NR 208.05 NoteNote: Pond and lagoon leakage rates may be estimated using total influent and effluent flows or calculated by actual field water balance testing if approved by the department. The change in storage volume (+/-) for fill and draw pond systems, storage lagoons, and other similar type systems may be used in the leakage rate estimation if the method for determining the change in storage volume(s) is approved by the department.
NR 208.05(3)(i)(i) Biosolids quality and management. Point assignments shall be as follows:
- See PDF for table PDF
NR 208.05 NoteNote: The definitions of “High quality limit”, “Ceiling limit”, “Pathogen control limit”, and “Vector attraction reduction limit” may be found in ch. NR 204 — Domestic Sewage Sludge Management.
NR 208.05(3)(j)(j) Staffing and preventative maintenance. Point assignments shall be as follows:
- See PDF for table PDF
NR 208.05(3)(k)(k) Operator certification and education. Point assignments shall be as follows:
- See PDF for table PDF
NR 208.05 NoteNote: The definition of “Operator-In-Charge” may be found in ch. NR 114 — Certification Requirements For Wastewater Treatment Plant Operators.
NR 208.05(3)(L)(L) Financial management. Point assignments shall be as follows:
- See PDF for table PDF
NR 208.05 NoteNote: The definitions of “User Charge” and “Replacement” may be found in ch. NR 162 — Clean Water Fund.
NR 208.05(3)(m)(m) Sewage collection systems.
NR 208.05(3)(m)1.1. Point assignments shall be as follows:
- See PDF for table PDF
NR 208.05(3)(m)2.2. Owners of sewage collection systems shall record and maintain information about the operation and maintenance of their sewage collection system, which may include the following: cleaning, root removal, flow monitoring, smoke testing, sewer line televising, manhole inspections, lift station servicing, manhole rehabilitation, mainline rehabilitation, private sewer inspections, private sewer infiltration/inflow (I/I) removal, precipitation, sanitary sewer overflows, building or basement backups, lift station failures, sewer pipe failures, complaints, and any other collection system information deemed important by the owner.
NR 208.05 NoteNote: Sanitary sewer overflow occurrences and sewage treatment facility overflow occurrences are reported under s. NR 210.21 (4). Additional reporting requirements under this chapter are required under s. NR 208.06 (1) (b). The department may initiate enforcement action under s. 283.89, Stats., for any sanitary sewer overflow or sewage treatment facility overflow.
NR 208.05(3)(n)(n) Grading summary. The department shall provide to the owner a summary of section grades, response ranges and resultant grade point average for the applicable completed CMAR sections under s. NR 208.04 (5) (a) to (m).
NR 208.05(3)(o)(o) Resolution or owner statement. The owner shall provide to the department a resolution or owner statement of review and response. Public and private treatment works owners shall complete and submit the resolution or owner statement with the CMAR. No point assignments are associated with this CMAR section.
NR 208.05(4)(4)Calculation of cmar grade point average (gpa). A grade point average shall be determined for each wastewater treatment works required to submit a CMAR. The grade point average shall be calculated as follows: multiply the CMAR section grade points associated with the letter grades for each section as shown in table 1 by the corresponding section weighting factor provided in table 2; add the resulting values determined for all the sections; divide the value determined by the sum of all the weighting factors used in calculating the individual section values.
G.P.A. = Sum (section grade points x section weighting factor) Sum of the applicable section weighting factors
Table 2
CMAR Section Weighting Factors
- See PDF for table PDF
NR 208.05 HistoryHistory: CR 04-022: cr. Register November 2004 No. 587, eff. 1-1-05; CR 12-027: r. and recr. (3) (m) Register July 2013 No. 691, eff. 8-1-13.
NR 208.06NR 208.06CMAR review and responses.
NR 208.06(1)(1)Owner review.
NR 208.06(1)(a)(a) The owner of the wastewater treatment works shall review and complete all applicable CMAR sections. The owner submitting a CMAR under this chapter shall provide a response for individual CMAR sections when required pursuant to table 1 and this section.
NR 208.06(1)(b)(b) Sanitary sewer collection system owners shall review the total number of sanitary sewer overflow occurrences and sewage treatment facility overflow occurrences for the year as reported under s. NR 210.21 (4) and, if overflows are reported, provide a response of actions taken or underway to reduce or eliminate such occurrences in the future.