated between 2 geotextiles.
NR 504.07(4)(a)2.2. The GCL shall be covered with a geomembrane the same day that it is unpacked and placed in position. The GCL may not be installed in standing water or during rain. The GCL shall be dry when installed and covered. A GCL exhibiting unconfined swelling shall be removed and replaced.
NR 504.07(4)(a)3.3. The GCL shall be installed in a relaxed condition and shall be free of tension or stress upon completion of the installation. The GCL may not be stretched to fit.
NR 504.07(4)(a)4.4. Adjoining panels of a GCL shall be laid with a minimum of 6 inches of overlap on the longitudinal seams and a minimum 20 inches of overlap on the panel end seams.
NR 504.07(4)(a)5.5. Irregular shapes, cuts or tears in the installed GCL shall be covered with a GCL patch that provides a minimum 12 inch overlap onto adjacent GCL surfaces.
NR 504.07(4)(a)6.6. A seal of loose bentonite granules shall be placed in seam overlaps at a minimum rate of one quarter pound per linear foot of seam for all panel end seams and longitudinal seams. The seal of loose bentonite may be deleted, with concurrence by the department, for longitudinal seams where the manufacturer has processed the overlap area to enhance sealing. The seal may not be deleted for any longitudinal seams that are transitions between construction phases.
NR 504.07(4)(a)7.7. Loose bentonite or bentonite amended soil shall be placed at all patches and penetrations.
NR 504.07(4)(a)8.8. GCL panels shall be certified needle-free through magnetic and metal detection tests.
NR 504.07(4)(a)9.9. The GCL shall be placed in direct contact with a soil barrier layer.
NR 504.07(4)(a)10.10. Vehicle traffic on the subgrade of the GCL and on the GCL shall be restricted to the minimum weight and number of machines needed to deploy the GCL and geomembrane. Vehicles shall be operated to minimize the formation of ruts and surface deformations and to prevent damage to the GCL and geomembrane. Deployment methods shall be selected to prevent any tearing or combing out of fibers of the GCL.
NR 504.07(4)(a)11.11. Soil cover placement over the geosynthetics shall be completed in the same construction season as the geosynthetic construction.